23
The Sponsor Body has not finalised its overarching engagement strategy and has yet to develop...
Conclusion
The Sponsor Body has not finalised its overarching engagement strategy and has yet to develop a plan of how it will engage with members of the public on the Programme. The Palace of Westminster is a UNESCO World Heritage Site, a symbol of British 45 C&AG’s Report, para 9 46 Update on possible relocation of parliamentary functions, Parliamentary website, 19 August 2020 47 C&AG’s Report, figure 6 48 Q 7 49 Q 24 50 Q 38 51 Q 64 Restoration and renewal of the Palace of Westminster 15 Parliamentary democracy, and receives over one million visitors in a typical year.52 The British public is ultimately footing the bill for the Programme, and any cost over runs.
Government Response
Not Addressed
Government Response
Not Addressed
HM Government
Not Addressed
Responses to the Committee The Sponsor Body is not a government body so will provide responses to the recommendations in the PAC report directly to the Committee.
Source
Committee
Public Accounts Committee
Inquiry
Restoration and renewal
Report
Nineteenth Report - Restoration and renewal of the Palace of Westminster
05 Oct 2020
HC 549
Addressee Bodies
HM Treasury
Timeline
Recommendation age
5.7 yrs
Report published
05 Oct 2020