A mechanism should be developed to allow small energy generation projects to defer and spread...

Conclusion
A mechanism should be developed to allow small energy generation projects to defer and spread grid connection payments over time.
Government Response Summary
The government indicates that the connections framework overseen by Ofgem and DNOs already allows for instalment payments in appropriate circumstances.
Paragraph Reference
75
Government Response
Accepted
HM Government Accepted
As part of the connections framework overseen by Ofgem, DNOs require payments from connection customers upfront, in advance of the connection being made. This protects electricity billpayers who would otherwise be liable for the costs incurred by the DNO should the connection customer abandon the project. However, within this framework DNOs do allow connection customers to pay by instalments, where appropriate.
Addressee Bodies
Wales Office
Timeline
Recommendation age 3.6 yrs
Report published 21 Oct 2022