Government response Not tracked (historical inquiry)
Delivery No statement from the addressee found

Recommendation 15: Clarify RT/CE/S/103 inspections

From Formal Inquiry: Potters Bar derailment of 10 May 2002 — Final Report (RSSB FI2013/F), published 18 March 2005.

Recommendation

Network Rail Company Standard RT/CE/S/103 should be revised to clarify the following: • Paragraph 4.4 as to how often track gauge in S&C is to be measured and by whom (ie basic inspector, supervisor or track engineer). • Paragraph 8.1.2 as to how often toe and heel openings are to be checked and by whom (ie basic inspector, supervisor or track engineer). • Paragraph 8.1.2 to prescribe where toe and heel opening should be measured in relation to the cross-section of the rails.

Jurisdiction: UK-wide
Page: 152
Reference: 5.12

Government response

No government response to this recommendation is on the record yet.

Delivery

No statement on delivery from the addressee has been found in the sources searched (last checked 27 February 2026). This is separate from the response above.

Source

Report Formal Inquiry: Potters Bar derailment of 10 May 2002 — Final Report (RSSB FI2013/F) 18 Mar 2005
Recommendation made 21.6 years ago