The Sponsor Body told us it has not estimated the costs associated with dissolving itself,...

Recommendation
The Sponsor Body told us it has not estimated the costs associated with dissolving itself, which will depend on what the changes to the governance arrangements and proposed work look like. Depending on their grade, its staff have notice periods of between three and 12 months.35 The independent expert review reported that making structural changes to major programmes, such as revising governance, often introduced new risks. Care needed to be taken to avoid decisions simply compounding issues that already existed.36 Changing the Programme’s governance
Government Response

A response document is linked to this report, dated 2 September 2022. Response attribution to this conclusion has not been verified. Read the response document.

Addressee Bodies
HM Treasury
Timeline
Recommendation age 4.2 yrs