22. Our ‘Principles of Good Administration’ say organisations should deal with people quickly, within reasonable timescales and within any published time limits. They should tell people if things take longer than stated or than can reasonably be expected to take.
23. Our ‘Principles of Good Administration’ also say organisations should provide effective services. They say where organisations are subject to published service standards they should plan and prioritise their resources to meet them.
24. IAS says it aims to assess applicants within 40 working days. This means it should have visited Ms O by 14 August. Instead, it took 81 working days to complete the assessment. This fell far short of the published timescale.
25. We asked IAS to explain what caused the delay, as we understand sometimes circumstances mean things go wrong completely unavoidably. We also asked it what action it took at the time to try and avoid or lessen the delay (including explaining the reasons to Ms O), and what action it had taken since to prevent the same problem happening again.
26. IAS tells us the reasons for the delay were outside its control and it did act to reduce the wait. We have considered these reasons before deciding if the delay amounted to a failing or not.
27. IAS explained that, when Ms O needed her assessment, it had difficulty with its staffing levels. This was due to a high rate of staff sickness and resignations. We completely accept staffing can be a challenge to any organisation. What is important in this instance is what was done to try and correct the problem.
28. When IAS explained this to Ms O’s MP in the complaint process, it said, ‘We do whatever we can to limit such impacts - for example, by moving staff from other areas, but it is not always possible to mitigate them entirely. It was such a staffing challenge that resulted in the delay in this instance.’ It said the delay was not due to maladministration (fault), but unavoidable events beyond its control.
29. IAS tells us that, at the time, it offered overtime to existing staff. It did not tell us what the uptake was for that offer or how it had any bearing on its provision of home assessments. It also tells us it is constantly recruiting assessment staff to fill vacancies as they come up. It also says training staff takes time, which means recruitment does not immediately fix delays. We recognise this, and accept there can be a lag between a staffing shortage happening and being corrected and thought carefully about this issue before reaching our final decision.
30. ICE investigated what happened and agreed the delay happened due to events beyond IAS’s control. It said the delay was unfortunate but not excessive and was not caused by maladministration. It concluded Ms O’s complaint was ‘justified’ but made no recommendations to put things right.
31. We recognise IAS took steps to reduce the delay by moving staff, offering them overtime and recruiting more people. However, these actions did not go far enough to prevent the significant delay Ms O experienced. We have seen no evidence of what it actually did, how it planned for the staffing shortage or the impact its actions had at the time. Despite the steps it says it took, the service IAS provided was not effective.
32. For these reasons we have taken a different view to ICE and decided the additional 41 working days Ms O had to wait were excessive. The failure to assess Ms O in a timely manner fell far short of providing an effective service and amounts to a failing.
33. Further, we cannot ignore how important this assessment was for Ms O. She was not simply waiting for a complaint response or reply to a letter. Instead, Ms O needed the appointment to prove her eligibility for money that would help her manage a sudden and profound disability. The matter was of potentially life-changing importance to her.
34. We also cannot ignore what IAS said to us during our investigation of this complaint. It told us, ‘Indeed, Ms O could have requested a face-to-face assessment at a consultation centre rather than waiting for a home visit, which would have reduced her waiting time, potentially within the 40 working day period, thereby removing the circumstances that resulted in the complaint.’
35. We strongly disagree and had serious concerns about this comment. The point of the home assessment is that some people, such as Ms O, simply cannot attend an assessment centre. Those comments caused us concern as they imply IAS is not taking the need for home assessments as seriously as it should.
36. Having seen evidence of a failing, we looked at the impacts Ms O has associated with IAS’s actions. She says, because of what happened, she: • waited longer than she should have done to start receiving her PIP payments • borrowed money to pay for treatment and adapt her home, which meant she went into debt and • experienced a lot of stress.
37. We have considered these impacts in turn.
38. DWP needed the IAS assessment before it could confirm Ms O’s eligibility for PIP and start paying it. As DWP did not have the necessary information it significantly delayed paying PIP to Ms O. This meant Ms O was receiving the lower DLA amount when her health meant she was eligible for the higher rate of PIP and associated mobility element.
39. If IAS had kept to its agreed timescale, it would have visited Ms O on 14 August at the latest. There is no sign Ms O’s condition changed during this time, which means we are confident she would have been eligible for PIP had it done so. However, the time it took IAS to visit her resulted in an eight-week delay to DWP approving her PIP.
40. Ms O received £122.70 more per week on PIP than when she was on DLA. Due to the additional eight weeks she had to wait, she is £981.60 worse off.
41. We have also spoken to Mr Y about the debt Ms O entered to better understand how this came about.
42. He explained Ms O relied on loans from family and friends to purchase a powered wheelchair that allowed her to continue being mobile. She also needed private physiotherapy sessions to help manage the symptoms of her stroke.
43. He says that, if she was in receipt of PIP sooner, she could have applied to the Motability Scheme to cover the cost of her wheelchair. The Motability Scheme is a programme endorsed by DWP that allows people in receipt of PIP or DLA to exchange their mobility element for leasing certain means of transport, including things like a powered wheelchair.
44. Ms O took receipt of a powered wheelchair on 7 June 2018. This cost £890. She bought it using loans from family and friends as she could not afford to buy it herself. We know how important this powered wheelchair is for Ms O’s quality of life and understand how quickly she needed it.
45. When considering if IAS’s actions meant Ms O entered debt, we can see she bought the wheelchair two weeks after making her PIP application. Even if IAS had met its published timescales, she would not have been receiving PIP at this time. In fact, DWP had not sent the referral to IAS by that point.
46. Further, there was the possibility Ms O could have rented a wheelchair until her PIP was awarded. She could have then applied to the Motability Scheme, which might have covered the cost her the chair. We recognise Ms O had to borrow money in this instance. However, this happened regardless of the delay at IAS, so we cannot say the delay resulted in Ms O taking on this part of the debt.
47. Ms O also attended three private physiotherapy sessions between 24 August and 18 October 2018. These appointments cost £70 each. Mr Y explained the appointments helped to manage the symptoms of Ms O’s stroke. But, had she had the PIP, she could have paid the £210 out of that. As we have recommended DWP pay her the PIP she missed out on, this money will settle the cost of the private physiotherapy.
48. Additionally, Ms O borrowed the money from family and friends. This means there was no cost for borrowing the money like there would be for spending on a credit card. As such, we cannot see any extra financial impact here. If this money has not been paid back, it can presumably be done so from the recommended payments discussed below.
49. Mr Y also says Ms O found it difficult and distressing to borrow money. We do not doubt this, and we agree the long wait Ms O experienced was very worrying for her. It must have been incredibly upsetting to have to borrow money through no fault of her own. We agree this has understandably been a source of frustration and upset for Ms O while she attempted to put right what happened.
50. We have looked at what IAS and DWP have done to put right the financial loss and emotional impact that resulted from what happened.
51. IAS’s complaint responses to Ms O sincerely apologise for the impact she has experienced due to the delays. However, it has declined to pay compensation to Ms O as it says it followed the relevant processes in trying to arrange a visit to her. It explained it could not reimburse her missed benefits and told her to speak to DWP to try and recover the money. When she did so, DWP told her she had missed out on payments ‘as a result of maladministration by the Assessment Provider’. It therefore chose not to pay her any additional money.
52. Ms O remains underpaid because DWP would have paid her additional PIP if the appointment had happened when it was supposed to. The apology from IAS does not go far enough to put right her individual experience, and the impacts she has experienced are unresolved.