14 Deferred

The Sponsor Body told us that there is currently no clarity “about whether some, all...

Recommendation
The Sponsor Body told us that there is currently no clarity “about whether some, all or none of [the NEP] comes across to the Sponsor Body” and if it does, at what stage of the Programme.33 It is vital that the independencies between projects are managed effectively in order for Restoration and Renewal to be completed on time and to budget. We have seen with Crossrail the risks inherent in managing the interfaces between multiple time- critical projects.34
Government Response Summary
The government states that the Sponsor Body is not a government body and will provide responses directly to the Committee.
Government Response
Deferred
HM Government Deferred
Responses to the Committee The Sponsor Body is not a government body so will provide responses to the recommendations in the PAC report directly to the Committee.
Addressee Bodies
HM Treasury
Timeline
Recommendation age 5.8 yrs
Report published 05 Oct 2020