Delivering value from government investment in major projects

Public Accounts Committee Closed Inquiry
Opened: 10 Jan 2024 Closed: 29 May 2024 Parliament page
Both the Committee and the National Audit Office (NAO) scrutinise how major projects are delivered, including inquiries on resetting of Government programmes and lessons from major projects and programmes . As part of this theme, the NAO’s report on delivering value from Government investment in major programmes looks at a … Read more
5 Recommendations
17 Conclusions
1 Report
1 Oral session
1 Letter
1 Event
Oral evidence sessions 1 session
Delivering value from government investment in major projects
Conrad Smewing · HM Treasury Nick Smallwood · Infrastructure and Projects Authority
Recommendations & Conclusions
7 results
2 Recommendation Not Addressed
Thirty-Second Report - Delivering …
Develop a plan to incentivise departments to conduct high-quality, independent major project evaluations.
Government departments still have few incentives to commission and carry out high-quality evaluations of major projects. High quality evaluation is an important means of providing evidence about what works, transparency about what value a project has produced, and making the … Read more
Government Response
The government agrees with the recommendation to develop a plan for incentivising evaluations, but its response discusses supplier and market engagement with SMEs and TechUK, which is irrelevant to the committee's specific request for an evaluation plan.
HM Treasury
View details
3 Recommendation Not Addressed
Thirty-Second Report - Delivering …
Analyse and issue guidance on governance for effective cross-government major projects.
There are signs of improved cross-government working but government still struggles to establish effective governance and accountability arrangements on the most complex projects where multiple departments are involved. In our February 2024 report on cross-government working in general we concluded … Read more
Government Response
The government agrees with the recommendation to analyze governance structures for cross-government working and issue guidance. However, its response focuses on the existing Digital, Data and Technology Playbook for managing digital projects, rather than addressing the broader request for general cross-government working guidance.
HM Treasury
View details
6 Recommendation Not Addressed
Thirty-Second Report - Delivering …
Outline plans for embedding cross-government learning in future major projects.
Government departments do not routinely learn lessons from their own projects or those of other departments, so are missing opportunities to improve effectiveness and efficiency of future projects. Applying learning about what has been successful in major project delivery can … Read more
Government Response
The government agrees with the recommendation to outline plans for embedding cross-government learning. However, its response outlines reviews of commercial and digital functional standards, development of a standard taxonomy, and reviews of controls and assurance frameworks, which are not direct plans for cross-government learning.
HM Treasury
View details
1 Conclusion Not Addressed
Thirty-Second Report - Delivering …
Committee took evidence from IPA and HM Treasury based on C&AG report.
On the basis of a report by the Comptroller and Auditor General, we took evidence from the Infrastructure and Projects Authority and HM Treasury.1
Government Response
The committee item is a factual statement about taking evidence from the IPA and HM Treasury. The government responds by agreeing to the 'recommendation' and detailing actions related to digital functions, a Technical Design Authority, and strategic supplier relationship management, which is irrelevant to the original statement.
HM Treasury
View details
7 Conclusion Not Addressed
Thirty-Second Report - Delivering …
High-quality evaluation essential for robust evidence, transparency, and delivering project value.
High quality evaluation is an important means of providing evidence about what works and transparency about what value a project has produced. In our May 2022 report on government’s use of evaluation and modelling, we stated: “Without the right incentives, … Read more
Government Response
Despite stating agreement, the government's response details its efforts to encourage international collaboration on antimicrobial products and antibiotic innovation, including commissioning an evaluability assessment from July 2025 to early 2026. This does not address the committee's conclusion on the importance of high-quality evaluation for major government projects.
HM Treasury
View details
8 Conclusion Not Addressed
Thirty-Second Report - Delivering …
Insufficient evaluations of government major projects, with significant departmental gaps remaining.
There are too few evaluations of government’s major projects. As we pointed out in our May 2022 report on the use of evaluation and modelling in government, in 2019, only 8% of £432 billion of spend on major projects had … Read more
Government Response
Despite stating agreement, the government's response focuses entirely on making public health a statutory objective for water companies, regulating sludge, and tackling antimicrobial resistance (AMR) in wastewater, with a White Paper planned for Autumn 2025. This does not address the committee's conclusion about the lack of evaluations for major government projects.
HM Treasury
View details
9 Conclusion Not Addressed
Thirty-Second Report - Delivering …
Persistent barriers, including political disengagement, continue to hinder effective departmental project evaluations.
In our May 2022 report on evaluation, we pointed out that the same barriers to departments doing more evaluations had been in place since 2013. These include a lack of political engagement and a lack of incentives for departments to … Read more
Government Response
Despite stating agreement, the government's response details actions related to monitoring healthcare-associated infections and antimicrobial resistance (AMR) in humans and animals, including a new data dashboard from UKHSA by Autumn 2025 and novel AMR surveillance pilots in animals until 2029. This does not address the committee's conclusion about barriers to government project evaluations.
HM Treasury
View details
Government Response AI assessment · 9 of 5 classified

Total 5 recs + 17 conclusions
Correspondence 1 letter
15 Apr 2024 Correspondence from Nick Smallwood, CEO at the Infrastructure and Projects Authority, Cabinet Office, re Follow up to the PAC hearing on delivering value from government investment in major projects (20/03/2024), dated 26 March 2024
Parliament page