In July 2023, the Committee reported that the Department for Transport (DfT) does not know what it is trying to achieve with the High Speed 2 station at Euston, despite spending over eight years planning and designing it. Construction work at Euston was paused for two years in March 2023. … Read more
3 Recommendations
29 Conclusions
1 Report
1 Oral session
5 Letters
1 Event
Oral evidence sessions 1 session
HS2 and Euston
Alan Over · Department for Transport Dame Bernadette Kelly DCB · Department for Transport Dr Nick Bisson · Department for Transport Sir Jon Thompson KCB · High Speed Two (HS2) Ltd
Title HC No. Published Items Response
Tenth Report - HS2 and Euston HC 67 7 Feb 2024 32 Responded
Recommendations & Conclusions
2 results
27 Conclusion Deferred
Tenth Report - HS2 and Euston
Releasing acquired Phase 2 land faces complex and time-consuming 'Crichel Down' rules.
The Department said it needed to assess what land that had been acquired for Phase 2b might need to be retained for Northern Powerhouse Rail and for some local interests, where the local authorities would like to retain the land. … Read more
Government Response
The government states it disagrees, but explains it is developing a programme for selling acquired Phase 2 land, which will balance value for money and local interests, and aims to share its plan by summer 2024.
HM Treasury
View details
29 Conclusion Deferred
Tenth Report - HS2 and Euston
Process for returning unused HS2 Phase 1 land remains painfully slow
We also highlighted that, where some Phase 1 land was going through the process of being returned (it could have been taken for temporary reasons such as utility diversions) the process had been painful and lengthy. HS2 Ltd said that … Read more
Government Response
The government states it disagrees, but explains it is developing a programme for selling acquired Phase 2 land which will balance value for money and local interests, and aims to share its plan by summer 2024, noting it will look to expedite work for compulsorily acquired land.
HM Treasury
View details
Government Response AI assessment · 32 of 3 classified

Total 3 recs + 29 conclusions
Correspondence 5 letters
10 Jan 2024 Correspondence from Sir Jon Thompson, Executive Chair, High Speed Two (HS2) Ltd, re Public Accounts Committee HS2 and Euston: Recall (16th November) follow up, dated 11 December 2023
Parliament page
10 Jan 2024 Correspondence from Dame Bernadette Kelly DCB, Permanent Secretary, Department for Transport, re Follow-up to the session of Thursday 16 November 2023 - HS2 and Euston, dated 8 December 2023
Parliament page
16 Nov 2023 Correspondence from Dame Bernadette Kelly DCB, Permanent Secretary, Department for Transport, re Accounting Officer Assessment of Decision to complete Phase 1 of HS2 – revision to BCR Range, dated 14 November 2023
Parliament page
16 Nov 2023 Correspondence from Dame Bernadette Kelly DCB, Permanent Secretary, Department for Transport, re Accounting Officer Assessment of Decision to complete Phase 1 of HS2 – Background and Overview, dated 14 November 2023
Parliament page
16 Nov 2023 Correspondence from Dame Bernadette Kelly DCB, Permanent Secretary, Department for Transport, re Accounting Officer Assessment of Decision to complete Phase 1 of HS2, dated 14 November 2023
Parliament page