As a result, the Department awarded the contract to ICF, accepting it’s accelerated timetable for...
Conclusion
As a result, the Department awarded the contract to ICF, accepting it’s accelerated timetable for completion, whilst also putting in place a manual processing facility as a contingency in case the timetable overran.74 ICF subsequently struggled to implement the required voucher application system, meaning that greater amounts of manual processing were needed for voucher applications. This contributed to the delays that homeowners and installers faced in engaging with the Scheme.75
Government Response
A response document is linked to this report, dated 1 March 2022. Response attribution to this conclusion has not been verified. Read the response document.
Source
Committee
Public Accounts Committee
Report
Twenty-Seventh Report - Green Homes Grant Voucher Scheme
01 Dec 2021
HC 635