The Committee will question Dame Bernadette Kelly, Permanent Secretary at the Department for Transport and Mark Thurston, Chief Executive of HS2 Ltd on progress with the design and development of a new HS2 station at Euston. Questions will include how the risks to value for money are being managed, integration …
Read more
13
Recommendations
14
Conclusions
1
Report
1
Oral session
1
Letter
1
Event
Activity timeline 5 events
24 Sep
2023
2023
7 Jul
2023
2023
Report published
15 May
2023
2023
24 Apr
2023
2023
Oral evidence
24 Apr
2023
2023
Formal meeting (oral evidence session) · The Grimond Room, Portcullis House
Oral evidence sessions 1 session
24 Apr 2023
View on parliament.uk
HS2 Euston
Alan Over · Department for Transport
Dame Bernadette Kelly DCB · Department for Transport
Mark Thurston · HS2 Ltd
Reports 1 report · click to expand
| Title | HC No. | Published | Items | Response |
|---|---|---|---|---|
| Sixty-Third Report - HS2 Euston | HC 1004 | 7 Jul 2023 | 27 | Responded |
Recommendations & Conclusions
12 results
2
Conclusion
Accepted
Sixty-Third Report - HS2 Euston
Ensure realistic and affordable Euston station budget and design before restarting construction.
The £2.6 billion budget set in 2020 proved to be completely unrealistic for what the Department wanted to deliver. In April 2020, as part of the overall Phase One budget of £44.6 billion set by the Department, HS2 Ltd set …
Read more
Government Response
The government agreed, stating the Euston Reset Programme will establish a realistic budget range, assess the updated station design for affordability, and provide a new delivery-into-service date before restarting construction work.
HM Treasury
View details
4
Recommendation
Accepted
Sixty-Third Report - HS2 Euston
Establish plan with Treasury for managing inflation and HS2 programme contingency.
The Department and HM Treasury have not reached a clear understanding about how they would manage high levels of inflation on the HS2 programme, including accessing Government-held contingency. In the 2022 Autumn Statement, HM Treasury confirmed that departments needed to …
Read more
Government Response
The government agreed, outlining specific principles for accessing government-held contingency on HS2, including requirements for HS2 Ltd to use existing funds first and exceptions for Secretary of State Retained Risk events, and committed to reporting back in six months.
HM Treasury
View details
6
Conclusion
Accepted
Sixty-Third Report - HS2 Euston
Demonstrate embedded lessons from past rail projects and specific measures addressing Euston cost overruns
The Department has not yet learned lessons from managing major rail programmes. In previous examination of other rail programmes like Thameslink and the Great Western Railway modernisation we have reported very similar problems to the ones we are now seeing …
Read more
Government Response
The government agreed, outlining actions to embed lessons from past rail projects, including working with the IPA, promoting a learning culture, identifying cost drivers in the Euston Reset Programme, and sharing insights for future projects like Birmingham Curzon Street and Manchester Piccadilly.
HM Treasury
View details
7
Conclusion
Accepted
Sixty-Third Report - HS2 Euston
Department exploring minimum and value-maximisation design options for HS2 Euston station
We asked the Department to give us an indication of what a reduced design for Euston station might look like. The Department told us that it would need to examine two options before it could come to the right solution: …
Read more
Government Response
The government agrees and has commenced the Euston Reset Programme, aiming to develop an affordable Euston campus that maximizes benefits within available funding by April 2025, which reflects the committee's observation of the Department's planned options examination.
HM Treasury
View details
8
Conclusion
Accepted
Sixty-Third Report - HS2 Euston
Pause in HS2 Euston construction used to develop affordable, passenger-focused design
The Department told us that it wanted to look at all elements of the design to see where the opportunities are to deliver something that prioritises passenger benefits and wider benefits of the scheme, but also reduces costs.14 It plans …
Read more
Government Response
The government agrees and has commenced the Euston Reset Programme, aiming to develop an affordable Euston campus that maximizes benefits within available funding by April 2025, which reflects the committee's observation of the Department's plans.
HM Treasury
View details
10
Recommendation
Accepted
Sixty-Third Report - HS2 Euston
HS2 Ltd identified significant efficiencies to meet affordable overall project costs
HS2 Ltd told us that there was pressure to drive the overall HS2 cost to what was deemed to be an affordable point. It viewed the £2.6 billion as a budget to work towards and undertook a lot of work …
Read more
Government Response
The government accepts the recommendation for an affordable Euston station design, committing to the Euston Reset Programme which will set a realistic budget, assess design maturity, and provide a new delivery-into-service date by Summer 2025.
HM Treasury
View details
11
Recommendation
Accepted
Sixty-Third Report - HS2 Euston
HS2 Euston cost estimates increased to £4.8 billion, requiring substantial reductions for affordability
Later, more detailed estimates showed that the costs were likely to be significantly higher, with the 11-platform design forecast to cost as much as £4.4 billion in June 2020, and the revised 10-platform design estimated to cost £4.8 billion in …
Read more
Government Response
The government accepts the recommendation for an affordable Euston station design, committing to the Euston Reset Programme which will set a realistic budget, assess design maturity, and provide a new delivery-into-service date by Summer 2025.
HM Treasury
View details
18
Recommendation
Accepted
Sixty-Third Report - HS2 Euston
Unclear purpose and drawdown mechanisms for HS2 Phase One's £4.3 billion contingency fund.
One potential source of additional funding to help manage higher costs from inflation and also higher costs at Euston is the government-held £4.3 billion contingency. This was set by the Department in 2020 as part of the £44.6 billion budget …
Read more
Government Response
The government accepts the recommendation to clarify contingency use, outlining existing principles for accessing the £4.3 billion government-held contingency via the Development Agreement, and commits to providing a six-month update to the Committee.
HM Treasury
View details
19
Recommendation
Accepted
Sixty-Third Report - HS2 Euston
Department's HS2 reports commenced, identifying an early £0.4 billion Euston cost pressure.
In response to our May 2020 recommendation on the lack of transparency on the HS2 programme, the Department began providing six-monthly reports to Parliament on progress, including on costs.44 The Department published its first update in October 2020 and, on …
Read more
Government Response
The government agrees, noting it transparently disclosed the significant £4.8 billion revised cost estimate to Parliament via the National Audit Office when it became available, and reaffirms its commitment to upholding transparency in the HS2 programme.
HM Treasury
View details
20
Recommendation
Accepted
Sixty-Third Report - HS2 Euston
Euston cost pressure consistently reported as £0.4 billion despite expected reductions from design changes.
The Department has continued to report that the cost pressure at Euston was £0.4 billion throughout its six-monthly updates, including in the October 2022 update, which was the latest at the time we took evidence.46 Since October 2021, with the …
Read more
Government Response
The government agrees, noting it transparently disclosed the significant £4.8 billion revised cost estimate to Parliament via the National Audit Office when it became available, and reaffirms its commitment to upholding transparency in the HS2 programme.
HM Treasury
View details
21
Recommendation
Accepted
Sixty-Third Report - HS2 Euston
HS2 Euston's actual cost estimate of £4.8 billion greatly exceeded previously reported figures.
However, HS2 Ltd’s latest cost estimate of £4.8 billion is significantly higher than previously reported, at £2.2 billion over the budget.49 The Department told us that it did not know of the £4.8 billion estimate until HS2 Ltd reported it …
Read more
Government Response
The government agrees, noting it transparently disclosed the significant £4.8 billion revised cost estimate to Parliament via the National Audit Office when it became available, and reaffirms its commitment to upholding transparency in the HS2 programme.
HM Treasury
View details
22
Recommendation
Accepted
Sixty-Third Report - HS2 Euston
HS2 Ltd's two-stage procurement process delays confident cost estimates for complex projects.
HS2 Ltd explained that it had not expected to have an estimate of costs that it was confident in until the end of 2022 following work by the construction partner on a detailed, ‘bottom-up’ costing of the design.55 This followed …
Read more
Government Response
The government agrees, noting it transparently disclosed the significant £4.8 billion revised cost estimate to Parliament via the National Audit Office when it became available, and reaffirms its commitment to upholding transparency in the HS2 programme.
HM Treasury
View details
Correspondence 1 letter
15 May 2023
Correspondence from Dame Bernadette Kelly DCB, Permanent Secretary, Department for Transport, re Public Accounts Committee Hearing on HS2 Euston – Monday April 24th, 2023, dated 3 May 2023