The Department and the APHA set out how the Weybridge redevelopment programme will provide the...
Conclusion
The Department and the APHA set out how the Weybridge redevelopment programme will provide the flexible laboratory facilities to improve the UK’s resilience to animal diseases in the long-term.35 However, it also recognised that it needs to mitigate the risks of a major breakdown at the Weybridge site until the redevelopment is completed over the next 15 years. The Department set out a number of actions it is taking. It has put in place a critical works ‘patch and repair’ programme to increase resilience at the site including the incinerator development works. This critical works programme has a planned investment of £250 million between 2015 and 2025. The Department is also increasing the number of staff to manage the site including bringing in more specialist engineering expertise. The Department said it currently has 23 staff managing the site and is looking to increase that to 46 over the next year. It also said that it is replacing the current facilities management contract with a new contract in 2024 which will properly take account of the specific requirements of the Weybridge site.36 34 Qq 8, 19, 22 35 Qq 3–5 36 Qq 3–4, 15, 18, 58 14 Redevelopment of Defra’s animal health infrastructure 2 Investing in the Weybridge site Existing laboratory capacity at the Weybridge site
Government Response Summary
The government agrees with the committee’s conclusion, committing to regular reviews of comprehensive business continuity plans, finalizing the Weybridge Development Control Plan by early 2023, conducting critical incident exercises, and developing a more detailed understanding of site vulnerabilities.
Government Response
Accepted
Government Response
Accepted
HM Government
Accepted
3.1 The government agrees with the Committee’s recommendation. Target implementation date: June 2023 3.2 The department and APHA have comprehensive business continuity plans which seek to mitigate and minimise the risk inherent in the aging facilities. These plans are regularly reviewed and will be next reviewed once the Weybridge Development Control Plan (WDCP) is finalised in early 2023. 3.3 In addition to business continuity planning, the agency and department run regular critical incident exercises to test business response and readiness for a wide variety of scenarios from fire through power and water supply interruptions and potential loss of facilities. 3.4 The agency is in the process of developing a more detailed understanding of the vulnerabilities at Weybridge site (as distinct from facility condition). This work will identify if and how capabilities can be delivered from alternate locations or facilities. The Weybridge facility and the science that takes place there – and across the country – acts as a strong mitigating factor that controls and reduces the threat to the public and the environment. 3.5 The government is already in conversation with other cross government laboratories and partners to identify opportunities to co-ordinate, utilise or support each other in the face of UK wide critical events, multiple events such as coincident animal disease outbreaks, cascade events, new and exotic zoonotic threats and pandemics and so on. 3.6 The agency also partners to undertake cross-government animal, zoonotic and public health emergency exercises every six months, the next of which is planned in 2023.
Source
Committee
Public Accounts Committee
Report
Twenty-Fourth Report - Redevelopment of Defra’s animal health infrastructure
16 Nov 2022
HC 42
Addressee Bodies
HM Treasury
Timeline
Recommendation age
3.7 yrs
Report published
16 Nov 2022