52
Reflect on GDA lessons for SMR efficiency and safety cases following first completion
Conclusion
Whilst the ONR has recently adapted the GDA to be more suitable for small modular reactor (SMR) technologies, to date no SMR design has completed the entire three step process. The ONR should reflect, both during and after the first SMR has completed the GDA, on the lessons to be learned on efficiency and applying appropriate safety cases for these smaller technologies, from other similar bodies, such as the Environment Agency and Health and Safety Executive that regulate Fusion energy facilities.
Paragraph Reference
252
Government Response
A response document is linked to this report, dated 25 October 2023. Response attribution to this conclusion has not been verified. Read the response document.
Source
Inquiry
Delivering nuclear power
Report
Eighth Report - Delivering nuclear power
31 Jul 2023
HC 626
Addressee Bodies
Department for Science, Innovation and Technology
Timeline
Recommendation age
3.1 yrs
Report published
31 Jul 2023