Defence Equipment Plan 2020-2030

Public Accounts Committee Closed Inquiry
Opened: 21 Dec 2020 Closed: 17 May 2021 Parliament page
The Ministry of Defence (MoD) publishes a ten-year Equipment Plan report every year, setting out intended investment on equipment and support projects over the next 10 years. It assesses whether this is affordable within its future budget. The Plan includes equipment already in use, such as the Lightning II jets, … Read more
27 Conclusions
1 Report
1 Oral session
3 Letters
1 Event
Oral evidence sessions 1 session
Defence Equipment Plan 2020-2030
Air Marshall Richard Knighton · Ministry of Defence Charlie Pate · Ministry of Defence Sir Simon Bollom · Ministry of Defence Stephen Lovegrove · Ministry of Defence
Recommendations & Conclusions
27 results
2 Conclusion
Fiftieth Report - Defence Equipmen…
Because of the repeated delays to the publication of the Integrated Review of Security, Defence,...
Because of the repeated delays to the publication of the Integrated Review of Security, Defence, Development and Foreign Policy, the Department was not able to provide details of how it proposes to use the £16.5 billion additional defence funding, or … Read more
Government Response
2.1 The government agrees with the Committee’s recommendation. Target implementation date: June 2021 2.2 Following the publication of the Integrated Review on 16 March 2021, the MOD published a summary … Read more
HM Treasury
View details
3 Conclusion
Fiftieth Report - Defence Equipmen…
The Department’s failure to break the cycle of short-term financial management is preventing it from...
The Department’s failure to break the cycle of short-term financial management is preventing it from developing essential military capabilities in ways that achieve value for money and is restricting its ability to respond to new opportunities or threats. The Department’s … Read more
Government Response
3.1 The government agrees with the Committee’s recommendation. Target implementation date: Autumn 2021 3.2 Alongside the Equipment Plan 2021, the department will write to the Committee, outlining the key principles … Read more
HM Treasury
View details
4 Conclusion
Fiftieth Report - Defence Equipmen…
The Defence equipment programme is routinely jeopardised by factors that drive inflation in defence projects.
The Defence equipment programme is routinely jeopardised by factors that drive inflation in defence projects. Defence projects are often long-term, complex and involve new technologies, which makes them vulnerable to cost inflation. This Committee has highlighted that inflation in equipment … Read more
Government Response
4.1 The government agrees with the Committee’s recommendation. Target implementation date: Autumn 2021 4.2 The department will write to the Committee alongside the department’s annual Equipment Plan report which will … Read more
HM Treasury
View details
5 Conclusion
Fiftieth Report - Defence Equipmen…
The Department has not established a reliable and sophisticated approach to estimating the cost of...
The Department has not established a reliable and sophisticated approach to estimating the cost of its future equipment programme, including setting realistic efficiency savings. The Department acknowledges the risk of costs escalating on its equipment projects, which are often large, … Read more
Government Response
5.1 The government agrees with the Committee’s recommendation. Target implementation date: Autumn 2021 5.2 The next Equipment Plan report will explain the improvements made to assess risk in long-term projects … Read more
HM Treasury
View details
6 Conclusion
Fiftieth Report - Defence Equipmen…
The Department does not have all the necessary arrangements or qualified staff in place to...
The Department does not have all the necessary arrangements or qualified staff in place to provide assurance that its Equipment Plan is reliable and has been subject to rigorous quality assurance. The Department has made some improvements to its production … Read more
Government Response
6. 1 The government agrees with the Committee’s recommendation. Target implementation date: March 2023 6.2 Strengthening the financial capabilities within the department is a key part of the department’s Finance … Read more
HM Treasury
View details
1 Conclusion
Fiftieth Report - Defence Equipmen…
On the basis of a report by the Comptroller and Auditor General, we took evidence...
On the basis of a report by the Comptroller and Auditor General, we took evidence from the Ministry of Defence on the Equipment Plan 2020–2030.1
Government Response
1.1 The government agrees with the Committee’s recommendation. Target implementation date: Autumn 2021 1.2 On 19 November 2020, the Prime Minister announced an increase in defence spending which will mean … Read more
HM Treasury
View details
7 Conclusion
Fiftieth Report - Defence Equipmen…
In our report on the Equipment Plan 2019–2029, we expressed our concern that the Department...
In our report on the Equipment Plan 2019–2029, we expressed our concern that the Department had still not established an affordable long-term investment programme in military equipment and had missed opportunities to take the necessary difficult decisions to develop an … Read more
Government Response
1.1 The government agrees with the Committee’s recommendation. Target implementation date: Autumn 2021 1.2 On 19 November 2020, the Prime Minister announced an increase in defence spending which will mean … Read more
HM Treasury
View details
8 Conclusion
Fiftieth Report - Defence Equipmen…
When asked if the financial problems with the Defence budget were ever likely to change,...
When asked if the financial problems with the Defence budget were ever likely to change, the Permanent Secretary pointed first to the Department not having a very good understanding of the drivers of inflation with defence projects. Second, and in … Read more
Government Response
4.1 The government agrees with the Committee’s recommendation. Target implementation date: Autumn 2021 4.2 The department will write to the Committee alongside the department’s annual Equipment Plan report which will … Read more
HM Treasury
View details
9 Conclusion
Fiftieth Report - Defence Equipmen…
The Permanent Secretary also explained that the Department has had to live with an annual...
The Permanent Secretary also explained that the Department has had to live with an annual budget cycle and plan its equipment programme without the certainty of funding over a 10-year period. He explained that this was very difficult to manage. … Read more
Government Response
3.1 The government agrees with the Committee’s recommendation. Target implementation date: Autumn 2021 3.2 Alongside the Equipment Plan 2021, the department will write to the Committee, outlining the key principles … Read more
HM Treasury
View details
10 Conclusion
Fiftieth Report - Defence Equipmen…
The Department acknowledged the risk of costs escalating on its biggest programmes— nuclear submarines and...
The Department acknowledged the risk of costs escalating on its biggest programmes— nuclear submarines and IT and communications systems—which are large, complex programmes involving the development of new technologies.19 It told us it assesses the risk of cost increases on … Read more
Government Response
5.1 The government agrees with the Committee’s recommendation. Target implementation date: Autumn 2021 5.2 The next Equipment Plan report will explain the improvements made to assess risk in long-term projects … Read more
HM Treasury
View details
11 Conclusion
Fiftieth Report - Defence Equipmen…
The Department acknowledged that its equipment projects are subject to uncertainties that affect their delivery...
The Department acknowledged that its equipment projects are subject to uncertainties that affect their delivery and cost. It is responsible for managing the risk of cost increases within its annual budget. For example, as approximately 15% of the Plan’s forecast … Read more
Government Response
5.1 The government agrees with the Committee’s recommendation. Target implementation date: Autumn 2021 5.2 The next Equipment Plan report will explain the improvements made to assess risk in long-term projects … Read more
HM Treasury
View details
12 Conclusion
Fiftieth Report - Defence Equipmen…
The Department’s adjustments to its cost estimates are still over-optimistic, including its assessment of the...
The Department’s adjustments to its cost estimates are still over-optimistic, including its assessment of the level of potential efficiency savings.26 We have previously raised our concerns that the Department was including efficiency savings that it was not confident of 17 … Read more
Government Response
5.1 The government agrees with the Committee’s recommendation. Target implementation date: Autumn 2021 5.2 The next Equipment Plan report will explain the improvements made to assess risk in long-term projects … Read more
HM Treasury
View details
13 Conclusion
Fiftieth Report - Defence Equipmen…
The Department acknowledged that its plans for achieving efficiency savings—which are based on thousands of...
The Department acknowledged that its plans for achieving efficiency savings—which are based on thousands of initiatives on equipment projects—did not always deliver the expected returns. It told us that it has introduced more rigorous scrutiny of savings proposals to help … Read more
Government Response
5.1 The government agrees with the Committee’s recommendation. Target implementation date: Autumn 2021 5.2 The next Equipment Plan report will explain the improvements made to assess risk in long-term projects … Read more
HM Treasury
View details
14 Conclusion
Fiftieth Report - Defence Equipmen…
We have previously recommended that the Department should improve its financial skills and asked what...
We have previously recommended that the Department should improve its financial skills and asked what progress had been made.34 The Department had not increased the number of professionally qualified finance staff, and said it was unhappy that the proportion of … Read more
Government Response
6. 1 The government agrees with the Committee’s recommendation. Target implementation date: March 2023 6.2 Strengthening the financial capabilities within the department is a key part of the department’s Finance … Read more
HM Treasury
View details
15 Conclusion
Fiftieth Report - Defence Equipmen…
The Department admitted that its Head Office was not providing sufficient challenge on the financial...
The Department admitted that its Head Office was not providing sufficient challenge on the financial judgements made by the TLBs when compiling the Equipment Plan.37 Because of the way the Department is organised under the delegated model, Head Office cannot … Read more
Government Response
6. 1 The government agrees with the Committee’s recommendation. Target implementation date: March 2023 6.2 Strengthening the financial capabilities within the department is a key part of the department’s Finance … Read more
HM Treasury
View details
16 Conclusion
Fiftieth Report - Defence Equipmen…
The Department claimed it has fulfilled previous Committee recommendations, albeit that it accepted that some...
The Department claimed it has fulfilled previous Committee recommendations, albeit that it accepted that some improvements were on-going.42 The National Audit Office has found that the Department has made improvements to its analysis and reporting, for example improving the presentation … Read more
Government Response
6. 1 The government agrees with the Committee’s recommendation. Target implementation date: March 2023 6.2 Strengthening the financial capabilities within the department is a key part of the department’s Finance … Read more
HM Treasury
View details
17 Conclusion
Fiftieth Report - Defence Equipmen…
In November 2020, the government announced that it would provide an additional £16.5 billion of...
In November 2020, the government announced that it would provide an additional £16.5 billion of funding over the next four years, which represents a 10% increase in the defence budget over this period.45 The Department said that HM Treasury has … Read more
Government Response
1.2 On 19 November 2020, the Prime Minister announced an increase in defence spending which will mean £188 billion will be spent on defence over the following four years – … Read more
HM Treasury
View details
18 Conclusion
Fiftieth Report - Defence Equipmen…
We have repeatedly urged the Department to take the difficult investment decisions needed to develop...
We have repeatedly urged the Department to take the difficult investment decisions needed to develop a balanced investment programme, highlighting missed opportunities to address fundamental weaknesses in its management of the Equipment Plan.48 The Department acknowledged that the lack of … Read more
Government Response
3.1 The government agrees with the Committee’s recommendation. Target implementation date: Autumn 2021 3.2 Alongside the Equipment Plan 2021, the department will write to the Committee, outlining the key principles … Read more
HM Treasury
View details
19 Conclusion
Fiftieth Report - Defence Equipmen…
The Department could not provide us with a detailed explanation of how it planned to...
The Department could not provide us with a detailed explanation of how it planned to use the additional £16.5 billion of funding as ministers have yet to finalise decisions.51 Given that the 2020–2030 Equipment Plan is unaffordable, it accepted that … Read more
Government Response
2.1 The government agrees with the Committee’s recommendation. Target implementation date: June 2021 2.2 Following the publication of the Integrated Review on 16 March 2021, the MOD published a summary … Read more
HM Treasury
View details
20 Conclusion
Fiftieth Report - Defence Equipmen…
The Department confirmed that the Integrated Review—which had not been published at the time we...
The Department confirmed that the Integrated Review—which had not been published at the time we took evidence—would contain substantially different capability choices from the current Equipment Plan.55 The government intends that the additional funding will be invested in capability enhancements … Read more
Government Response
2.1 The government agrees with the Committee’s recommendation. Target implementation date: June 2021 2.2 Following the publication of the Integrated Review on 16 March 2021, the MOD published a summary … Read more
HM Treasury
View details
21 Conclusion
Fiftieth Report - Defence Equipmen…
The Department assured us that it has been closely involved in the Integrated Review and...
The Department assured us that it has been closely involved in the Integrated Review and it had a clear view on the priorities and roles that Defence would need to play in the future. It highlighted the increasing threat from … Read more
Government Response
2.2 Following the publication of the Integrated Review on 16 March 2021, the MOD published a summary of key spending and investment decisions in the Defence Command Paper, ‘Defence in … Read more
HM Treasury
View details
22 Conclusion
Fiftieth Report - Defence Equipmen…
We are concerned that the Department has no flexibility in its 2020–2030 Equipment Plan budget,...
We are concerned that the Department has no flexibility in its 2020–2030 Equipment Plan budget, which limits its ability to respond quickly to new or emerging threats.63 The National Audit Office report showed that the Department has only made provision … Read more
Government Response
3.3 Since the Committee's report, the department published the Defence Command Paper which sets out new policy aims and the capability decisions that were underpinned by the additional £16.5 billion … Read more
HM Treasury
View details
23 Conclusion
Fiftieth Report - Defence Equipmen…
The Department also needs ‘headroom’ in its budget to keep up with the pace of...
The Department also needs ‘headroom’ in its budget to keep up with the pace of change on new technologies.66 It is therefore assessing how much contingency is appropriate for both the nuclear programme and more conventional equipment projects in the … Read more
Government Response
3.3 Since the Committee's report, the department published the Defence Command Paper which sets out new policy aims and the capability decisions that were underpinned by the additional £16.5 billion … Read more
HM Treasury
View details
24 Conclusion
Fiftieth Report - Defence Equipmen…
We remain extremely concerned that the Department continues to manage a long- term spending programme...
We remain extremely concerned that the Department continues to manage a long- term spending programme on a year-by-year, cash-limited budget.69 Faced with funding shortfalls, the Department took a range of measures to balance its 2020–21 budget, including introducing commitment levels … Read more
Government Response
3.3 Since the Committee's report, the department published the Defence Command Paper which sets out new policy aims and the capability decisions that were underpinned by the additional £16.5 billion … Read more
HM Treasury
View details
25 Conclusion
Fiftieth Report - Defence Equipmen…
The National Audit Office has also reported that the Department’s continued focus on living within...
The National Audit Office has also reported that the Department’s continued focus on living within its in-year budget is affecting its ability to develop the military capabilities that are needed.72 The commands undertook yet another re-prioritisation exercise to balance the … Read more
Government Response
3.3 Since the Committee's report, the department published the Defence Command Paper which sets out new policy aims and the capability decisions that were underpinned by the additional £16.5 billion … Read more
HM Treasury
View details
26 Conclusion
Fiftieth Report - Defence Equipmen…
Faced with an unaffordable programme, we questioned the Department’s ability to achieve value for money...
Faced with an unaffordable programme, we questioned the Department’s ability to achieve value for money from its equipment expenditure. We have seen many examples of the Department not buying the quantity of kit or the number of capabilities that it … Read more
Government Response
3.3 Since the Committee's report, the department published the Defence Command Paper which sets out new policy aims and the capability decisions that were underpinned by the additional £16.5 billion … Read more
HM Treasury
View details
27 Conclusion
Fiftieth Report - Defence Equipmen…
While pointing out that this was also a problem encountered by other countries, the Department...
While pointing out that this was also a problem encountered by other countries, the Department acknowledged that it did not have a good understanding of the unique factors that drive inflation on defence projects, and that there was work to … Read more
Government Response
4.1 The government agrees with the Committee’s recommendation. Target implementation date: Autumn 2021 4.2 The department will write to the Committee alongside the department’s annual Equipment Plan report which will … Read more
HM Treasury
View details
Correspondence 3 letters
29 Jun 2021 Correspondence from David Williams, Permanent Secretary, Ministry of Defence, re follow up to 4th February PAC oral evidence session: Defence Equipment Plan 2020-2030, dated 22 June 2021
Parliament page
1 Mar 2021 Correspondence from Sir Stephen Lovegrove, Permanent Secretary, Ministry of Defence, re Follow up questions to PAC hearing on 4 February, dated 26 February 2021
Parliament page
18 Jan 2021 Correspondence from Sir Stephen Lovegrove, Permanent Secretary, Ministry of Defence, re EQUIPMENT PLAN 2020-2030: UPDATE ON AFFORDABILITY, dated 12 January 2021
Parliament page