11 Not Addressed

From 3 March, in response to the anticipated shortage of ventilators, the Department began to...

Conclusion
From 3 March, in response to the anticipated shortage of ventilators, the Department began to purchase as many ventilators as it could using existing NHS supply chain framework agreements, which are designed to ensure competitive pricing. It explained that as part of these initial efforts, it discussed the possibility of speeding up the manufacture of devices available through the framework, but found that this was not possible as the devices are normally built at the point of order and have complex supply chains. By 12 March the Department had managed to order an additional 2,400 mechanical ventilators. However, it recognised that this still left a ‘huge deficit’ in terms of what it thought would be needed.17
Government Response Summary
The government reiterated that most devices were purchased through standard framework agreements with due diligence, without addressing the committee's observations on the challenges of increasing manufacturing speed or the initial 'huge deficit' in supply.
Government Response
Not Addressed
HM Government Not Addressed
3.2 The majority of devices purchased during this period were through framework agreements where NHS standard procurement processes had been followed. These include usual full due diligence checks.
Addressee Bodies
HM Treasury
Timeline
Recommendation age 5.7 yrs
Report published 25 Nov 2020