Building Information
Recommendations about premises information and plans
6
Recommendations
100% accepted
Government Response
Accepted (4)Accepted in Part (2)
Recommendations in This Theme
recommendation across 1 inquiry
Across 1 inquiry
Tagged Recommendations
6 total
P1-1
Accepted
Grenfell Tower Inquiry
Require external wall information for fire services
The owner and manager of every high-rise residential building be required by law to provide their local fire and rescue service with information about the design of its external walls …
- The government accepted this recommendation in principle in January 2020 (Government Response to Grenfell Tower Inquiry Phase 1 Report, MHCLG, January 2020). - The …
UK Government
P1-30
Accepted in Part
Grenfell Tower Inquiry
Require evacuation plans for high-rise buildings
The owner and manager of every high-rise residential building be required by law to draw up and keep under regular review evacuation plans, copies of which are to be provided …
- The government accepted this recommendation in principle in January 2020 (Government Response to Grenfell Tower Inquiry Phase 1 Report, MHCLG, January 2020). - The …
UK Government
P1-33
Accepted in Part
Grenfell Tower Inquiry
Require PEEP information in premises information box
The owner and manager of every high-rise residential building be required by law to include up-to-date information about persons with reduced mobility and their associated PEEPs in the premises information …
- The government accepted this recommendation in principle in January 2020 (Government Response to Grenfell Tower Inquiry Phase 1 Report, MHCLG, January 2020). - Residential …
UK Government
P1-5
Accepted
Grenfell Tower Inquiry
Require building floor plans for fire services
The owner and manager of every high-rise residential building be required by law to provide their local fire and rescue services with up-to-date plans in both paper and electronic form …
- The government accepted this recommendation in principle in January 2020 (Government Response to Grenfell Tower Inquiry Phase 1 Report, MHCLG, January 2020). - The …
UK Government
P1-6
Accepted
Grenfell Tower Inquiry
Require premises information boxes
The owner and manager of every high-rise residential building be required by law to ensure that the building contains a premises information box, the contents of which must include a …
- The government accepted this recommendation in principle in January 2020 (Government Response to Grenfell Tower Inquiry Phase 1 Report, MHCLG, January 2020). - The …
UK Government
P1-7
Accepted
Grenfell Tower Inquiry
Equip fire services to receive electronic plans
All fire and rescue services be equipped to receive and store electronic plans and to make them available to incident commanders and control room managers.
- NFCC accepted all Phase 1 recommendations directed to it (NFCC Response, 2020). - The government's Phase 1 progress report stated this recommendation is complete, …
National Fire Chiefs Cou…