6. Mr E applied for the NDRHI on 21 November 2018. On 23 November, Ofgem emailed him explaining the further evidence it needed from him by 5pm on 26 November. This included a request for the following:
‘Please provide copies of planning permission relevant to your plant or official confirmation from your local planning authority that planning permission is not required’.
7. It said that failure to provide the requested information by 26 November 2018 may result in his application being ‘not properly made’. It stated that if this information is not supplied to it in time, then his application may be at risk of rejection.
8. Ofgem wrote to Mr E rejecting his application on 29 November 2018. It said if he wanted to request a formal review of the decision, he needed to do this within 28 days.
9. Mr E emailed Ofgem on 29 November 2018. He said he had contacted Ofgem before the stated deadline, saying planning permission had not been required for his property. He attached a printout from a government website which stated that planning permission was not needed ‘to use buildings already on your land for farming purposes’ or ‘to change the inside of a building’. He said his system had gone into an existing agricultural building for agricultural use and asked Ofgem to clarify why, based on the information on the government website, this was not an accepted reason for the lack of planning permission.
10. Mr E emailed Ofgem again on 13 December stating he had not received a reply. He said he had spoken to the local authority (LA) who had verbally confirmed that his understanding was correct (in that he did not need planning permission). He said the LA had agreed to put this in writing but there would be a charge for this. He said this may take ‘a day or two’ but, in the meantime, he enclosed a copy of a receipt from the LA to show he had requested this information. He said this would help him to meet Ofgem’s additional deadline of 21 December 2018.
11. On 21 December 2018, Mr E emailed Ofgem and asked it to review its decision to reject his application. He gave Ofgem copies of his previous emails. Ofgem responded on 24 December and said it was considering his review request. It sent him a further email on 23 January 2019 to say the consideration was still ongoing.
12. On 4 February 2019, Mr E emailed Ofgem again. He attached an email he had received from the LA (dated 28 January 2019) which, he said, confirmed that he did not need planning permission.
13. On 20 February 2019, Ofgem issued the outcome of its formal review and said it was upholding its original decision to reject Mr E’s application. It said this was because he had not given evidence from the relevant planning authority that planning permission was not needed (either in his original application or in response to its request for further information dated 23 November 2018). Ofgem said if he wished to request a second review (also known as a Statutory Review) of the decision, he should do this within 28 days.
14. On 18 March 2019, a solicitor contacted Ofgem on Mr E’s behalf. It said some issues had come to light which it needed to investigate and asked Ofgem to extend its review request deadline for 14 days. Ofgem responded the following day and agreed to extend the deadline until 29 March 2019.
15. Mr E emailed Ofgem on 19 March 2019. He said he was unclear why the solicitor had requested the extension on his behalf. He said he was now submitting the formal review request himself and did not need an extension to the deadline. He gave Ofgem details of information he had submitted previously, including the information he had received from the LA.
16. On 2 April 2019, a different solicitor contacted Ofgem on Mr E’s behalf and submitted a Freedom of Information (FOI) request. It asked for anonymised details of any cases where Ofgem had granted an NDRHI application despite not having received a planning permission letter or a letter from the planning authority confirming that such permission was not needed.
17. On 16 April 2019, Ofgem wrote to Mr E with the outcome of its second formal review of its decision to reject his applications under the NDRHI. It said it had seen no evidence that Mr E had supplied the needed evidence about planning permission either with his original application or in response to the request for further information. As such, it was satisfied the decision to reject his application had been correct. It invited Mr E to request a Statutory Review within 28 days if he was still unhappy.
18. On 19 April 2019, Mr E’s solicitors submitted an FOI request for anonymised details of successful NDRHI applications where the applicant had not given a planning permission letter or letter from the relevant planning authority that planning permission was not needed.
19. On 2 May 2019, Ofgem responded to Mr E’s solicitors’ FOI request. It said that, although it held the requested information, under the relevant data protection legislation, it was not required to provide it (so had decided not to ). It said the solicitor could request a review of that decision.
20. On 7 May 2019, Mr E’s solicitors emailed Ofgem and said they would be requesting a Statutory Review of its decision to refuse his NDRHI application. However, they requested an extension of time as they were still pursuing the FOI request which, in their view, would be important to the NDRHI decision.
21. On 9 May 2019, Mr E’s solicitor asked for a review of the FOI decision. On the same day, Ofgem responded to the request to extend the NDRHI review time limit and agreed to extend until seven days after Ofgem had responded to the FOI issue.
22. On 5 July 2019, Ofgem upheld its refusal of Mr E’s FOI request and informed him of his right to appeal to the Information Commissioners Office (ICO) if he was not satisfied with the outcome of its reconsideration.
23. On 8 July 2019, Mr E’s solicitor contacted Ofgem again. It said it still wished to request a Statutory Review. However, as Mr E was still intending to pursue his FOI request, the solicitor requested a further 60 days extension to submit the request. Ofgem responded on 9 July 2019. It noted that it had already responded to the FOI issue and asked why the solicitor needed more time to submit an NDRHI Statutory Review request. Ofgem said it had already granted an extension in this case.
24. On 10 July 2019, Mr E’s solicitors wrote to the ICO requesting a review of Ofgem’s response to his FOI request. It also sent a copy of this request to Ofgem. On 16 July 2019, Ofgem responded to the solicitor. It agreed to extend the deadline for submission of the NDRHI Statutory Review request until 14 August 2019.
25. On 13 August 2019, Mr E’s solicitor submitted a Statutory Review request. It referred to the information Mr E had given Ofgem previously (including information from the LA and said this was evidence he had not needed planning permission.
26. On 16 August 2019, Ofgem noted receipt of the Statutory Review request. It also asked the solicitor to provide it with details Mr E had provided to the LA when asking whether planning permission had been needed. The solicitor provided that information on 21 August 2019 (this included copies of an email exchange between Mr E and the LA).
27. On 9 September 2019, Ofgem provided its response to its Statutory Review of its decision. Ofgem said it was upholding the original decision to reject the application. It said Mr E had not given the relevant evidence about planning permission either when he first applied or when asked to do so by the required deadline. Ofgem referred to the exchanges between Mr E and the LA but noted they had not specifically related to Mr E’s property (instead, it had been a general view about whether farmers needed planning permission to change the use of farm buildings). Ofgem explained that the Statutory Review marked the final stage of its internal review process. It stated that, should Mr E be dissatisfied with its response, he could take his complaint to the Parliamentary and Health Service Ombudsman.
28. On 10 November 2020, Mr E’s solicitors wrote to Ofgem again (it had been pursuing its FOI request, first through the ICO and then through the court system). It said it had discovered that Ofgem had approved a large number of applications in the absence of planning permission and asked it to reconsider Mr E’s case because of this. Ofgem responded and said it had given its final response to the Statutory Review request and was not prepared to revisit the matter. It noted the solicitor’s comment about other applications being granted the applications and invited the solicitor to share that information so Ofgem could comment on it.