Keri Holdsworth
PFD Report
All Responded
Ref: 2015-0060
All 2 responses received
· Deadline: 15 Apr 2015
Coroner's Concerns (AI summary)
This junction is a recurring danger zone with a history of several serious and fatal incidents, specifically for vehicles making right turns to or from the northbound A19.
View full coroner's concerns
(1) This is the latest in several serious incidents at this junction, three of which have been fatal within the last five years. All of the fatal incidents have involved vehicles either turning right at this junction to join the northbound A19, or turning right from the northbound into the Dalton Piercy junction:
Responses
Action Planned
The Highways Agency has extended a route safety study to consider whether a bridge at Elwick could facilitate closure of central reserve gaps, including the Dalton Piercy junction. The study is due to report in August 2015. (AI summary)
The Highways Agency has extended a route safety study to consider whether a bridge at Elwick could facilitate closure of central reserve gaps, including the Dalton Piercy junction. The study is due to report in August 2015. (AI summary)
View full response
Dear Sir REGULATION 28 REPORT INQUEST INTO THE DEATH OF THE LATE KERI VICTORIA HOLDSWORTH refer to your letter of 28 February 2015 enclosing your Regulation 28 Report following your inquest into the death of Keri Holdsworth on 13 June 2014. You have requested in your report that the Highways Agency close the A19 Dalton Piercy junction to traffic wishing to turn right; and report to you what action the Highways Agency intends to take in this respect. Prior to the above accident the Highways Agency undertook a Route Safety Action Plan to identify locations on the A19 that display a poor accident record_ This highlighted the junctions at Elwick, a short distance north of the Dalton Piercy junction. Study work was initiated to look at what improvements could be made to the junction including the provision of a bridge and the closure of the central reserve gaps. Following the above accident the scope of this study was extended to consider whether the provision of a bridge at Elwick could facilitate the closure of some or all of the central reserve gaps, including the Dalton Piercy junction, along the section of the A19 between the A689 and A179 junctions. Hartlepool Borough Council are partner in this study The study is due to report in August 2015. Closure of any of the gaps, including the Dalton Piercy junction will be dependent on the outcome of the study which will consider whether there are viable alternative routes for right turning traffic and whether there is a strong business case for doing so. Construction of any subsequent scheme would be subject to availability of funds_
Noted
Hartlepool Borough Council clarifies that the relevant stretch of road falls under the jurisdiction of Highways England, but they are in dialogue with Highways England and will assist as required. (AI summary)
Hartlepool Borough Council clarifies that the relevant stretch of road falls under the jurisdiction of Highways England, but they are in dialogue with Highways England and will assist as required. (AI summary)
View full response
Dear Mr Donnelly INQUEST INTQ THE DEATH QE THE LATE KERLVICTORIA HOLDSWORTH Thank you for your letter dated the 17th April, 2015. My apologies if there has been any misunderstanding: The position is that this stretch of network falls under the jurisdiction of Highways England (formerly known as The Highways Agency): All responsibility for speed restrictions, layout design and potential scheme improvements lies with them and not with ourselves at Hartlepool Borough Council We are however in dialogue with Highways England and will assist in any associated external, third party issues that may arise through design briefs etc that are required. contacted Highways England (Highways Agency) upon receipt of your last 11 correspondence and asked them as lead body to respond on behalf of both ourselves and the Highways Agency, explaining the position in respect of potential studies being carried out to improve the safety of the network: AII funding responsibility for improvements to the A19 network lie with Highways England and therefore deems them to be the project sponsor and instigator of any improvement scheme(s) 0420 C W M Donnelly, The Coroners Service, Town Hall, Albert Road, Middlesbroughdocx road
2- further assistance, please do not the position, and if can be of any hope this clarifies or alternatively e-mail at hesitate to contact me ont
2- further assistance, please do not the position, and if can be of any hope this clarifies or alternatively e-mail at hesitate to contact me ont
Sent To
- Hartlepool Borough Council
- Highways Agency
Response Status
Linked responses
2 of 2
56-Day Deadline
15 Apr 2015
All responses received
About PFD responses
Organisations named in PFD reports must respond within 56 days explaining what actions they are taking.
Source: Courts and Tribunals Judiciary
Report Sections
Investigation and Inquest
On 14"h June 2014 | commenced an investigation into the death of Keri Victoria Holdsworth: The investigation concluded at the end of the inquest on 16"h February 2015. The conclusion of the inquest was accidental death, following a road traffic crash on the 13/h June 2014 wherein the deceased sustained fatal injuries_
Circumstances of the Death
On the 13/h June 2014 the deceased was involved in a road traffic crash at the junction of the A19 road and the road from Dalton Piercy village. She had been travelling northwards in the offside lane, and probably braked suddenly as a van in the central reservation was about to pull out and join the northbound carriageway: She lost control of her vehicle, crossed over the junction and collided almost head on with a southbound vehicle travelling in the offside southbound lane
Action Should Be Taken
In my opinion action should be taken to prevent future deaths and believe yoU [ANDIOR your organisation] have the power to take such action: The specific action is the closure of thejunction to traffic wishing_to turn right
Similar PFD Reports
Reports sharing organisations, categories, or themes
Related Inquiry Recommendations
Public inquiry recommendations addressing similar themes
Revise signal sighting standard to explicitly consider signal readability
Ladbroke Grove Inquiry
Hazardous road design
Define additional time required for reading gantry-mounted and complex signals
Ladbroke Grove Inquiry
Hazardous road design
Clarify "very short duration" definition within the signal sighting standard
Ladbroke Grove Inquiry
Hazardous road design
Identify and retrospectively review locations affected by "very short duration" ambiguity
Ladbroke Grove Inquiry
Hazardous road design
Clarify "overhead line equipment" in signal sighting standard to mean wires and droppers
Ladbroke Grove Inquiry
Hazardous road design
Define acceptable limits for temporary signal obscuration in sighting standards
Ladbroke Grove Inquiry
Hazardous road design
Explicitly define cab sight lines for signal positioning based on driver's eye
Ladbroke Grove Inquiry
Hazardous road design
Railtrack to conduct safety examination of Paddington station layout and operations.
Ladbroke Grove Inquiry
Hazardous road design
Data sourced from Courts and Tribunals Judiciary under the Open Government Licence.