Future funding for RAAC remediation beyond 2024-25 remains uncertain despite 2030 eradication goal.

Conclusion
NHS England also provided us with an update on its progress in dealing with known RAAC buildings. At the time we took evidence in September, it told us that there were projects to remove RAAC from the then 24 sites where it had a full understanding of the issues. It was aiming to eradicate RAAC in most places by 2030.53 We asked whether there would be enough money to continue and complete remediation after 2024–25, when current funding runs out. DHSC told us that it had no reason to think there would not be enough funding but that this would have to be considered as part of the next spending review.54
Government Response

A response document is linked to this report, dated 8 March 2024. Response attribution to this conclusion has not been verified. Read the response document.

Addressee Bodies
HM Treasury
Timeline
Recommendation age 2.8 yrs
Report published 17 Nov 2023