Recommendation HIDD-31: Require external work to be contractual, specified by Project Manager

From Hidden Inquiry — Final Report, published 7 November 1989.

Recommendation

BR shall ensure that where work is required from areas outside the command of the person in overall charge, that work should be carried out on a contractual basis to a specification provided by the Project Manager.

Jurisdiction: UK-wide

Government response

No government response to this recommendation is on the record yet.

Delivery

No statement on delivery from British Railways Board has been found in the sources searched (last checked 27 February 2026). This is separate from the response above.

Source

Report Hidden Inquiry — Final Report 07 Nov 1989

Responsible bodies

British Railways Board Primary
Recommendation made 37.0 years ago