Government response Not tracked (historical inquiry)
Delivery No statement from the addressee found

Recommendation 76: Immediate analysis without waiting for legislation

From The Public Inquiry into the Piper Alpha Disaster, published 12 November 1990.

Recommendation

The regulatory body should ask operators which have not already done so to undertake an evacuation, escape and rescue analysis forthwith, without waiting for legislation. The timetable for completion of this analysis should be agreed between the regulatory body and the industry but should not exceed a total of 12 months, and that only for operators of a large number of installations (para 20.9).

Jurisdiction: UK-wide
Page: 397
Reference: Recommendation 76

Government response

No government response to this recommendation is on the record yet.

Delivery

No statement on delivery from the addressee has been found in the sources searched (last checked 27 February 2026). This is separate from the response above.

Source

Report The Public Inquiry into the Piper Alpha Disaster 12 Nov 1990
Recommendation made 35.9 years ago