Decommissioning Sellafield

Public Accounts Committee Closed Inquiry
Opened: 31 Oct 2024 Closed: 21 Aug 2025 Parliament page
The Sellafield nuclear site closed in 2003, having operated since 1950. Work began to decommission the site in 2005. Highly hazardous materials are stored there from across the UK’s nuclear industry, and it holds a legacy of contaminated buildings, untreated waste and ageing facilities. The Nuclear Decommissioning Authority (NDA), the … Read more
9 Recommendations
23 Conclusions
1 Report
1 Oral session
7 Letters
1 Event
Oral evidence sessions 1 session
Clive Maxwell · Department for Energy Security and Net Zero David Peattie · Nuclear Decommissioning Authority Euan Hutton · Sellafield Ltd Kate Bowyer · Nuclear Decommissioning Authority Lee McDonough · Department for Energy Security and Net Zero
Recommendations & Conclusions
32 results
2 Recommendation
28th Report - Decommissioning Sell…
Publish medium-term targets for Sellafield's key decommissioning activities and report annual progress.
The targets set for Sellafield Ltd neither support DESNZ and the NDA in holding it to account for poor performance, nor allow Sellafield Ltd to demonstrate it is making meaningful progress towards addressing the site’s hazards. In recent years, Sellafield … Read more
HM Treasury
View details
3 Conclusion
28th Report - Decommissioning Sell…
Require Sellafield Ltd to update Committee on plutonium analysis and alternative project costs.
Sellafield’s ability to deliver its largest projects on time and budget is still too variable. While there are some recent signs of improvement, Sellafield continues to repeat old mistakes. Four of the largest projects at Sellafield will collectively cost £1.15 … Read more
HM Treasury
View details
4 Conclusion
28th Report - Decommissioning Sell…
Require Sellafield Ltd to explain actions addressing deteriorating asset condition and maintenance team productivity.
The failure of the Replacement Analytical Project illustrates the need to improve asset management at Sellafield. Sellafield is frequently in a race against time to complete work before assets (such as buildings or equipment) reach the end of their life … Read more
HM Treasury
View details
5 Conclusion
28th Report - Decommissioning Sell…
Publish financial model scenarios to reduce NDA estate lifetime decommissioning costs, including funding constraints.
DESNZ is not doing enough to ensure that long–term value for money is achieved from decommissioning the Sellafield site. The cost of decommissioning Sellafield continues to grow – notwithstanding the billions spent on the site every year. The NDA’s tight … Read more
HM Treasury
View details
6 Recommendation
28th Report - Decommissioning Sell…
Publish bullying/harassment prevalence, staff survey results, and reporting effectiveness metrics in NDA Annual Report.
The NDA and Sellafield Ltd still have more to do to build a culture where all employees feel able to raise concerns and report poor behaviour. The exceptionally hazardous nature of many of Sellafield’s activities means that it is imperative … Read more
HM Treasury
View details
1 Conclusion
28th Report - Decommissioning Sell…
Committee took evidence on the decommissioning of the Sellafield site.
On the basis of a report by the Comptroller and Auditor General, we took evidence from the Department for Energy Security and Net Zero (the Department), the Nuclear Decommissioning Authority (the NDA) and Sellafield Ltd on the decommissioning of the … Read more
HM Treasury
View details
7 Conclusion
28th Report - Decommissioning Sell…
Magnox Swarf Storage Silo's radioactive leak persists, with emptying delayed significantly until 2054-2059.
We heard from the NDA that the Magnox Swarf Storage Silo is “the most hazardous building in the UK”. It has been leaking radioactive water into the ground since 2018–we calculated, at current rates, enough to fill an Olympic–size swimming … Read more
HM Treasury
View details
8 Recommendation
28th Report - Decommissioning Sell…
Sellafield Ltd consistently misses waste retrieval and vitrification targets since 2020 due to various issues.
Since 2020, Sellafield Ltd has missed most of its operational targets for retrieving waste, and turning liquid waste into a glass–like substance (both of which reduce the hazard the waste poses).12 It told us that the COVID–19 pandemic had had … Read more
HM Treasury
View details
9 Recommendation
28th Report - Decommissioning Sell…
Plutonium management at Sellafield shows improvement, with long-term strategy to reduce risks by 2060.
The Department, NDA and Sellafield Ltd have all taken actions to improve the management of the plutonium stored at Sellafield since the previous Committee expressed concerns about this. The previous Committee raised then the lack of a long–term strategy for … Read more
HM Treasury
View details
10 Conclusion
28th Report - Decommissioning Sell…
Sellafield Ltd consistently underperforms against strategic waste processing targets, impacting wider site cleanup plans.
Sellafield Ltd has–in conjunction with the NDA and the Office for Nuclear Regulation–set a ‘strategic tolerance’ for completing key activities. It described this to us as the date “we really want to hit”, to ensure that the site is fully … Read more
HM Treasury
View details
11 Conclusion
28th Report - Decommissioning Sell…
Sellafield Ltd plans significant acceleration of waste retrieval, requiring substantial capability development over next few years.
Sellafield Ltd has shown that it is technically possible to retrieve waste from all of its oldest ponds and silos.25 The plan to make the site less hazardous assumes that it will be able to significantly accelerate the speed it … Read more
HM Treasury
View details
12 Recommendation
28th Report - Decommissioning Sell…
Efficient waste retrieval demands constant iteration, strong performance culture, and sophisticated, transparent target setting.
We explored with the witnesses what Sellafield Ltd needs to do to reach the point where retrieving waste becomes an efficient, routine activity. As well as installing the right equipment, they emphasised the importance of “constant iteration” – addressing problems … Read more
HM Treasury
View details
13 Conclusion
28th Report - Decommissioning Sell…
Major project delays and costs at Sellafield significantly escalated since 2018 due to poor planning.
When it last took evidence on Sellafield, the previous Committee was told that major project delivery was improving.32 The NDA told it that “cost forecasting is improving” while the Department said that “for the first time now, the estimates of … Read more
HM Treasury
View details
14 Conclusion
28th Report - Decommissioning Sell…
Recent major project delivery at Sellafield shows tangible signs of improvement, with several projects on track.
DESNZ told us that it nevertheless believes that “there is some tangible evidence on improvement” and that “the overall direction of travel on project delivery is improving at the site”.36 Four of the five major projects which have been approved … Read more
HM Treasury
View details
15 Conclusion
28th Report - Decommissioning Sell…
New Programme and Project Partners (PPP) model improves major project delivery at Sellafield.
We asked the witnesses to explain what has led to the apparent improvement in how projects are now being delivered. Sellafield Ltd told us that it was now delivering its largest projects in a new way, which it calls ‘Programme … Read more
HM Treasury
View details
16 Conclusion
28th Report - Decommissioning Sell…
Improved project planning and robust assurance processes contribute to better delivery outcomes at Sellafield.
More generally, the Department and the NDA told us that they believed that there was a much greater focus on ensuring projects were well–planned. ‘Reference class forecasting’ is being used to help ensure that project baselines are realistic, and there … Read more
HM Treasury
View details
17 Conclusion
28th Report - Decommissioning Sell…
NDA and Sellafield Ltd actively share project learning and best practice group-wide.
We asked the NDA and Sellafield Ltd what they were doing to ensure that other projects benefitted from these improvements. Sellafield Ltd told us that it was looking to share learning with those projects which were being delivered under its … Read more
HM Treasury
View details
18 Conclusion
28th Report - Decommissioning Sell…
Replacement Analytical Project faced significant cost increases and delays due to inadequate planning.
A notable exception to this positive trend is the ‘Replacement Analytical Project’ (RAP) – which Sellafield Ltd now believes should be abandoned.44 This project would have refurbished a laboratory on the site so Sellafield Ltd would be able to continue … Read more
HM Treasury
View details
19 Conclusion
28th Report - Decommissioning Sell…
Sellafield Ltd adopted a new, cheaper plan for analytical services despite long-term uncertainties.
Sellafield Ltd now plans to convert a different building to support SRP, and also refurbish the existing building so it can carry on using it until 2040 (whereas RAP had been expected to remain in use until 2070).49 The NDA … Read more
HM Treasury
View details
20 Conclusion
28th Report - Decommissioning Sell…
Significant financial waste on previous projects indicates slow learning of lessons at Sellafield.
The previous Committee criticised the NDA in 2018 for failing to learn the lessons from projects it had cancelled after belatedly realising that there were more cost–effective ways to reduce risk (having spent £586 million of taxpayers’ money on three … Read more
HM Treasury
View details
21 Conclusion
28th Report - Decommissioning Sell…
Sellafield's century-long decommissioning plan faces urgent race against ageing assets.
The NDA told us that its plan for decommissioning Sellafield will take around a hundred years, and has three phases. The current phase, focussing on ‘minimising the risk of offsite consequences’ will last until approximately the 2060s; in the next … Read more
HM Treasury
View details
22 Conclusion
28th Report - Decommissioning Sell…
Increasing maintenance backlog and unknown asset conditions negatively impact Sellafield operations.
There is an increasing backlog of maintenance tasks at Sellafield which is affecting the condition of Sellafield’s assets. Sellafield Ltd could not carry out some tasks during the COVID–19 pandemic due to restrictions on working practices to prevent transmission of … Read more
HM Treasury
View details
23 Conclusion
28th Report - Decommissioning Sell…
Deteriorating asset condition poses acute risks, impeding hazard reduction and future site operations.
We explored with the witnesses the implications of assets’ condition for Sellafield Ltd’s plans to address hazards and clean up the site by 2125 and identified four areas of particular concern. Firstly – poor availability of assets has impeded Sellafield … Read more
HM Treasury
View details
24 Recommendation
28th Report - Decommissioning Sell…
Sellafield decommissioning costs have significantly risen, potentially compromising long-term value for money.
The forecast cost of decommissioning Sellafield has risen considerably since we last reported. It now stands at £136 billion, an increase of 18.8% since March 2019.68 We challenged the witnesses about the adequacy of the NDA’s budget as we are … Read more
HM Treasury
View details
25 Conclusion
28th Report - Decommissioning Sell…
Funding constraints force difficult decisions, risking long-term costs and facility obsolescence.
The NDA acknowledged that its funding settlement for 2025–26 means “there are difficult decisions to be made about some of the less critical aspects”.70 It subsequently told us that it would ideally “remove risk/ hazard and liability at the earliest … Read more
HM Treasury
View details
26 Conclusion
28th Report - Decommissioning Sell…
Department relies on NDA boards for resource allocation; lacks recent greenfield cost analysis.
We explored how the Department, as sponsor, ensures that the NDA and Sellafield Ltd achieve value for money. It told us that it was for the NDA board and the Sellafield board to decide how to allocate resources, within the … Read more
HM Treasury
View details
27 Recommendation
28th Report - Decommissioning Sell…
UKGI's role in NDA oversight remains unconvincing and unclear.
The previous Committee questioned whether UK Government Investments (UKGI) ‘is playing any useful role’ – and whether its function could instead be discharged by the Department.78 The Department told us that UKGI did help it hold the NDA to account, … Read more
HM Treasury
View details
28 Conclusion
28th Report - Decommissioning Sell…
Geological Disposal Facility project experiences significant delays and slow progress.
The NDA also needs to construct a ‘Geological Disposal Facility’ (‘GDF’) to store waste permanently – including that currently at Sellafield. This project is still at a very early stage: it needs to drill boreholes before it can even start … Read more
HM Treasury
View details
29 Recommendation
28th Report - Decommissioning Sell…
Government must improve valuing whistleblowers, addressing Sellafield mistreatment allegations.
The previous Committee took evidence on how the civil service responds to whistleblowing, and found that the government needs to do more to signal the value of whistleblowers.85 It is particularly important that everyone working on a site as hazardous … Read more
HM Treasury
View details
30 Conclusion
28th Report - Decommissioning Sell…
Sellafield believes its safety reporting processes are robust and effective.
Sellafield Ltd told us that it believed it does have a robust process for reporting safety issues as this is one of the conditions of its nuclear site licence. It pointed to the “green rating” it had received the last … Read more
HM Treasury
View details
31 Recommendation
28th Report - Decommissioning Sell…
Sellafield Ltd uses NDAs and makes significant special payments for employment claims.
The Department also considered that workers’ willingness to report safety issues is correlated with their willingness to report other poor behaviour.89 We asked about Sellafield Ltd’s use of non–disclosure agreements–a previous Public Accounts Committee report noted that these agreements have … Read more
HM Treasury
View details
32 Conclusion
28th Report - Decommissioning Sell…
Sellafield's workplace culture demonstrates improvement through new 'Speak Up' initiatives.
The NAO report recognises that there has been an improvement since 2021 in the number of employees at Sellafield who would recommend it as a great place to work.95 Sellafield Ltd informed us that the most recent survey showed a … Read more
HM Treasury
View details
Correspondence 7 letters
8 Jan 2026 To committee Letter from the Group Chief Executive of the Nuclear Decommissioning Authority relating to Decommissioning Sellafield, 12 December 2025
Parliament page
8 Jan 2026 To committee Letter from the Interim Permanent Secretary at the Department for Energy Security & Net Zero relating to Decommissioning Sellafield, 12 December 2025
Parliament page
15 Dec 2025 To committee Letter from the Chief Executive Officer of Sellafield Ltd relating to recommendations of the Committee’s Twenty-eighth Report on Decommissioning Sellafield, 04 December 2025
Parliament page
24 Nov 2025 To committee Letter from the Chair to the Permanent Secretary at the Department for Energy Security and Net Zero, the Group Chief Executive Officer at the Nuclear Decommissioning Authority and the Chief Executive Officer at Sellafield Ltd relating to Treasury Minute response – Decommissioning Sellafield, 14 November 2025
Parliament page
4 Sep 2025 To committee Letter from the Chief Executive Officer at Sellafield Limited relating to the 28th Report of Session 2024-25, Decommissioning Sellafield, Recommendation 4, 13 August 2025
Parliament page
24 Apr 2025 To committee Letter from the Group Chief Executive Officer at the Nuclear Decommissioning Authority relating to the oral evidence session held on 20 March on Decommissioning Sellafield, 04 April 2025
Parliament page
7 Apr 2025 To committee Letter from the Group Chief Executive Officer of the Nuclear Decommissioning Authority relating to Public Accounts Committee’s visit to Sellafield, March 17
Parliament page