Coroner's Concerns (AI summary)
Inadequate low fencing at the railway line allowed easy access, posing a significant risk of death or injury from high-speed trains to both adults and children, despite a clear duty to prevent access.
View full coroner's concerns
During the course of the inquest the evidence revealed matters giving rise to concern. In my opinion  there is a risk that future deaths will occur unless action is taken. (1) You have a duty under the Railway Safety (Miscellaneous Provisions) Regulations 1997 to prevent  access to the railway line so far as is reasonably practicable.  (2) The fencing at the scene of Mr Key’s death was a low wooden fence which was easy to climb over.  (3) The British Transport Police (BTP) report into the death, reference CRU 2018 1711 & BTP 404‐14091,  of which you received a copy, recommended replacing the fence and gate with a heightened palisade  gate and fence. I agree with that recommendation.   (4) Trains regularly travel on this section of the track at speeds of 125 mph.  (5) Children and adults would, like Mr Key, be able to climb the wooden fence and be at risk of injury or  death on the track from passing trains.  (6) It would be reasonably practicable for you to fence the track at this point in the way suggested in the  BTP Report. 

##DW<<corAddress>> Tel ##DW<<corTel>> | Fax ##DW<<corFax>>
Responses
Network Rail Private Sector
25 Feb 2019
Action Taken
Network Rail has installed additional meshing and netting at the location. They will investigate whether affixing a mesh to the galvanised iron tubular hand rail safety rail at the top of the bridge could make this area more secure. (AI summary)
View full response
Dear Sir , RE: Regulation 28 Report Steven John (Deceased) Firstly, on behalf of all at Network Rail, would Iike to take this opportunity to express my sincere condolences to the family of Mr Key: refer to your report dated 25 February 2019 made under paragraph 7 Schedule 5 of the Coroners and Justice Act 2009 and Regulations 28 and 29 of the Coroners (Investigations) Regulations 2013 in relation to the inquest into the sad death of Steven John Network Rail takes its safety obligations seriously and has taken additional measures beyond those required by its standards, to install additional meshing and netting at this location to act as an increased deterrent to climbing: This is explained in the responses to your matters of concern: Background As noted in your report; the conclusion of the inquest was that Steven died on 14 September 2018 as a result of multiple injuries sustained after laying down on the railway track in front of an oncoming Virgin train travelling from Glasgow to London, approximately mile south of Oxenholme Railway Station, where the train driver had no opportunity for avoiding him: Response to matters of concern In your report you raise some matters of concern, which respond to below:
1. Network Rail has duty under the Railway Safety (Miscellaneous Provisions) Regulations 1997 to prevent access to the railway line s0 far a8 is reasonably practicable: Network Rail Standard NRILZITRKI51OO on the Management of Fencing & Other Boundary Measures, has been created to ensure Network Rail complies with its legal Your Key Key: very

obligations regarding fencing and boundaries, including its obligation under Regulation 3 of the Railway Safety (Miscellaneous Provisions) Regulations 1997 t0, so far as is reasonably practicable, prevent unauthorised access to rail infrastructure:
2. The fencing at the scene of Mr Key's death was a low wooden fence which was easy to climb over; The boundary measure in place at the area in question is wooden post and rail fence, with additional meshing and netting attached to the post ad wire fence to provide an additional deterrent to climbing: This fencing is subject to an annual inspection and risk assessment in accordance with NRILZITRKI51OO. The Standard requires boundary measures to be assessed according to the likelihood and consequences of unauthorised access. The likelihood of unauthorised access taking place is scored according to the risk of such access taking place. A likelihood score is given between 1 and 4, with a score of for areas at low risk of unauthorised access, for non-grazing agricultural land or remote woodland, and a score of 4 for areas at high risk of unauthorised access, where there has been recorded evidence of trespass within the last 12 months_ The consequence of unauthorised access is similarly scored between 1 and 4, where score of 1 denotes low risk consequences i.e. for track categories 5 or 6, and a score of 4 denotes very high risk consequences, i.e: thirdlfourth rail electrified, or track category 1A areas The area where Mr Key accessed the railway was last assessed on 26t July 2018. It has a likelihood score of 3, because the adjacent land is used to graze livestock and therefore the likelihood of unauthorised access is deemed to be high, and a consequence score of 3 because this is category track Track category is determined by a matrix of line speed, train frequency and tonnage. Using the matrix within NRILZITRKI51OO, this score (3 for likelihood and 3 for consequence) ordinarily requires a Class Il fence, but where, as in this case, the adjacent land is used for livestock grazing then stock fencing; i.e. a Class III fence, may be considered standard. 3 The British Transport Police report into Mr Key's death recommended replacing the fence and gate with a heightened palisade gate and fence: Network Rail grades boundary measures in terms of barrier class, with a Class barrier the most stringent type of barrier; e.g: vertical bar (palisade) , expanded metal, brick & mortar walls, concrete panels and decorative iron railings, then a Class II barrier being of a type to include welded mesh, chain link fencing or close boarded timber, and finally a Class III barrier being of a type to include post & wire (including stock netting where appropriate) , post & rail (timber or equivalent) , dry stone walls or natural features including ditches hedges and watercourses
e.g: very
e.g: being

The boundary measures in this area are equivalent to a Class Il barrier due to the installation of the additional meshing; which is in fact higher standard of barrier than required by NRILZITRK51OO This is because, given the scoring for this boundary, and as the adjacent land is grazing land, Network Rail would be permitted to utilise a Class IlI stock fence barrier. As this area has no prior evidence of trespass, a Class III boundary measure would be appropriate as per the Standard, and in effectively having a Class Il equivalent barrier in place consider that Network Rail has met its obligation to prevent unauthorised access to the railway in so far as reasonably practicable.
4. Trains regularly travel on this section of the track at speeds of 125mph: While our records indicate that the line speed at this location is 11Omph, nevertheless accept that trains do travel at high speed along this section of the track: 5 Children and adults would; like Mr Key, be able to climb the wooden fence and be at risk of injury or death on the track from passing trains. As indicated, there is no prior evidence of trespass in this area. Network Rail has process in place for monitoring incidents of trespass and designating parts of its boundary as 'hotspots' for trespass, which in turn would trigger the implementation of an action plan to mitigate the trespass risk in a particular area: This area has not met any triggers for further assessment; Notwithstanding this, Network Rail takes its safety obligations seriously, and has taken additional measures beyond those required by its standards, to install additional meshing and netting at this location to act as an increased deterrent to climbing: 6_ It would be reasonably practicable for Network Rail to fence the track at this point in the way suggested in the BTP Report: While understand the British Transport Police's recommendation to replace the fence and gate with heightened palisade gate and fence, Network Rail is responsible for looking after some 20,000 miles of track ad 30,000 bridges and it is not reasonably practicable to fence all of it with palisade. Our risk assessment process takes account of all local factors in determining the most appropriate boundary measure to implement; bearing in mind what is reasonably practicable. Unfortunately, the risk of trespass cannot be entirely eliminated even with the best of fencing; but consider that in this particular area the current boundary measures in place meet the reasonably practicable test That said, Network Rail is constantly striving to improve safety on our network and that is why we create and adhere to standards such as NRILZITRKI5IOO. In the light of Mr Key's death, we have reviewed the risk of potential trespass in this area in general and have identified the bridge wing wall and the galvanised iron tubular hand rail / safety rail at track level as an area where we could further mitigate any risk of trespass. To this end, the Route Structures Senior Asset Engineer has been

requested to investigate whether affixing a mesh to the galvanised iron tubular hand rail safety rail at the of the bridge could make this area more secure_ this response answers your concerns, but if | can be of further assistance , or if you would Iike further clarification, please do not hesitate to contact me.
Sent To
  • Network Rail
Response Status
Linked responses 1 of 1
56-Day Deadline 6 Aug 2019
All responses received
About PFD responses

Organisations named in PFD reports must respond within 56 days explaining what actions they are taking.

Source: Courts and Tribunals Judiciary

Report Sections
Investigation and Inquest
On the 16 October 2018 I commenced an investigation into the death of Steven John Key. The  investigation concluded at the end of the inquest on 25 February 2019. The conclusion of the inquest was  that on the 14 September 2018 Mr Key laid down on the railway track in front of an oncoming train,  approximately 1 mile South of Oxenholme Railway Station. He suffered multiple injuries from which he  died at the scene.  

Cause of Death: Multiple Injuries 

Coroners Conclusion: Mr Key killed himself
Circumstances of the Death
Mr Key left home on the afternoon of the 14 September 2018 and walked to the railway line  approximately 1 mile south of Oxenholme Station, at Helme Lane, Natland LA9 7PS, in Cumbria. He was  able to access the line by climbing over a low fence and up a banking. He then laid down on the track in  front of a Virgin train travelling from Glasgow to London. The driver had no opportunity for avoiding him.  He died from the injuries he received.
Copies Sent To
British Transport Police  I have also sent it to the following who may find it useful or of interest.  Department for Transport  Office of Rail and Road I am also under a duty to send the Chief Coroner a copy of your response Mr Robert Chapman Assistant Coroner County of Cumbria
Related Inquiry Recommendations

Public inquiry recommendations addressing similar themes

Replace Buried Metallic LPG Pipes
ICL Inquiry
Public Infrastructure Physical Hazards
New LPG Safety Regime
ICL Inquiry
Public Infrastructure Physical Hazards
LPG Supplier Registration
ICL Inquiry
Public Infrastructure Physical Hazards
Polyethylene Piping Research
ICL Inquiry
Public Infrastructure Physical Hazards
Limit perimeter fencing height to a maximum of 2.2 metres
Taylor Inquiry
Public Infrastructure Physical Hazards
Paint and mark all emergency gates in fences with "Emergency Exit
Taylor Inquiry
Public Infrastructure Physical Hazards
Keep all perimeter fence gates to pitch unlocked and open during matches
Taylor Inquiry
Public Infrastructure Physical Hazards
Annually inspect all crush barriers for corrosion; repair or replace as needed