Delivery No statement from Railtrack found

Recommendation LADB-46: Establish and apply criteria for signallers exceeding maximum 72-hour work week

From Ladbroke Grove Inquiry — Final Report, published 19 June 2001.

Recommendation

Railtrack management should set out the criteria for allowing signallers, in exceptional circumstances, to exceed the maximum of 72 hours of work per week, and ensure that these criteria are, and continue to be, correctly applied (para 12.19).

Jurisdiction: UK-wide

Government response

No government response to this recommendation is on the record yet.

Delivery

No statement on delivery from Railtrack has been found in the sources searched (last checked 27 February 2026). This is separate from the response above.

Source

Report Ladbroke Grove Inquiry — Final Report 19 Jun 2001

Responsible bodies

Railtrack Primary

Themes and tags

Recommendation made 25.4 years ago