25
Bat protection structure increased specific railway section costs from £73 million to £168 million.
Conclusion
In follow–up evidence, the Department confirmed that the total cost of building the structure will be £95 million (in 2019 prices). The Department also reported that the cost of building that section of the railway, irrespective of any mitigation works, would have been £73 million, meaning that the bat structure more than doubled the costs of that section of railway to £168 million.43
Government Response
A response document is linked to this report, dated 16 May 2025. Response attribution to this conclusion has not been verified. Read the response document.
Source
Committee
Public Accounts Committee
Report
10th Report - HS2: Update following the Northern leg cancellation
28 Feb 2025
HC 357
Addressee Bodies
HM Treasury
Timeline
Recommendation age
1.5 yrs
Report published
28 Feb 2025