Harry Colledge
PFD Report
1 of 1 responses identified
Ref: 2024-0096
All 1 listed response identified
· Deadline: 19 Apr 2024
Coroner's Concerns (AI summary)
Highway operatives lack specific training to identify road defects hazardous to cyclists. Additionally, a road's natural geological movement causes defects that current inspections may not adequately identify, posing risks to all road users.
View full coroner's concerns
1. Highway operatives gave evidence that their inspections primarily consider the impact of defects upon cars using that road surface. All gave evidence of no specific training or experience with regards to identifying defects which present a hazard to bicycle users, when expert evidence indicated that the Council’s statutory duty required reasonable steps to protect all road users which includes cyclists. The evidence of Council witnesses was unanimous that since Mr Colledge’s death, there has been no additional training, updates, briefings or policy reviews to offer further knowledge of operatives in safely assessing defects which pose risks to cyclists or road users other than car drivers. I consider there is a risk of future deaths of all cyclists if Highways Operatives and inspectors are not able to identify defects on a carriageway which present a risk to cyclists as opposed to simply car users.
2. Evidence from a Highways Expert, , explained that Island Lane is part of peat/moss road which is the subject of natural movement when it rains. The water is absorbed by the peat/moss and swells caused the tarmac to move then it compacts when it dries and the road surface lowers, causing cracks. ’ evidence was that there is natural movement but these defects rarely get better, only worse. I am concerned that the road surfacing on Island Lane, Winmarleigh will continue to be the subject of natural movement and the present surfacing is hampered by the geography of the location including camber of the road. I consider there is a risk of future deaths to road users if the surfacing of this road is not adequately maintained. Whilst the inspection schedule timescales enacted by the Council are considered to be appropriate, I consider there is a risk of future deaths due to the present surfacing and underlying geological features of this road if inspections are unable to reasonably identify hazardous defects.
2. Evidence from a Highways Expert, , explained that Island Lane is part of peat/moss road which is the subject of natural movement when it rains. The water is absorbed by the peat/moss and swells caused the tarmac to move then it compacts when it dries and the road surface lowers, causing cracks. ’ evidence was that there is natural movement but these defects rarely get better, only worse. I am concerned that the road surfacing on Island Lane, Winmarleigh will continue to be the subject of natural movement and the present surfacing is hampered by the geography of the location including camber of the road. I consider there is a risk of future deaths to road users if the surfacing of this road is not adequately maintained. Whilst the inspection schedule timescales enacted by the Council are considered to be appropriate, I consider there is a risk of future deaths due to the present surfacing and underlying geological features of this road if inspections are unable to reasonably identify hazardous defects.
Responses
Action Taken
Lancashire County Council delivered debrief presentations to staff, undertook additional safety inspections, and implemented a temporary speed reduction. They commissioned a review of the Highway Safety Inspection Policy and a full Geotechnical Survey of Island Lane. (AI summary)
Lancashire County Council delivered debrief presentations to staff, undertook additional safety inspections, and implemented a temporary speed reduction. They commissioned a review of the Highway Safety Inspection Policy and a full Geotechnical Survey of Island Lane. (AI summary)
View full response
Dear Ms Bisset Response to Regulation 28 Report Inquest into the death of Harry Colledge I am writing in response to your Regulation 28 notice dated 16.11.2023 to outline the actions taken by Lancashire County Council (“the Council”) to address your concerns. The Council has taken this incident, and your findings, very seriously. The Council took a proactive approach in addressing your concerns immediately following the conclusion of the inquest hearing, prior to receipt of your Regulation 28 notice. Geotechnical investigations were undertaken prior to the inquest to identify whether any short-term actions were required at the accident locus to ensure the safety of highway users. I provide further detail below. In addition, the Council took immediate action following the conclusion of the inquest on 13.10.2023. The following actions have been taken to address your concerns:
1. Inquest Debrief Following the conclusion of the inquest, a meeting was arranged between Senior Managers to review this case and discuss your findings, which were delivered in Court on 13.10.2023, and ensure steps were put in place to address your concerns. As a result of the meeting between Senior Managers, a debrief presentation was developed containing the key facts of the case, lessons learnt, and operational instructions. This presentation was delivered to all Countywide Operational Managers and the Highway Inspection Manager on 18.10.2023. The presentation was then shared with all maintenance operational staff and Highway Safety Inspectors in a series of team meetings, which were completed by 27.10.2023. The incident debrief has also been delivered to wider Highway services to ensure a greater operational awareness. In summary, the debrief highlighted: Lancashire County Council PO Box 100, County Hall, Preston, PR1 0LD
2 That it was inappropriate to use Highway Operative staff to identify defects in a "find and fix" way, as carried out on 14.09.2022 following the series of defect reports provided by the Parish Council, and that this practice would not be used in future. That the recording of all defect reporting by the public must be managed through the service Highway Asset Management System and that any works done must also be recorded. That operational staff and Highway Safety Inspectors must be on notice of surface cracking – particularly but not exclusively, on the Moss Road Network. That operational staff and Highway Safety Inspectors must be on notice of defects which are a hazard to all road users including cyclists and non-motorised users.
2. Training In addition to the specific learning from this incident delivered through debrief sessions, the Council has developed its training programme as follows: a) Highway Safety Inspectors The role of a Highway Safety Inspector is to carry out cyclic inspections in line with the inspection regime set out in the Council’s Highway Safety Inspection Policy. The policy sets out that this role will be responsible for the identification and consequent action relating to maintainable vehicular highway defects within the bounds of Section 41 of the Highways Act 1980. It is recommended in national guidance set out in Well Managed Highways that Highway Inspectors are trained, qualified and competent in the identification of defects. The UK Roads Board sets out minimum competency standards and these are delivered through the IHE (Institute of Highways Engineers) Training and Certification scheme. Highways Authorities are required to demonstrate that Highway Safety Inspectors have been assessed against these standards. The core modules of the training undertaken by Highway Inspectors employed by the Council include: an understanding of highway law, inspection policies and procedures (including maintenance priorities, road hierarchies, inspection frequency, methods, levels, and response criteria), material recognition and measuring techniques, hazard and defect recognition (including types of defects, techniques of defect repair), health and safety, and safety inspection and assessment. The Council currently employs 13 cyclic Highway Safety Inspectors. Existing highway safety inspectors are required to refresh their formal training every 5 years and there were a number of new inspectors who required foundation training. This training is in line with national standards as set out by IHE. It is accredited by CABWI and is identified as a mandatory training requirement including refresher training for all Lancashire County Council Highway Inspectors. Refresher training was completed on
31.10.2023. Foundation training was delivered over 3 sessions on 13.11.2023, 11.12.2023 and
08.01.2024. The final course was completed on 12.01.2024.
3 On-going development and ensuring that Highway Safety Inspectors are up to date with any national changes, is delivered through targeted additional accredited training and through regular team meetings which are held monthly. b) Highway Technicians for Countrywide Maintenance The role of Highway Technicians as part of the Countywide Maintenance Team includes the responsibility to reactively respond to publicly reported defects on the maintainable vehicular highway. This role will assess and validate the reported defect in line with the Council's Highway Safety Inspection Policy and manage the delivery of a permanent repair within the response times set out in the policy. As part of a review of the role and the responsibilities required for the validation and assessment of highway defects, it was identified that to ensure Highway Technicians were suitably trained and competent in this part of their role, they should also be trained to the same standard as the Highway Safety Inspectors through on-the-job and formal accredited training. It was also identified that their operational line manager, the Assistant Operations Engineer, should also undertake formal training. A further 26 countywide staff have completed this training over 4 sessions which concluded in January
2024. The same training sessions delivered to Highway Safety Inspectors, as highlighted above, have also been delivered to Highway Technicians. c) Highway Operative The role of Highway Operatives is to drive and operate vehicles and plant to prepare and lay materials to maintain and improve the highway network as directed by the Countywide Maintenance Team compliant with site plans, and Health and Safety Legislation and completing records on hand-held IT equipment. Highway Operatives are trained to use the vehicles, plant and tools required to carry out highway defect repairs safely. They are specifically trained in the method of repair required for the wide range of highway defects that they are directed to repair. Highway Operatives work in crews of 2 or 3 and crews are made up of a Chargehand and Operative, the Chargehand having supervisory responsibility over the Operative. Chargehand are usually more experienced highway workers and have a wide and comprehensive experience of highway repairs. Highway Operatives are not required to identify or assess any defect as set out in the Highway Safety Inspection Policy, however they are given the scope to repair additional defects they may see within the area of highway contained in any traffic management already in place. The delivery of the inspection regime set out in the Highway Safety Inspection Policy is the primary responsibility of the Highway Safety Inspectors and Highway Technicians and not that of the Highway Operatives.
4 As outlined above, there is an instruction in place that Highway Operatives are not to be used for defect identification through the "find and fix" method of working, their capacity being limited to repairing additional defects to those directed where they can be seen within existing traffic management arrangements. However, in light your findings, the Council recognises that Highways Operatives would benefit from awareness training in the form of a toolbox talk to include general defect types and impacts on all types of highways users is to be delivered to all operatives. The presentation has been drafted and approved in readiness for countrywide delivery and will be delivered over a 2 week period starting on
22.01.2024. This will also set out a clear process for reporting defects to Highways Inspectors and Highways Technicians for assessment should they be seen whilst carrying out their general duties. d) Awareness Training – front line highway teams The Council has carefully considered how, in addition to formal training, continued development and awareness can be delivered to front line highway teams. The Council intends to deliver an annual workshop for highway staff who are responsible for the inspection and assessment of highway defects to ensure compliance with the Highway Safety Inspection Policy, to deliver a consistent countywide approach and to update staff on any national guidance changes and learning from operational activities. This will be arranged in April 2024 and annually thereafter.
3. Development and promotion of “LoveCleanStreets” In April 2022, the Council launched “LoveCleanStreets”, a new public reporting system to replace its web-based reporting tool. LoveCleanStreets has significant advantages over the original reporting tool, in that it can be used both as an App and in a web-based form. It also allows customers to pin the location of a defect onto a map and attach photographs. This allows the receiving maintenance team to be directed correctly to the exact location so defects can be assessed within the 2-day response time set out in the Highways Safety Inspection policy. LoveCleanStreets passes all provided information directly into the County's Highway Asset Management system where it is managed by the Countywide Teams. In April 2023 the Council’s web-based reporting system was replaced by LoveCleanStreets and all digital requests are now received via this system. Whilst the Council remains open to other forms of defect reporting for example through telephone calls, the use of LoveCleanStreets is being actively promoted as the most efficient and accurate way in which customers can advise of highway defects. Where reports are received by telephone or other means, the Customer Access Team will now create a LoveCleanStreets report to ensure that any defects are mapped accurately and can be responded to effectively.
4. Highway Safety Inspection Policy Review
5 The Council has identified that in addition to the current requirement set out in the Policy to review it as and when necessary, but especially when changes to either legislation or national guidance are introduced, an annual review of the whole policy should also be carried out. The Policy has been updated and republished to include this change. The Council has also identified that a peer review of the Highway Safety Inspection Policy could assist in identifying any changes or improvements to the current policy. The original policy was written in 2018 and was compared with other local authorities at that time. A peer authority has been commissioned and the review will start on 22.01.2024. It is anticipated that this review will take up to 8 months to complete. Although this review will consider all aspects of the Council’s Highway Safety Inspection Policy, the Council will highlight the outcome of this case and ask the reviewer to consider this as a matter of priority to ensure any additional learning or recommendations can be progressed.
5. Moss Road Strategy In light of Mr Colledge’s accident, the Council commissioned a full Geotechnical Survey of Island Lane, which was disclosed prior to the inquest. Research into increasing the longevity of moss roads is ongoing within the Council. New and innovative techniques and products (including the use of geosynthetic materials) have been trialled in several locations with varying degrees of success. Where cracking in the carriageway surface is reported, the area will be inspected by a qualified Highways Inspector to determine the depth of the cracking. If the cracking is shallow and only penetrates the surface course, the affected area can be cut out and resurfaced. Where the cracking penetrates down the superficial deposits, the affected road surface area could be cut out and the underlying road construction excavated and replaced. Alternatively, it may be possible to inject/pour material into the crack to fill the void to avoid excavating large sections of the road. Awareness of common defects on peat moss roads has been raised through the post-incident debrief, which is set out above. The Council’s current Moss Road Strategy will be reviewed by the Council’s Asset Management Team. It is anticipated that this review will be completed by April 2024. The strategy will also be re-published with any updates and will be reviewed annually from 2024.
1. Inquest Debrief Following the conclusion of the inquest, a meeting was arranged between Senior Managers to review this case and discuss your findings, which were delivered in Court on 13.10.2023, and ensure steps were put in place to address your concerns. As a result of the meeting between Senior Managers, a debrief presentation was developed containing the key facts of the case, lessons learnt, and operational instructions. This presentation was delivered to all Countywide Operational Managers and the Highway Inspection Manager on 18.10.2023. The presentation was then shared with all maintenance operational staff and Highway Safety Inspectors in a series of team meetings, which were completed by 27.10.2023. The incident debrief has also been delivered to wider Highway services to ensure a greater operational awareness. In summary, the debrief highlighted: Lancashire County Council PO Box 100, County Hall, Preston, PR1 0LD
2 That it was inappropriate to use Highway Operative staff to identify defects in a "find and fix" way, as carried out on 14.09.2022 following the series of defect reports provided by the Parish Council, and that this practice would not be used in future. That the recording of all defect reporting by the public must be managed through the service Highway Asset Management System and that any works done must also be recorded. That operational staff and Highway Safety Inspectors must be on notice of surface cracking – particularly but not exclusively, on the Moss Road Network. That operational staff and Highway Safety Inspectors must be on notice of defects which are a hazard to all road users including cyclists and non-motorised users.
2. Training In addition to the specific learning from this incident delivered through debrief sessions, the Council has developed its training programme as follows: a) Highway Safety Inspectors The role of a Highway Safety Inspector is to carry out cyclic inspections in line with the inspection regime set out in the Council’s Highway Safety Inspection Policy. The policy sets out that this role will be responsible for the identification and consequent action relating to maintainable vehicular highway defects within the bounds of Section 41 of the Highways Act 1980. It is recommended in national guidance set out in Well Managed Highways that Highway Inspectors are trained, qualified and competent in the identification of defects. The UK Roads Board sets out minimum competency standards and these are delivered through the IHE (Institute of Highways Engineers) Training and Certification scheme. Highways Authorities are required to demonstrate that Highway Safety Inspectors have been assessed against these standards. The core modules of the training undertaken by Highway Inspectors employed by the Council include: an understanding of highway law, inspection policies and procedures (including maintenance priorities, road hierarchies, inspection frequency, methods, levels, and response criteria), material recognition and measuring techniques, hazard and defect recognition (including types of defects, techniques of defect repair), health and safety, and safety inspection and assessment. The Council currently employs 13 cyclic Highway Safety Inspectors. Existing highway safety inspectors are required to refresh their formal training every 5 years and there were a number of new inspectors who required foundation training. This training is in line with national standards as set out by IHE. It is accredited by CABWI and is identified as a mandatory training requirement including refresher training for all Lancashire County Council Highway Inspectors. Refresher training was completed on
31.10.2023. Foundation training was delivered over 3 sessions on 13.11.2023, 11.12.2023 and
08.01.2024. The final course was completed on 12.01.2024.
3 On-going development and ensuring that Highway Safety Inspectors are up to date with any national changes, is delivered through targeted additional accredited training and through regular team meetings which are held monthly. b) Highway Technicians for Countrywide Maintenance The role of Highway Technicians as part of the Countywide Maintenance Team includes the responsibility to reactively respond to publicly reported defects on the maintainable vehicular highway. This role will assess and validate the reported defect in line with the Council's Highway Safety Inspection Policy and manage the delivery of a permanent repair within the response times set out in the policy. As part of a review of the role and the responsibilities required for the validation and assessment of highway defects, it was identified that to ensure Highway Technicians were suitably trained and competent in this part of their role, they should also be trained to the same standard as the Highway Safety Inspectors through on-the-job and formal accredited training. It was also identified that their operational line manager, the Assistant Operations Engineer, should also undertake formal training. A further 26 countywide staff have completed this training over 4 sessions which concluded in January
2024. The same training sessions delivered to Highway Safety Inspectors, as highlighted above, have also been delivered to Highway Technicians. c) Highway Operative The role of Highway Operatives is to drive and operate vehicles and plant to prepare and lay materials to maintain and improve the highway network as directed by the Countywide Maintenance Team compliant with site plans, and Health and Safety Legislation and completing records on hand-held IT equipment. Highway Operatives are trained to use the vehicles, plant and tools required to carry out highway defect repairs safely. They are specifically trained in the method of repair required for the wide range of highway defects that they are directed to repair. Highway Operatives work in crews of 2 or 3 and crews are made up of a Chargehand and Operative, the Chargehand having supervisory responsibility over the Operative. Chargehand are usually more experienced highway workers and have a wide and comprehensive experience of highway repairs. Highway Operatives are not required to identify or assess any defect as set out in the Highway Safety Inspection Policy, however they are given the scope to repair additional defects they may see within the area of highway contained in any traffic management already in place. The delivery of the inspection regime set out in the Highway Safety Inspection Policy is the primary responsibility of the Highway Safety Inspectors and Highway Technicians and not that of the Highway Operatives.
4 As outlined above, there is an instruction in place that Highway Operatives are not to be used for defect identification through the "find and fix" method of working, their capacity being limited to repairing additional defects to those directed where they can be seen within existing traffic management arrangements. However, in light your findings, the Council recognises that Highways Operatives would benefit from awareness training in the form of a toolbox talk to include general defect types and impacts on all types of highways users is to be delivered to all operatives. The presentation has been drafted and approved in readiness for countrywide delivery and will be delivered over a 2 week period starting on
22.01.2024. This will also set out a clear process for reporting defects to Highways Inspectors and Highways Technicians for assessment should they be seen whilst carrying out their general duties. d) Awareness Training – front line highway teams The Council has carefully considered how, in addition to formal training, continued development and awareness can be delivered to front line highway teams. The Council intends to deliver an annual workshop for highway staff who are responsible for the inspection and assessment of highway defects to ensure compliance with the Highway Safety Inspection Policy, to deliver a consistent countywide approach and to update staff on any national guidance changes and learning from operational activities. This will be arranged in April 2024 and annually thereafter.
3. Development and promotion of “LoveCleanStreets” In April 2022, the Council launched “LoveCleanStreets”, a new public reporting system to replace its web-based reporting tool. LoveCleanStreets has significant advantages over the original reporting tool, in that it can be used both as an App and in a web-based form. It also allows customers to pin the location of a defect onto a map and attach photographs. This allows the receiving maintenance team to be directed correctly to the exact location so defects can be assessed within the 2-day response time set out in the Highways Safety Inspection policy. LoveCleanStreets passes all provided information directly into the County's Highway Asset Management system where it is managed by the Countywide Teams. In April 2023 the Council’s web-based reporting system was replaced by LoveCleanStreets and all digital requests are now received via this system. Whilst the Council remains open to other forms of defect reporting for example through telephone calls, the use of LoveCleanStreets is being actively promoted as the most efficient and accurate way in which customers can advise of highway defects. Where reports are received by telephone or other means, the Customer Access Team will now create a LoveCleanStreets report to ensure that any defects are mapped accurately and can be responded to effectively.
4. Highway Safety Inspection Policy Review
5 The Council has identified that in addition to the current requirement set out in the Policy to review it as and when necessary, but especially when changes to either legislation or national guidance are introduced, an annual review of the whole policy should also be carried out. The Policy has been updated and republished to include this change. The Council has also identified that a peer review of the Highway Safety Inspection Policy could assist in identifying any changes or improvements to the current policy. The original policy was written in 2018 and was compared with other local authorities at that time. A peer authority has been commissioned and the review will start on 22.01.2024. It is anticipated that this review will take up to 8 months to complete. Although this review will consider all aspects of the Council’s Highway Safety Inspection Policy, the Council will highlight the outcome of this case and ask the reviewer to consider this as a matter of priority to ensure any additional learning or recommendations can be progressed.
5. Moss Road Strategy In light of Mr Colledge’s accident, the Council commissioned a full Geotechnical Survey of Island Lane, which was disclosed prior to the inquest. Research into increasing the longevity of moss roads is ongoing within the Council. New and innovative techniques and products (including the use of geosynthetic materials) have been trialled in several locations with varying degrees of success. Where cracking in the carriageway surface is reported, the area will be inspected by a qualified Highways Inspector to determine the depth of the cracking. If the cracking is shallow and only penetrates the surface course, the affected area can be cut out and resurfaced. Where the cracking penetrates down the superficial deposits, the affected road surface area could be cut out and the underlying road construction excavated and replaced. Alternatively, it may be possible to inject/pour material into the crack to fill the void to avoid excavating large sections of the road. Awareness of common defects on peat moss roads has been raised through the post-incident debrief, which is set out above. The Council’s current Moss Road Strategy will be reviewed by the Council’s Asset Management Team. It is anticipated that this review will be completed by April 2024. The strategy will also be re-published with any updates and will be reviewed annually from 2024.
Sent To
- Lancashire County Council
Responses Identified
Responses identified
1 of 1
56-Day Deadline
19 Apr 2024
All listed responses identified
About PFD responses
Organisations named in PFD reports must respond within 56 days explaining what actions they are taking.
Source: Courts and Tribunals Judiciary
Report Sections
Investigation and Inquest
On the 3rd January 2023 the Coroner’s Office was notified of the death of Harry College and an investigation commenced into his death. An inquest was opened and adjourned on the 17th January 2023 and a final inquest took place on the 12th and 13th October 2023. The conclusion of the inquest was that:
“Harry COLLEDGE died on the 2nd January 2023 at the Royal Preston Hospital as a result of injuries he sustained having been thrown from his bicycle. Mr COLLEDGE was an otherwise fit and healthy man who was a keen cyclist. On the 2nd of January 2023 he was cycling along Island Lane, Winmarleigh when his bicycle entered a crack defect in the carriageway, causing him to be thrown from his bicycle. This defect had been identified to the relevant Council in September 2022 and the subject of highway inspections on the 15th and 26th September 2022, involving six highways team operatives. Despite the Council's notification of the defect and its approximate location, these inspections did not identify the defect which caused Mr COLLEDGE's injuries and thus a dangerous hazard had remained on Island Lane from 9th September 2022 to 2nd January 2023.”
4. Circumstances of the death
Mr Harry Colledge was a fit and active 84 year old man. On the 2nd January 2023 he was cycling his bicycle with a friend, a common activity for Mr Colledge. He was riding along Island Lane, Winmarleigh when his bicycle entered a crack defect in the carriageway causing him to be thrown from his bicycle and sustain injuries which caused his death. The crack defect in question had been seen by local residents and members of the local Parish Council on the 9th September 2022. They took photographs of the defect and others on the road, and reported them to the Highways department at the Lancashire County Council. The senior manager who received the photographs tasked others to inspect the road and repair the defects. Four Highways operatives attended the road in two vehicles on the 15th of September 2022. The road was driven in its entirety and no defects were noticed or repaired. A second, scheduled inspection took place by Highways inspectors on the 26th of September 2022. This also involved two operatives conducting a driven inspection and neither observed the crack defect which caused Mr Colledge’s collision. Consequently the crack was not repaired and remained hazardous in the roadway at the time of Mr Colledge’s incident and death.
“Harry COLLEDGE died on the 2nd January 2023 at the Royal Preston Hospital as a result of injuries he sustained having been thrown from his bicycle. Mr COLLEDGE was an otherwise fit and healthy man who was a keen cyclist. On the 2nd of January 2023 he was cycling along Island Lane, Winmarleigh when his bicycle entered a crack defect in the carriageway, causing him to be thrown from his bicycle. This defect had been identified to the relevant Council in September 2022 and the subject of highway inspections on the 15th and 26th September 2022, involving six highways team operatives. Despite the Council's notification of the defect and its approximate location, these inspections did not identify the defect which caused Mr COLLEDGE's injuries and thus a dangerous hazard had remained on Island Lane from 9th September 2022 to 2nd January 2023.”
4. Circumstances of the death
Mr Harry Colledge was a fit and active 84 year old man. On the 2nd January 2023 he was cycling his bicycle with a friend, a common activity for Mr Colledge. He was riding along Island Lane, Winmarleigh when his bicycle entered a crack defect in the carriageway causing him to be thrown from his bicycle and sustain injuries which caused his death. The crack defect in question had been seen by local residents and members of the local Parish Council on the 9th September 2022. They took photographs of the defect and others on the road, and reported them to the Highways department at the Lancashire County Council. The senior manager who received the photographs tasked others to inspect the road and repair the defects. Four Highways operatives attended the road in two vehicles on the 15th of September 2022. The road was driven in its entirety and no defects were noticed or repaired. A second, scheduled inspection took place by Highways inspectors on the 26th of September 2022. This also involved two operatives conducting a driven inspection and neither observed the crack defect which caused Mr Colledge’s collision. Consequently the crack was not repaired and remained hazardous in the roadway at the time of Mr Colledge’s incident and death.
Similar PFD Reports
Reports sharing organisations, categories, or themes
Related Inquiry Recommendations
Public inquiry recommendations addressing similar themes
Training for IPC professionals engineers and clinicians
Scottish Hospitals Inquiry
Staff training and development
IPC role specifications and staffing levels
Scottish Hospitals Inquiry
Staff training and development
Balancing vulnerability with professional curiosity
Southport Inquiry
Staff training and development
Data sourced from Courts and Tribunals Judiciary under the Open Government Licence.