25
Deferred
We wrote to the Department and HM Treasury number of times (see Annex 1) after...
Conclusion
We wrote to the Department and HM Treasury number of times (see Annex 1) after our evidence session and asked it to clarify what it had agreed with EDFE in terms of the land and buildings that will be transferred to the NDA, and how it planned to resolve any issues or disagreements between what will be transferred. Both departments responded and told us that a suite of legal agreements had been put in place which provided a framework for the transfer of assets and resources when sites were being decommissioned. They also explained that, in practice, the land required for decommissioning will be determined on a site-by-site basis, reflecting technical, operational, and regulatory requirements. We were told that joint planning work between EDFE, Magnox Ltd and NDA was underway to identify, prioritise and address matters relating to station transfer, and that this was “progressing towards a detailed joint plan for transfer starting with Hunterston B by the end of the year”. Further, if disputes were to arise in any of these areas, legally binding resolution procedures, as set out in the legal agreements governing the transfer, would come into force as well as governance and escalation forums if required.42
Government Response Summary
The department requests a revised implementation date of May 2023 for the delivery of detailed transfer plans for AGR stations, starting with Hunterston B, and proposes sharing the Hunterston B plan with the Committee when completed, along with a summary of progress for the remaining stations.
Government Response
Deferred
Government Response
Deferred
HM Government
Deferred
6.2 EDF and NDA are currently working together to deliver detailed transfer plans for the AGR stations, starting with Hunterston B, with an anticipated delivery date of May 2023. Accordingly, the department would request a revised implementation date for this recommendation of May 2023. 6.3 A sufficiently detailed transfer plan for Hunterston B will be available in May 2023, but necessary work will need to take place to support detailed transfer plans for the subsequent stations, which will be completed in the years thereafter. The department proposes sharing the detailed Hunterston B plan with the Committee when completed, with a summary of progress of plans for the remaining stations at that time.
Source
Committee
Public Accounts Committee
Report
Third Report - The future of the Advanced Gas-cooled Reactors
20 May 2022
HC 118
Addressee Bodies
HM Treasury
Timeline
Recommendation age
4.0 yrs
Report published
20 May 2022