31
The IPA should review the data that it publishes in its Major Project Annual Report,...
Recommendation
The IPA should review the data that it publishes in its Major Project Annual Report, and this should be extended at least to add timelines of project approvals and estimates.
Paragraph Reference
128
Government Response
Acknowledged
Government Response
Acknowledged
HM Government
Acknowledged
The UK Government publishes significant detail and data on the government’s major project portfolio. As part of the annual report the IPA publishes specific information on all GMPP projects4 including, departmental narratives on the whole life costs, schedules (including any deviations from the planned schedule) and delivery confidence assessment’s over time. The IPA also publishes a list with the names of Senior Responsible Owners (SROs) for the Government Major Projects Portfolio (GMPP).5Government recognises that increased transparency of data about major projects would be beneficial for tracking progress of major projects, the IPA will review this proposal and consider whether this information can be added to the annual report.
Source
Report
Third Report - Delivering the Government’s infrastructure commitments through major projects
28 Jul 2020
HC 125
Timeline
Recommendation age
5.8 yrs
Report published
28 Jul 2020