John Hickmott

PFD Report All Responded Ref: 2025-0605
Date of Report 1 December 2025
Coroner Adam Smith
Coroner Area Milton Keynes
Response Deadline est. 26 January 2026
All 1 response received · Deadline: 26 Jan 2026
Response Status
Responses 1 of 2
56-Day Deadline 26 Jan 2026
All responses received
About PFD responses

Organisations named in PFD reports must respond within 56 days explaining what actions they are taking.

Source: Courts and Tribunals Judiciary

Coroner’s Concerns
I received evidence from witnesses who had attended the scene of the collision soon afterwards or driven past shortly beforehand, commenting on how dark it was and how difficult it would have been to see a pedestrian. I also received evidence from a Highways Strategic Asset Manager at Milton Keynes City Council, together with documents, indicating that a number of streetlights on this stretch of road had previously been reported as not working. These included a streetlight almost immediately above where the collision with Mr Hickmott took place and other adjacent/nearby streetlights. Specifically, there had been reports on 6 October 2024 of three individual streetlights not working, then on 20 November 2024 a report of a block of five more streetlights not working. It was stated in the Council's enquiry document that, "Several lamps on both sides of V11 are permanently out between the two Northfield Drive turnings" and that, "This is making this already accident-prone stretch of road more dangerous as the turnings are very dark." According to the Council's procedure at the time, the block of five lights should have been repaired within 14 days of having been reported defective and the three individual lights within 28 days. These lights had not been repaired at the time of the collision involving Mr Hickmott, nor when the Forensic Collision Investigator undertook a reconstruction 21 days later (see below). The evidence from the Highways Strategic Asset Manager was that six of the streetlights were repaired on 19 March 2025 and two more on 16 April 2025. I received a Collision Investigation Report from a Forensic Collision Investigator at Thames Valley Police's Forensic Collision Investigation Unit. This included detailed evidence about conspicuity, and how Mr Hickmott would have been especially inconspicuous in the dark, in the absence of working streetlighting proximate to the incident. This evidence included photographs from a reconstruction undertaken at the site in hours of darkness 21 days after the incident. The streetlights were still not working at that time. This evidence was striking in demonstrating how a pedestrian would be almost invisible to a driver (even when one knows they are present and are looking for them) until the driver is within 20 - 30 metres of the pedestrian, at which point they would start to be illuminated by car headlights. The Council’s Highways Strategic Asset Manager also stated that, following an inspection of the same stretch of road, undertaken on 19 November 2025 following questions received from me, six streetlights were found not to be working (not previously reported to the Council as faulty). This may suggest a more fundamental technical problem with the streetlights on this stretch of road. The evidence of the Highways Strategic Asset Manager was that the priorities and timescales for repairs of faulty streetlights were already, as at November 2024, set out in the Council's contract with its principal highway services contractor, as well as the Code of Practice for Highways Electrical Maintenance. Despite this, the faults reported on 6 October and 20 November 2024 were not repaired until 19 March and 16 April 2025. I am concerned at:
1) The timeliness of repairs being undertaken when streetlights are reported as not being lit;
2) The extent of monitoring of scheduled repairs to ensure timely repair;
3) The extent to which proactive inspections are undertaken by the Council to identify faulty streetlights, or blocks of lights, that may not have been reported to the Council.
Responses
Highways and Transportation Milton Keynes Council
14 Jan 2026
Milton Keynes City Council has reiterated contractual requirements for streetlight repairs, introduced 10% sample check inspections and comprehensive reporting, and implemented a Road Safety Assessment for larger outages. They also plan to install a remote monitoring system for most streetlights by April 2026. AI summary
View full response
Dear Mr Smith,

Thank you for your Regulation 28 Report dated 1 December 2025 concerning the tragic death of Mr John Charles Hickmott on 19 February 2025.

Milton Keynes City Council (MKCC) offers its sincere condolences to Mr Hickmott’s family and all those affected.

Coroner’s Concerns You raised the following areas of concern:

1. Timeliness of repairs when streetlights are reported as not being lit.
2. Monitoring and oversight of scheduled repairs to ensure timely action.
3. The extent of proactive inspections to identify faulty streetlights or larger-scale outages not yet reported.

MKCC response and actions.

1.Timeliness of repairs when Streetlights are reported as not being lit

General streetlight repair works are contractually required to be fixed by our contractor within the stated 14 days for the block faults, unless it is outside of our control, such as an electricity supply issue to our assets.

The requirements of the contract have been reiterated to the contractor via formal notification.

2.Monitoring and oversight of scheduled repairs to ensure timely action

MKCC now undertake a sample check inspection of 10% of the repair works carried out by the contractor.

All works will be updated within the highways asset system with before and after reports and photographs. These reports will be reviewed at the regular operational lighting team meeting before being formalised into the contractual key performance indicators which form part of the overall performance framework of the contract.

3.The extent of proactive inspections to identify faulty streetlights or larger scale outages not yet reported By April 2026, most of the highways street lighting assets and all grid road and high priority lighting areas will have had a remote monitoring system installed. This enables proactive inspection and early identification of any streetlights out. This will replace most manual scouting. There will remain a minimal level manual ‘fault scouting’ and identification to check any significant or unclear fault reports from the system.

From time to time there are circumstance on grid roads outside of our control where the stated streetlight repair timeline for larger outages cannot be met. MKCC have introduced a Road Safety Assessment for these instances, undertaken by an accredited Safety Auditor, who will consider temporary “Street Lights Not Working” signage as well or Temporary reduced speed limit signage, or further road safety interventions on a risk assessment basis. (end)
Report Sections
Investigation and Inquest
On 24 February 2025, Dr Sean Cummings, Assistant Coroner, commenced an investigation into the death of John Charles HICKMOTT aged 63. The investigation concluded at the end of the inquest on 21 November 2025. My conclusion at the inquest was that Mr Hickmott died by road traffic collision. The medical cause of death was: 1(a) Multiple fractures and cardiogenic shock.
Circumstances of the Death
On 19 February 2025, at around 19:15 hours, Mr Hickmott crossed the road (V11 Tongwell Street, Northfield, Milton Keynes) near to the Audi garage. There was a pedestrian footpath at either side of the road where he crossed and a pedestrian island in the middle of the road so that pedestrians could stop midway. The road at this point is a single carriageway road, with a 60mph limit. It was dark and the weather was dry, although the road was damp. A number of nearby streetlights, including one immediately above the site of the collision, were not working at the time. The nearest lit streetlights were 75m and 105m respectively in opposite directions from the site of the collision. Mr Hickmott stepped from the pedestrian island in front of a moving car. On the evidence, he was probably intoxicated at the time. He had been seen a few minutes earlier stumbling on the grass verge and into the road. He was struck by the car and died at the scene from the injuries he sustained. The driver of the vehicle that collided with Mr Hickmott was following all rules and regulations, including driving well below the speed limit. He was not impaired by drugs or alcohol. Mr Hickmott would only have become visible to him at the last moment. The driver reacted appropriately and took evasive action, but once Mr Hickmott stepped into the road, the collision was sadly unavoidable.
Related Inquiry Recommendations

Public inquiry recommendations addressing similar themes

Replace Buried Metallic LPG Pipes
ICL Inquiry
Public Infrastructure Physical Hazards
New LPG Safety Regime
ICL Inquiry
Public Infrastructure Physical Hazards
LPG Supplier Registration
ICL Inquiry
Public Infrastructure Physical Hazards
Polyethylene Piping Research
ICL Inquiry
Public Infrastructure Physical Hazards
Limit perimeter fencing height to a maximum of 2.2 metres
Taylor Inquiry
Public Infrastructure Physical Hazards
Paint and mark all emergency gates in fences with "Emergency Exit
Taylor Inquiry
Public Infrastructure Physical Hazards
Keep all perimeter fence gates to pitch unlocked and open during matches
Taylor Inquiry
Public Infrastructure Physical Hazards
Annually inspect all crush barriers for corrosion; repair or replace as needed
Taylor Inquiry
Public Infrastructure Physical Hazards

Data sourced from Courts and Tribunals Judiciary under the Open Government Licence.