Improving the performance of defence contracts

Public Accounts Committee Closed Inquiry
Opened: 9 Jun 2021 Closed: 5 Aug 2021 Parliament page
The National Audit Office and the Public Accounts Committee regularly report on the delays and cost overruns, across many significant Ministry of Defence (MoD) equipment procurement programmes, that have been “eroding our national defence and security for years”. Specific recent examples include boats 4-7 of the Astute attack submarine (£1 … Read more
1 Recommendation
23 Conclusions
1 Report
1 Oral session
2 Letters
1 Event
Oral evidence sessions 1 session
Improving the performance of defence contracts
Andrew Forzani · Ministry of Defence David Williams · Daily Mail Sir Simon Bollom · Ministry of Defence
Recommendations & Conclusions
24 results
2 Conclusion
Twenty-Second - Improving the perf…
We are deeply concerned about departmental witnesses’ inability or unwillingness to answer basic questions and...
We are deeply concerned about departmental witnesses’ inability or unwillingness to answer basic questions and give a frank assessment of the state of its major programmes. The Department is not sufficiently open about programme progress and risks. A few weeks … Read more
Government Response
agree with the Committee’s conclusion. The department assesses the value for money of all its investments. Value for money is evidenced and scrutinised at key approvals and assurance milestones and … Read more
HM Treasury
View details
3 Conclusion
Twenty-Second - Improving the perf…
The Department does not make enough demands of its suppliers to share the financial risks...
The Department does not make enough demands of its suppliers to share the financial risks as well as the rewards of contracting for major equipment capabilities. The Department is dependent on a limited supplier base to deliver its major equipment … Read more
Government Response
agree with the Committee’s conclusion. The department recognises the importance of managing supplier performance including the apportionment of financial and programme risk. CAAS (Cost Assurance & Analysis Service) Approvals Team … Read more
HM Treasury
View details
4 Conclusion
Twenty-Second - Improving the perf…
The Department continually fails to learn from its mistakes.
The Department continually fails to learn from its mistakes. The Department has been delivering equipment programmes for decades and has overseen many expensive failures. There have been at least 13 formal reviews of defence procurement policy over the last 35 … Read more
Government Response
agree with the Committee’s conclusion. The department has a track record of delivering savings; the underlying cost of the Defence Equipment & Support (DE&S) managed element of the Equipment Plan … Read more
HM Treasury
View details
5 Conclusion
Twenty-Second - Improving the perf…
The Department will not secure a step change in performance until it can recruit and...
The Department will not secure a step change in performance until it can recruit and retain the highly skilled staff that it requires. The Department continues to suffer from skills shortages in key areas critical to effective contract and programme … Read more
Government Response
5.1 The government agrees with the Committee’s recommendation. Target implementation date: Spring 2022 5.2 The department acknowledges that the there is a highly competitive UK market for project delivery skills … Read more
HM Treasury
View details
6 Conclusion
Twenty-Second - Improving the perf…
The Department continues to be unclear about what additional capability the taxpayer will get from...
The Department continues to be unclear about what additional capability the taxpayer will get from the extra £16.5 billion in the 2020 Spending Review. We remain to be convinced that the government’s substantial uplift to the Department’s budget will not … Read more
Government Response
agree with the Committee’s conclusion. The £16.5 billion extra funding from Spending Review 2020 will support the aims and priorities outlined in the Integrated Review to better counter developing and … Read more
HM Treasury
View details
1 Conclusion
Twenty-Second - Improving the perf…
On the basis of a report by the Comptroller and Auditor General, we took evidence...
On the basis of a report by the Comptroller and Auditor General, we took evidence from the Ministry of Defence (the Department) and Defence Equipment & Support on improving the performance of major equipment contracts.1
Government Response
On the basis of a report by the National Audit Office, the Committee took evidence on 12 July 2021 from the Ministry of Defence. The Committee published its report on … Read more
HM Treasury
View details
7 Conclusion
Twenty-Second - Improving the perf…
Cost increases or cuts to funding on the Department’s programmes can have a profound impact...
Cost increases or cuts to funding on the Department’s programmes can have a profound impact on the level of military capability that can be achieved. For example, it is procuring considerably fewer Ajax armoured vehicles and Challenger 3 tanks than … Read more
HM Treasury
View details
8 Conclusion
Twenty-Second - Improving the perf…
We questioned the Department in detail on the Ajax programme to procure armoured reconnaissance vehicles...
We questioned the Department in detail on the Ajax programme to procure armoured reconnaissance vehicles for the Army. In 2014, the Department agreed a deal with General Dynamics United Kingdom (GDUK) to procure 589 vehicles - down from an initial … Read more
Government Response
2021. This is the government’s response to the Committee’s report. Relevant reports • NAO report: Investigation into the British Business Bank’s accreditation of Greensill capital – Session 2021-22 (HC 301) … Read more
HM Treasury
View details
9 Conclusion
Twenty-Second - Improving the perf…
The Department had told the NAO that it considered initial operating capability achievable by the...
The Department had told the NAO that it considered initial operating capability achievable by the end of June 2021, but in our public evidence session, witnesses could not tell us when some sort of capability will be secured, even in … Read more
HM Treasury
View details
10 Conclusion
Twenty-Second - Improving the perf…
The Department has spent nearly £4 billion of its budget by March 2021—including payments to...
The Department has spent nearly £4 billion of its budget by March 2021—including payments to GDUK of £3.1 billion—out of budgeted whole-life costs of £5.5 billion.26 It has so far received 14 vehicles, 2% of its contractual fleet requirement.27 Witnesses … Read more
HM Treasury
View details
11 Conclusion
Twenty-Second - Improving the perf…
HM Treasury directs that Accounting Officers should confirm to Parliament that procurements remain value for...
HM Treasury directs that Accounting Officers should confirm to Parliament that procurements remain value for money (VFM) where there are significant changes to costs and schedules. The Accounting Officer had assessed eight of the projects examined by the NAO for … Read more
Government Response
The government agrees with the Committee’s recommendation. Target implementation date: Spring 2022 2.2 Although the department agrees with the Committee’s recommendation it does not agree with the Committee’s conclusion. The … Read more
HM Treasury
View details
12 Conclusion
Twenty-Second - Improving the perf…
We asked witnesses about the process for determining value for money and whether it monitors...
We asked witnesses about the process for determining value for money and whether it monitors whether programmes remain so. The Department told us that there are routine ‘touchpoints’ through a capability’s life, but acknowledged that it does not routinely take … Read more
Government Response
The government agrees with the Committee’s recommendation. Target implementation date: Spring 2022 2.2 Although the department agrees with the Committee’s recommendation it does not agree with the Committee’s conclusion. The … Read more
HM Treasury
View details
13 Recommendation
Twenty-Second - Improving the perf…
Across the 20 projects and programmes examined by the NAO, 14 are being procured partly...
Across the 20 projects and programmes examined by the NAO, 14 are being procured partly or wholly non-competitively, despite the fact that ‘competition by default’ has been departmental policy for nearly a decade. In only four of these cases was … Read more
HM Treasury
View details
14 Conclusion
Twenty-Second - Improving the perf…
The Department spends significant sums on the developmental stages of programmes while suppliers may not...
The Department spends significant sums on the developmental stages of programmes while suppliers may not be paying their fair share. The Department argued that it is standard practice to pay for work against agreed milestones across areas such as development, … Read more
Government Response
The government agrees with the Committee’s recommendation. Target implementation date: Spring 2022 3.2 Although the department agrees with the Committee’s recommendation, it does not agree with the Committee’s conclusion. The … Read more
HM Treasury
View details
15 Conclusion
Twenty-Second - Improving the perf…
Problems with supplier performance include their inability to undertake complex design work within agreed timetables,...
Problems with supplier performance include their inability to undertake complex design work within agreed timetables, difficulties in satisfying safety regulators’ requirements, and their inability to project management effectively due to under- resourcing.37 However, the Department has also contributed to problems, … Read more
HM Treasury
View details
16 Conclusion
Twenty-Second - Improving the perf…
The Department has ambitions to improve delivery performance through use of ‘agile’ procurement—delivery methods where...
The Department has ambitions to improve delivery performance through use of ‘agile’ procurement—delivery methods where the requirement and solutions are developed collaboratively in discrete steps with flexibility around requirements, cost and schedule. However, delivery teams found that agile approaches were … Read more
HM Treasury
View details
17 Conclusion
Twenty-Second - Improving the perf…
The Department’s willingness and ability to systematically record its learning from existing programmes is critical...
The Department’s willingness and ability to systematically record its learning from existing programmes is critical to securing improvements in the future. There have been at least 13 formal reviews of defence procurement policy over the last 35 years, which have … Read more
Government Response
The government agrees with the Committee’s recommendation. Target implementation date: Summer 2022 4.2 Although the department agrees with the Committee’s recommendation it does not agree with the Committee’s conclusion. The … Read more
HM Treasury
View details
18 Conclusion
Twenty-Second - Improving the perf…
The same lessons have been identified again and again across programmes, including underestimation of programme...
The same lessons have been identified again and again across programmes, including underestimation of programme complexity at the design stage, users being unclear about their requirements, the need to have sufficient resources and skills in place, and shortcomings in delivering … Read more
Government Response
The government agrees with the Committee’s recommendation. Target implementation date: Summer 2022 4.2 Although the department agrees with the Committee’s recommendation it does not agree with the Committee’s conclusion. The … Read more
HM Treasury
View details
19 Conclusion
Twenty-Second - Improving the perf…
In 2018, the Department established a Strategic Partnering Programme (SPP) to maximise commercial leverage with...
In 2018, the Department established a Strategic Partnering Programme (SPP) to maximise commercial leverage with its 19 most important suppliers by improving contract performance and managing strategic risks.45 The Department told us that the 38 C&AG’s report, para 3.16 39 … Read more
Government Response
4.5 In 2018, the department established a Strategic Partnering Programme (SPP) which is based on good practice principles, transparency and sharing of data and lessons between supplier and commissioner. Category … Read more
HM Treasury
View details
20 Conclusion
Twenty-Second - Improving the perf…
The Department has relatively more ambitious savings targets of £628 million over the next 10...
The Department has relatively more ambitious savings targets of £628 million over the next 10 years for its ‘category management’ programme. Category management involves grouping together related products and services into market ‘segments’ to generate efficiencies. The Department’s earlier attempt … Read more
Government Response
The government agrees with the Committee’s recommendation. Target implementation date: Summer 2022 4.2 Although the department agrees with the Committee’s recommendation it does not agree with the Committee’s conclusion. The … Read more
HM Treasury
View details
21 Conclusion
Twenty-Second - Improving the perf…
Having the right people in place to manage suppliers is essential to ensure programme progress...
Having the right people in place to manage suppliers is essential to ensure programme progress and to hold suppliers to account. However, many of the Department’s programmes were reliant on temporary contractors to fill these roles, especially in the Department’s … Read more
Government Response
The government agrees with the Committee’s recommendation. Target implementation date: Spring 2022 5.2 The department acknowledges that the there is a highly competitive UK market for project delivery skills ranging … Read more
HM Treasury
View details
22 Conclusion
Twenty-Second - Improving the perf…
The Department is also reliant on contractors on some of its maritime programmes, where between...
The Department is also reliant on contractors on some of its maritime programmes, where between one sixth and one third of staff working on the Spearfish, Type 31e frigate and Fleet Solid Support programme teams are contractors. The Department puts … Read more
Government Response
The government agrees with the Committee’s recommendation. Target implementation date: Spring 2022 5.2 The department acknowledges that the there is a highly competitive UK market for project delivery skills ranging … Read more
HM Treasury
View details
23 Conclusion
Twenty-Second - Improving the perf…
Senior responsible owners (SROs) have responsibility for ensuring a programme meets its objectives.
Senior responsible owners (SROs) have responsibility for ensuring a programme meets its objectives. SROs oversee governance of programmes and steer them through key decision points, assisted by a delivery team. The NAO’s analysis showed that the median time in post … Read more
Government Response
The government agrees with the Committee’s recommendation. Target implementation date: Spring 2022 5.2 The department acknowledges that the there is a highly competitive UK market for project delivery skills ranging … Read more
HM Treasury
View details
24 Conclusion
Twenty-Second - Improving the perf…
The Department secured an additional £16.5 billion in funding over the next four years in...
The Department secured an additional £16.5 billion in funding over the next four years in the 2020 Spending Review. Given the Department’s track record of short-term financial management, and schedule delays and cost growth across its programmes, we asked the … Read more
Government Response
6.2 Although the department agrees with the Committee’s recommendation, it does not agree with the Committee’s conclusion. The £16.5 billion extra funding from Spending Review 2020 will support the aims … Read more
HM Treasury
View details
Correspondence 2 letters
21 Sep 2021 Correspondence from David Williams, Permanent Secretary, Ministry of Defence, re follow up to 12 July 2021 PAC oral evidence session: Improving the performance of major equipment contracts, dated 14 September 2021
Parliament page
9 Sep 2021 Correspondence from Andrew Forzani Director General, COMRCL Ministry of Defence, re Correction related to “Improving the performance of defence contractors, HC185 dated 12 July 2021 - Fixed Priced Contracts, dated 2 August 2021
Parliament page