Background to the NDRHI scheme
6. The NDRHI is a government environmental programme designed to increase the use of renewable heat to help reduce carbon emissions and meet the UK’s renewable energy targets.
7. The Department for Energy Security and Net Zero (formerly the Department for Business, Energy and Industrial Strategy) closed the NDRHI scheme in Great Britain to new applicants on 31 March 2021, with some applicants able to apply up to 31 March 2023 under specific circumstances.
8. Accredited installations get quarterly payments over 20 years based on the amount of eligible heat generated. The scheme operates within England, Scotland and Wales.
9. Mrs O told us the company’s stage one application went to review. During the COVID-19 pandemic the TG application was extended and the company withdrew its application after advice from Ofgem.
10. After this, the company submitted a revised TG application. This happened five times meaning more properties could be added to the district heating scheme. Mrs O explains had the TG application been granted, this would have resulted in more NDRHI payments.
11. Mrs O says during stages one and two of the application process, the company submitted plans to show the site layout and boreholes. Importantly the plans showed they were not hydraulically connected. For the company to meet the requirements for the NDRHI scheme it had to show that the properties connected to the district heating were on a shared loop, meaning hydraulic connection for the boreholes was needed. Also, the total stated capacity for the heat pumps had to be 100kw or greater.
12. Mrs O said each property had its own heat pump and two shared a borehole, but the boreholes were not connected hydraulically. This meant the TG application was rejected. Mrs O says Ofgem did not tell the company about the requirements of the heating system at stages one and two of the TG application process and it was only told at stage three.
13. Mrs O says that if the company had known the TG would not be granted, it would have explored other options. Mrs O tells us the company feels Ofgem is negligent in the TG review process. It feels the guidance documents are not good enough as they did not explain what a shared ground loop is and there is no description of what counts as a ‘hydraulically linked’ heating system.
14. Ofgem sent its first response to Mrs O on 8 September 2022. It said the NDRHI TG application was rejected on 14 July, and it was also outside of the 28-day period for a request for a Right of Review (RoR). Ofgem explained it is not in the complaints team’s remit to overturn a decision, but it could give information on why the application was rejected.
15. The response explained the stage one consideration and how this is focused on a review of the budget and to confirm this was available for the application. It said while there was a requirement to indicate the capacity of the proposed installation, no review would be done to assess if this was eligible at stage one.
16. Ofgem said the TG application could be withdrawn if it considered a ‘material change’ during stages one and three. It explained it was the responsibility of the applicant to provide the correct details.
17. Ofgem said no evidence was given at stage one to show there were smaller installations. Ofgem also explained it was only aware of the specifics of the installation when Mrs O sent an email on 1 May. It also reminded Mrs O that technical matters would not be assessed until stage three of the application process.
18. Ofgem disagreed its approach at stage one and stage two had been ‘lax’, and said it reviewed the application in line with the guidance and regulatory requirements. It went on to say stage two only considers financial close, and this does not relate to the technical parts of the heating system installation.
19. Ofgem agreed with Mrs O’s understanding about the guidance, in particular that there were multiple shared ground loop installations. Ofgem stressed it is the applicant’s responsibility to understand the structure of the overall heat pump system including that it is made of separate installations and not a single large installation.