12
Accepted
A mechanism should be developed to allow small energy generation projects to defer and spread...
Conclusion
A mechanism should be developed to allow small energy generation projects to defer and spread grid connection payments over time.
Government Response Summary
The government indicates that the connections framework overseen by Ofgem and DNOs already allows for instalment payments in appropriate circumstances.
Paragraph Reference
75
Government Response
Accepted
Government Response
Accepted
HM Government
Accepted
As part of the connections framework overseen by Ofgem, DNOs require payments from connection customers upfront, in advance of the connection being made. This protects electricity billpayers who would otherwise be liable for the costs incurred by the DNO should the connection customer abandon the project. However, within this framework DNOs do allow connection customers to pay by instalments, where appropriate.
Source
Committee
Welsh Affairs Committee
Inquiry
Grid capacity in Wales
Report
First Report - Grid Capacity in Wales
21 Oct 2022
HC 218
Addressee Bodies
Wales Office
Timeline
Recommendation age
3.6 yrs
Report published
21 Oct 2022