3rd report - The Global Combat Air Programme
Select Committee
Defence Committee
HC 598
14 January 2025
No response data available yet.
Government response
2nd Special Report - The Global Combat Air Programme: Government Response · published 21 Mar 2025
Recommendations & Conclusions
15 results
1
Conclusion
Global Combat Air Programme welcomed as vital for UK combat air sovereignty and allied relations
Conclusion
We welcome the establishment of the Global Combat Air Programme (GCAP), which will be one of the UK’s most significant defence programmes over the next decade and beyond. If delivered as planned, GCAP will enable the UK to retain national …
Read more
Ministry of Defence
View Details
2
Conclusion
Confidence in Japan and Italy's commitment and technical capabilities for Global Combat Air Programme
Conclusion
The Committee’s visits to Japan and Italy inspired great confidence in the commitment and capabilities of both our international partners. In particular, recognising that involvement in GCAP entails a significant step both politically and militarily for Japan, the Committee was …
Read more
Ministry of Defence
View Details
3
Conclusion
Assess potential new Global Combat Air Programme partners cautiously, prioritising 2035 in-service date
Conclusion
An open-minded but cautious approach should be taken to including new international partners within GCAP. The potential benefits will need to be weighed carefully against the risks, with any proposed partnering opportunity carefully assessed on its own merits. Any additional …
Read more
Ministry of Defence
View Details
4
Conclusion
Sustain empowerment of Global Combat Air Programme delivery structures to ensure timely decision-making
Conclusion
Given the ambitious timescales for GCAP, its delivery structures at the Governmental and industrial levels will need to be sufficiently empowered to take timely and binding decisions as the programme progresses. A repeat of the structural failings which contributed to …
Read more
Ministry of Defence
View Details
5
Conclusion
Flexibility in Global Combat Air Programme workshare supported while ensuring equal partnership perception
Conclusion
We support an element of flexibility in workshare arrangements for GCAP, whilst also recognising the need for all three nations involved to be, and be seen to be, equal partners over the course of the programme. (Conclusion, Paragraph 36)
Ministry of Defence
View Details
6
Conclusion
Establish a clearly defined framework for workshare flexibility to prevent negotiation delays.
Conclusion
Care must be taken to ensure that any flexibility around workshare is exercised within a clearly defined framework to avoid unnecessarily reopening negotiations and introducing delay. (Recommendation, Paragraph 37) Affordability
Ministry of Defence
View Details
7
Recommendation
Provide multi-year funding and transparent cost information for the GCAP programme.
Recommendation
With the defence budget under increasing pressure, it is incumbent on both Government and industry to keep tight control of costs as GCAP progresses. As more detailed information on programme costs becomes available, it must be made available to Parliament …
Read more
Ministry of Defence
View Details
8
Conclusion
Promote the broader economic benefits of GCAP to maintain public and political support.
Conclusion
If political and public support for GCAP is to be maintained, it is essential that the Government not only makes the case for its necessity as a military capability, but also promotes the broader economic benefits that it will bring. …
Read more
Ministry of Defence
View Details
9
Conclusion
Support and encourage Japan's legislative progress to enable successful GCAP fighter exports.
Conclusion
The Committee was greatly encouraged by Japan’s recognition of the importance of exports to their GCAP partners. Nonetheless, Japan’s inexperience as a defence exporter is likely to present unique challenges for GCAP which were not in evidence for Typhoon. The …
Read more
Ministry of Defence
View Details
10
Recommendation
Ensure GCAP is future-proofed to accommodate UK AI advances and counter adversary capabilities.
Recommendation
Our recent report on Developing AI Expertise and Capacity in UK Defence examined some of the challenges and opportunities presented by the use of artificial intelligence in defence. These are not exclusive to the air domain, 30 but they will …
Read more
Ministry of Defence
View Details
11
Conclusion
Build sufficient flexibility into GCAP to operate alongside future uncrewed combat solutions.
Conclusion
There are many unresolved questions about how best to harness Autonomous Collaborative Platforms (ACPs) alongside the existing and future combat fleet, with the development of advanced uncrewed platforms in particular requiring significant further work. Given these uncertainties it is essential …
Read more
Ministry of Defence
View Details
12
Conclusion
Failure to capitalise on Hawk success led to loss of UK manufacturing capacity.
Conclusion
The Hawk trainer aircraft has been a UK defence export success story, but with domestic production lines closing four years ago the skills and manufacturing capacity which had built up over decades will prove challenging and costly to regenerate. We …
Read more
Ministry of Defence
View Details
13
Conclusion
Implement a holistic approach to recruit and retain a skilled GCAP defence workforce.
Conclusion
Building and maintaining a skilled workforce will be crucial to GCAP’s success. With the defence industry facing fierce competition from other sectors for skilled workers, it is essential that a holistic approach is taken to recruitment and retention. GCAP offers …
Read more
Ministry of Defence
View Details
14
Conclusion
Prioritise retaining Typhoon workforce and securing export orders to bridge Tempest production gap.
Conclusion
Retention of the existing Typhoon manufacturing workforce, made more challenging by dwindling production runs and the gap until full-scale production of Tempest is underway, must be a priority; and securing further Typhoon export orders to ensure a consistent pipeline of …
Read more
Ministry of Defence
View Details
15
Conclusion
GCAP must break the mould of previous multilateral defence programme failures.
Conclusion
Whilst progress to date has been positive, previous multilateral defence programmes have frequently seen costs spiral and delays pile up and GCAP will have to break the mould if it is to achieve its ambitious target date. Decisions made at …
Read more
Ministry of Defence
View Details