23

HS2 Ltd concluded £95m bat tunnel was most efficient option after considering 15 alternatives.

Conclusion
HS2 Ltd confirmed that it was its decision to build the structure and not one required by Natural England. However, the Department and HS2 Ltd told us that, despite its cost, that they had concluded the ‘tunnel’ structure was the most efficient and appropriate way to protect the bats out of the 15 options considered.39 Other options were rejected because of either “excessive cost, technical infeasibility or ecological ineffectiveness”. Their assessment included “robust challenge” from HM Treasury, a review by Arup on whether the solution could be delivered more efficiently and work with the Department for Environment, Food and Rural Affairs and Natural England to test whether the structure would provide the legal compliance and whether there were any better solutions that also reduced costs.40
Government Response

A response document is linked to this report, dated 16 May 2025. Response attribution to this conclusion has not been verified. Read the response document.

Addressee Bodies
HM Treasury
Timeline
Recommendation age 1.5 yrs
Report published 28 Feb 2025