James Scott
PFD Report
Partially Responded
Ref: 2025-0374
Coroner's Concerns (AI summary)
Inadequate gully maintenance, insufficient warning signage, and the continued presence of surface water on a known flood-risk road contributed to a fatal incident.
View full coroner's concerns
[BRIEF SUMMARY OF MATTERS OF CONCERN] (1) The area is a known flood risk (2) Whilst the precise cause of the flooding is unknown, a more regular maintenance schedule may have prevented the buildup of vegetation within the gullies and therefore assisted in the drainage of the heavy rainfall experienced that day thus reducing the amount of surface water present on the road (3) The fact that only a Temporary Sign was in place in an area known for years to be a flood risk (4) The surface water was a contributory factor in this death
Responses
Action Planned
National Highways is working with Hampshire County Council and the M3 J9 scheme team to address flood risk issues on the A33, including drainage remediation, ditch clearing, and gully repairs. HCC and NH are coordinating on traffic management and further investigations, with maintenance planned through March 2028. (AI summary)
National Highways is working with Hampshire County Council and the M3 J9 scheme team to address flood risk issues on the A33, including drainage remediation, ditch clearing, and gully repairs. HCC and NH are coordinating on traffic management and further investigations, with maintenance planned through March 2028. (AI summary)
View full response
REGULATION 29 RESPONSE TO A REPORT TO PREVENT FUTURE DEATH
THIS RESPONSE IS BEING SENT TO:
The Area Coroner for Hampshire, Portsmouth and Southampton, Rosamund Rhodes-Kemp, in response to a ‘Regulation 28 Report to Prevent Future Death’ following an inquest hearing into the death of James Scott.
1. NATIONAL HIGHWAYS
I am Christine Allen, Regional Director, South East region, responding on behalf of Nick Harris, Chief Executive of National Highways Limited, Bridge House, 1 Walnut Tree Close, Guildford, Surrey GU1 4LZ.
2. CORONERS MATTERS OF CONCERN
The MATTERS OF CONCERN were identified as follows:
(1) The area is a known flood risk. (2) Whilst the precise cause of the flooding is unknown, a more regular maintenance schedule may have prevented the build-up of vegetation within the gullies and therefore assisted in the drainage of the heavy rainfall experienced that day thus reducing the amount of surface water present on the road. (3) The fact that only a Temporary Sign was in place in an area known for years to be a flood risk. (4) The surface water was a contributory factor in this death.
3. BACKGROUND
Location The A33 Basingstoke Road southbound near Kings Worthy / Abbots Worthy carriageway is the responsibility of Hampshire County Council (HCC). The National Highways (NH) network then starts southbound opposite the London Road junction.
The HCC section of the highway at the staggered junction, and both roads of the B3047, fall to the A33 with a much steeper gradient from the left junction from the B3037 Alresford. This results in the catchment for rain / surface water to naturally run down hill, being the A33 slip road.
Drainage This location is a recorded flood risk site over a distance of 1523 metres in length from the NH boundary at the London Road junction, start of A34 slip road to the end of the A33 southbound on slip where it meets the main A34. In relation to the incident on 5 July 2024 and the coroner’s concerns, we have considered the flood events recorded within the first 400 metres of that flood risk site.
The location of the incident is a recorded flood risk site. It is recorded as a category B (High). The incident on 5 July 2024 has been included as a flood event in the drainage database to inform the categorisation of this location. The grading assessment of flood risk sites is calculated automatically by our Geotechnical Data Management System (GDMS) monthly and is based on the number of reported flood events at each asset location. There are only three reported incidents at this location in the last 5 years and no further flood events have been recorded in this area since July 2024.
Upon receipt of the coroner’s concerns, we found there to be a lack of clarity on the ownership of the overall drainage system at this location. As a result, NH and HCC met on site on 12 September 2025, and this has now been clarified and agreed. This clarification is set out further on in this response.
Maintenance As a recorded flood risk site, the maintenance frequency is increased from the standard of every two years to twice a year for drainage assets e.g. gullies, catchpits and channels (if applicable).
Inspection We undertake various types of inspection of our network which serve to inform us of the state and operability of our assets, these inspection types are principally: o Safety Inspections – these are driven inspections of the network conducted by our own Inspectors; at this location they take place on a weekly basis. These inspections identify any areas of concern and defects at an early stage enabling assessment, prioritisation and rectification. Inspectors are aware of identified issues on their routes, including flood risk sites and focus attention on drainage assets in those locations. o Condition Surveys – these are technical assessments of the condition and serviceability of the assets, for drainage assets these are conducted by specialist 3rd party contractors on a ‘find and fix’ basis to the Design Manual for Roads and Bridges (DMRB) standard CS 551 Drainage surveys - Part 13 and are prioritised based on the GDMS flood risk grading of an area. The grading of this area has not currently initiated a ‘find and fix’ scheme but we detail our plans outside of this later on in this response.
The inspection regime is carried out in accordance with our standards and severe weather planning requirements.
Weather To confirm, there were no weather alerts in place for the area on the day of the incident or the days immediately preceding it.
NH and our contractors monitor weather routinely due to the impact it can have on our business-as-usual activities. In the event of a weather alert (forecast) of severe weather, which includes heavy rain, an impact assessment is conducted to determine what, if any action is required to maintain the safety of road users on the network. A severe weather event for heavy rain fall, will trigger consideration of any specific areas
of vulnerability where additional measures may be required, or additional resources need to be stood up to affect a rapid response. This includes locations identified as flood risk sites.
In the event of severe weather that is likely to cause disruption or impact on the network we invoke the process detailed in our Crisis Management Manual (CMM) which sees us escalating our operating state from ‘Normal Operations’ to ‘Regional Alert’. This state triggers multiple actions including briefings and tactical teleconferences which include our supply chain within the region to consider the impact and any measures that may need to be actioned in advance of or in response to the threat. Depending on the severity of the event this may include measures such as additional resources, equipment or pre-emptive work prior to the arrival of the inclement weather.
4.
DETAILS OF ACTION TAKEN
Inspections Our weekly safety inspections prior to the incident were all completed and documented with no drainage follow up action required. Please note this was conducted on one gully known to belong to NH at the time. Ownership of the drainage systems in the area has now been established with HCC.
Drainage The first drainage flood risk site visit of financial year 1 April 2024 to 31 March 2025 was ordered on 23 April 2024 with a six-month window for completion. The work was completed on 31 August 2024. The drainage flood risk site visit prior to this was carried out on 23 November 2023 which was flood risk site visit two for the previous financial year.
During these works the gully lid was lifted, vegetation and detritus cleared, and the gully jetted with any waste sucked out and removed.
M3 Junction 9 Improvement Scheme The location of the incident has now been taken under the management of the NH M3 Junction 9 (J9) major improvement scheme to improve congestion and traffic flow in the wider area. The scheme is being delivered by our supply chain and overseen by ourselves. In circumstances like this we invoke a Detailed Local Operating Agreement (DLOA) which sets out whether the scheme or normal operations is responsible for the maintenance and inspection activity in the area. The M3 J9 major improvement scheme has now taken responsibility for cyclic maintenance in this area until completion of their scheme scheduled for March 2028. Safety inspections will remain with our NH Inspectors but with the addition of regular driven site checks by the scheme Traffic Safety Control Officer (TSCO) who will identify and act on any defects that arise.
Site Meetings / Maintenance Work On 21 August 2025 the M3 J9 scheme attended the area, strimmed and jetted the filter drains removing overburden and lifted manhole lids ensuring lines were cleared and unburdened with sediment.
On 28 August 2025 our drainage engineers conducted a site visit to the location of the incident. We were unsuccessful in our efforts to combine this meeting with HCC representatives however we have since completed a collaborative visit. NH identified the following additional work on our own network which was instructed on 2 September 2025:
1. Sweeping of kerb line on Northbound and Southbound carriageways between London Road and A34.
2. Check side entry inlets in whole area.
3. Removal of overburden across entire area.
4. Review drainage systems from the St Marys Close Pedestrian crossing northwards to the London Road pedestrian crossing.
5. Repair or replace eight gullies and locate outfalls in the ditch on the southbound verge between Kings Worthy House and London Road pedestrian crossing. [This action required HCC collaboration to clarify ownership].
6. Vegetation clearance in the ‘ditch’ line (HCC land) and clearance of the ditch to the River Itchen. [As above this action required collaboration with HCC to clarify ownership].
A further site visit was conducted on 12 September 2025. This was attended by HCC’s Principal Engineer, Hampshire Police and NH Drainage Engineers plus representatives from the M3 J9 scheme. All attendees agreed to the remedial work instructed on 2 September 2025 above with the addition of:
7. M3 J9 scheme to arrange jetting of NH gullies to outlet.
8. A review of resurfacing extents within the M3 J9 scheme as the program currently stops approximately 25 metres short of the current NH boundary and an extension will avoid a double joint in a short distance.
9. M3 J9 scheme to review if drainage can be improved during the surfacing phase of the works to remove the flat spot at the rolling crown and to gain flow into the gullies on the southbound carriageway between London Road and Worthy Clinic.
Full road closures of the area were implemented overnight on 15-16 September 2025 where Items 1-4 and 7 above were completed.
Signage The temporary “Road liable to flooding” sign was on site at the time of the incident. Our review has found the sign can be seen on site on 27 April 2023 and 21 May 2024.
At the first site visit on 28 August 2025, it was noted that the sign had been laid down on the verge, this was reinstated by NH that day. The M3 J9 scheme has been instructed to ensure the sign remains in place until instructed to be removed by the NH Operations Directorate South East Drainage team upon completion of the actions proposed and a suitable period of monitoring.
5 DETAILS OF FURTHER ACTION PROPOSED
Inspections Weekly safety inspections will continue as planned through the NH routine program.
Drainage Work In addition to Items 8 and 9 of the Maintenance Work above, the following further action is to be undertaken:
1. Review of any further works identified during overnight closure on 15-16 September 2025.
2. Further works to be considered by M3 J9 scheme on the central reserve due to the pedestrian crossing being moved out slightly to narrow the lane. HCC to repair defective gullies at Itchen Abbas Road.
3. HCC to jet and clean drainage system from Itchen Abbas Road and Kings Worthy House to outlet in ditch.
4. HCC to ensure ditch is clear and flowing.
5. HCC to investigate where ditch drains to and ensure functionality.
6. HCC to liaise with M3 J9 scheme team to agree traffic management requirements and works they intend to undertake.
7. M3 J9 team to support HCC wherever possible to facilitate road space access to complete the HCC works.
Maintenance Regular planned maintenance will continue in accordance with the frequency determined by NH flood risk sites. This will be delivered by the M3 J9 scheme for the duration of their works that are due to be completed by March 2028.
Signage
No further signage action required at present due to extensive M3 J9 scheme traffic management and signage now in place. M3 J9 scheme to ensure that “Road liable to flooding” sign is not removed without prior consent of NH drainage engineers.
6
TIMETABLE FOR ACTION
Date Action Item 21/08/2025 Central reserve filter drain remediated. Section 4 – Item 1 28/08/2025 Re-instatement of ‘Road liable to flooding’ sign. Section 4 - Signage 15 – 16/09/2025 Complete items 1-4, 6 and 7 of the Maintenance Work.
Section 4 31/12/25 Repair / replacement of 3 NH owned gullies. Section 4 – Item 5 TBC (HCC) HCC remediation works including 5 gully repairs / replacements. Section 5 – Item 2 TBC pending review of M3 J9 program Further works that may be required, such as surfacing or additional drainage. Section 4 – Item 8-9
7 SAFETY OF ROAD USERS
The safety of everyone on our road network matters; it is an imperative for our business in what we set out to achieve and a core value of our organisation in how we go about it. The action taken and planned on the A33 is designed in this light to help to prevent future deaths at this location.
8
17 September 2025 Signed:
Christine Allen, Regional Director South East region
THIS RESPONSE IS BEING SENT TO:
The Area Coroner for Hampshire, Portsmouth and Southampton, Rosamund Rhodes-Kemp, in response to a ‘Regulation 28 Report to Prevent Future Death’ following an inquest hearing into the death of James Scott.
1. NATIONAL HIGHWAYS
I am Christine Allen, Regional Director, South East region, responding on behalf of Nick Harris, Chief Executive of National Highways Limited, Bridge House, 1 Walnut Tree Close, Guildford, Surrey GU1 4LZ.
2. CORONERS MATTERS OF CONCERN
The MATTERS OF CONCERN were identified as follows:
(1) The area is a known flood risk. (2) Whilst the precise cause of the flooding is unknown, a more regular maintenance schedule may have prevented the build-up of vegetation within the gullies and therefore assisted in the drainage of the heavy rainfall experienced that day thus reducing the amount of surface water present on the road. (3) The fact that only a Temporary Sign was in place in an area known for years to be a flood risk. (4) The surface water was a contributory factor in this death.
3. BACKGROUND
Location The A33 Basingstoke Road southbound near Kings Worthy / Abbots Worthy carriageway is the responsibility of Hampshire County Council (HCC). The National Highways (NH) network then starts southbound opposite the London Road junction.
The HCC section of the highway at the staggered junction, and both roads of the B3047, fall to the A33 with a much steeper gradient from the left junction from the B3037 Alresford. This results in the catchment for rain / surface water to naturally run down hill, being the A33 slip road.
Drainage This location is a recorded flood risk site over a distance of 1523 metres in length from the NH boundary at the London Road junction, start of A34 slip road to the end of the A33 southbound on slip where it meets the main A34. In relation to the incident on 5 July 2024 and the coroner’s concerns, we have considered the flood events recorded within the first 400 metres of that flood risk site.
The location of the incident is a recorded flood risk site. It is recorded as a category B (High). The incident on 5 July 2024 has been included as a flood event in the drainage database to inform the categorisation of this location. The grading assessment of flood risk sites is calculated automatically by our Geotechnical Data Management System (GDMS) monthly and is based on the number of reported flood events at each asset location. There are only three reported incidents at this location in the last 5 years and no further flood events have been recorded in this area since July 2024.
Upon receipt of the coroner’s concerns, we found there to be a lack of clarity on the ownership of the overall drainage system at this location. As a result, NH and HCC met on site on 12 September 2025, and this has now been clarified and agreed. This clarification is set out further on in this response.
Maintenance As a recorded flood risk site, the maintenance frequency is increased from the standard of every two years to twice a year for drainage assets e.g. gullies, catchpits and channels (if applicable).
Inspection We undertake various types of inspection of our network which serve to inform us of the state and operability of our assets, these inspection types are principally: o Safety Inspections – these are driven inspections of the network conducted by our own Inspectors; at this location they take place on a weekly basis. These inspections identify any areas of concern and defects at an early stage enabling assessment, prioritisation and rectification. Inspectors are aware of identified issues on their routes, including flood risk sites and focus attention on drainage assets in those locations. o Condition Surveys – these are technical assessments of the condition and serviceability of the assets, for drainage assets these are conducted by specialist 3rd party contractors on a ‘find and fix’ basis to the Design Manual for Roads and Bridges (DMRB) standard CS 551 Drainage surveys - Part 13 and are prioritised based on the GDMS flood risk grading of an area. The grading of this area has not currently initiated a ‘find and fix’ scheme but we detail our plans outside of this later on in this response.
The inspection regime is carried out in accordance with our standards and severe weather planning requirements.
Weather To confirm, there were no weather alerts in place for the area on the day of the incident or the days immediately preceding it.
NH and our contractors monitor weather routinely due to the impact it can have on our business-as-usual activities. In the event of a weather alert (forecast) of severe weather, which includes heavy rain, an impact assessment is conducted to determine what, if any action is required to maintain the safety of road users on the network. A severe weather event for heavy rain fall, will trigger consideration of any specific areas
of vulnerability where additional measures may be required, or additional resources need to be stood up to affect a rapid response. This includes locations identified as flood risk sites.
In the event of severe weather that is likely to cause disruption or impact on the network we invoke the process detailed in our Crisis Management Manual (CMM) which sees us escalating our operating state from ‘Normal Operations’ to ‘Regional Alert’. This state triggers multiple actions including briefings and tactical teleconferences which include our supply chain within the region to consider the impact and any measures that may need to be actioned in advance of or in response to the threat. Depending on the severity of the event this may include measures such as additional resources, equipment or pre-emptive work prior to the arrival of the inclement weather.
4.
DETAILS OF ACTION TAKEN
Inspections Our weekly safety inspections prior to the incident were all completed and documented with no drainage follow up action required. Please note this was conducted on one gully known to belong to NH at the time. Ownership of the drainage systems in the area has now been established with HCC.
Drainage The first drainage flood risk site visit of financial year 1 April 2024 to 31 March 2025 was ordered on 23 April 2024 with a six-month window for completion. The work was completed on 31 August 2024. The drainage flood risk site visit prior to this was carried out on 23 November 2023 which was flood risk site visit two for the previous financial year.
During these works the gully lid was lifted, vegetation and detritus cleared, and the gully jetted with any waste sucked out and removed.
M3 Junction 9 Improvement Scheme The location of the incident has now been taken under the management of the NH M3 Junction 9 (J9) major improvement scheme to improve congestion and traffic flow in the wider area. The scheme is being delivered by our supply chain and overseen by ourselves. In circumstances like this we invoke a Detailed Local Operating Agreement (DLOA) which sets out whether the scheme or normal operations is responsible for the maintenance and inspection activity in the area. The M3 J9 major improvement scheme has now taken responsibility for cyclic maintenance in this area until completion of their scheme scheduled for March 2028. Safety inspections will remain with our NH Inspectors but with the addition of regular driven site checks by the scheme Traffic Safety Control Officer (TSCO) who will identify and act on any defects that arise.
Site Meetings / Maintenance Work On 21 August 2025 the M3 J9 scheme attended the area, strimmed and jetted the filter drains removing overburden and lifted manhole lids ensuring lines were cleared and unburdened with sediment.
On 28 August 2025 our drainage engineers conducted a site visit to the location of the incident. We were unsuccessful in our efforts to combine this meeting with HCC representatives however we have since completed a collaborative visit. NH identified the following additional work on our own network which was instructed on 2 September 2025:
1. Sweeping of kerb line on Northbound and Southbound carriageways between London Road and A34.
2. Check side entry inlets in whole area.
3. Removal of overburden across entire area.
4. Review drainage systems from the St Marys Close Pedestrian crossing northwards to the London Road pedestrian crossing.
5. Repair or replace eight gullies and locate outfalls in the ditch on the southbound verge between Kings Worthy House and London Road pedestrian crossing. [This action required HCC collaboration to clarify ownership].
6. Vegetation clearance in the ‘ditch’ line (HCC land) and clearance of the ditch to the River Itchen. [As above this action required collaboration with HCC to clarify ownership].
A further site visit was conducted on 12 September 2025. This was attended by HCC’s Principal Engineer, Hampshire Police and NH Drainage Engineers plus representatives from the M3 J9 scheme. All attendees agreed to the remedial work instructed on 2 September 2025 above with the addition of:
7. M3 J9 scheme to arrange jetting of NH gullies to outlet.
8. A review of resurfacing extents within the M3 J9 scheme as the program currently stops approximately 25 metres short of the current NH boundary and an extension will avoid a double joint in a short distance.
9. M3 J9 scheme to review if drainage can be improved during the surfacing phase of the works to remove the flat spot at the rolling crown and to gain flow into the gullies on the southbound carriageway between London Road and Worthy Clinic.
Full road closures of the area were implemented overnight on 15-16 September 2025 where Items 1-4 and 7 above were completed.
Signage The temporary “Road liable to flooding” sign was on site at the time of the incident. Our review has found the sign can be seen on site on 27 April 2023 and 21 May 2024.
At the first site visit on 28 August 2025, it was noted that the sign had been laid down on the verge, this was reinstated by NH that day. The M3 J9 scheme has been instructed to ensure the sign remains in place until instructed to be removed by the NH Operations Directorate South East Drainage team upon completion of the actions proposed and a suitable period of monitoring.
5 DETAILS OF FURTHER ACTION PROPOSED
Inspections Weekly safety inspections will continue as planned through the NH routine program.
Drainage Work In addition to Items 8 and 9 of the Maintenance Work above, the following further action is to be undertaken:
1. Review of any further works identified during overnight closure on 15-16 September 2025.
2. Further works to be considered by M3 J9 scheme on the central reserve due to the pedestrian crossing being moved out slightly to narrow the lane. HCC to repair defective gullies at Itchen Abbas Road.
3. HCC to jet and clean drainage system from Itchen Abbas Road and Kings Worthy House to outlet in ditch.
4. HCC to ensure ditch is clear and flowing.
5. HCC to investigate where ditch drains to and ensure functionality.
6. HCC to liaise with M3 J9 scheme team to agree traffic management requirements and works they intend to undertake.
7. M3 J9 team to support HCC wherever possible to facilitate road space access to complete the HCC works.
Maintenance Regular planned maintenance will continue in accordance with the frequency determined by NH flood risk sites. This will be delivered by the M3 J9 scheme for the duration of their works that are due to be completed by March 2028.
Signage
No further signage action required at present due to extensive M3 J9 scheme traffic management and signage now in place. M3 J9 scheme to ensure that “Road liable to flooding” sign is not removed without prior consent of NH drainage engineers.
6
TIMETABLE FOR ACTION
Date Action Item 21/08/2025 Central reserve filter drain remediated. Section 4 – Item 1 28/08/2025 Re-instatement of ‘Road liable to flooding’ sign. Section 4 - Signage 15 – 16/09/2025 Complete items 1-4, 6 and 7 of the Maintenance Work.
Section 4 31/12/25 Repair / replacement of 3 NH owned gullies. Section 4 – Item 5 TBC (HCC) HCC remediation works including 5 gully repairs / replacements. Section 5 – Item 2 TBC pending review of M3 J9 program Further works that may be required, such as surfacing or additional drainage. Section 4 – Item 8-9
7 SAFETY OF ROAD USERS
The safety of everyone on our road network matters; it is an imperative for our business in what we set out to achieve and a core value of our organisation in how we go about it. The action taken and planned on the A33 is designed in this light to help to prevent future deaths at this location.
8
17 September 2025 Signed:
Christine Allen, Regional Director South East region
Sent To
- Hampshire County Council
- National Highways
Response Status
Linked responses
1 of 2
56-Day Deadline
18 Sep 2025
About PFD responses
Organisations named in PFD reports must respond within 56 days explaining what actions they are taking.
Source: Courts and Tribunals Judiciary
Report Sections
Investigation and Inquest
On 09 July 2024 I commenced an investigation into the death of James Alexander SCOTT aged 25. The investigation concluded at the end of the inquest on 17 July 2025. The conclusion of the inquest was that: On the evening of 5th July 2024 James Scott, aged 25, was driving Southbound on the A33 when he lost control of the vehicle which turned sideways crossing onto the opposite carriageway colliding with a Northbound vehicle. He sustained fatal injuries and was sadly pronounced deceased at the scene.
Circumstances of the Death
This report concerns a fatal road traffic collision between a Vauxhall Corsa and a Ford Ranger towing a SBS trailer upon which was a trailer, which occurred around 21:44 on Friday 5th July 2024 on the A33 near Kings Worthy, Hampshire. Mr Scott was travelling South in his Vauxhall Corsa where the vehicle has passed through an area of standing water. Consequently, the Corsa has entered a state of clockwise yaw, passing through the central reserve and into the path of the oncoming Ford Ranger which was travelling North. The Vauxhall and Ford have collided in ‘T-Bone’ formation, with Mr Scott sustaining fatal injuries and being sadly declared deceased at the scene. On examination it was observed that two of the drains to the nearside of the southbound lane were compacted with vegetation, resulting in little or no surface drainage. This is despite annual scheduled maintenance for year 2023/2024 taking place on 19th May 2023 and 15th November 2023. This included clearing gullies and catch pits either side of the A33. A Temporary “Flood” warning sign was located within the nearside grass verge, around 8 meters north of the commencement of the flooding. The ‘Temporary’ warning sign had been present for about 5 years prior to the collision. Whilst ownership of the sign is subject to debate between National Highways and Hampshire County Council, the area is known to be a flood risk and has been one for several years prior to the collision. The Forensic examiner concluded that the standing water was a contributory factor in the collision and was relevant to factors affecting Mr Scott.
Similar PFD Reports
Reports sharing organisations, categories, or themes
Related Inquiry Recommendations
Public inquiry recommendations addressing similar themes
Remove all spikes and inward-facing constructions from perimeter and radial fences
Taylor Inquiry
Public Infrastructure Physical Hazards
Limit perimeter fencing height to a maximum of 2.2 metres
Taylor Inquiry
Public Infrastructure Physical Hazards
Provide sufficient 1.1-metre wide gates in perimeter fences for emergency evacuation
Taylor Inquiry
Public Infrastructure Physical Hazards
Paint and mark all emergency gates in fences with "Emergency Exit
Taylor Inquiry
Public Infrastructure Physical Hazards
Keep all perimeter fence gates to pitch unlocked and open during matches
Taylor Inquiry
Public Infrastructure Physical Hazards
Annually inspect all crush barriers for corrosion; repair or replace as needed