The Energy Company Obligation 4 (ECO4) and the Great British Insulation Scheme (GBIS), both funded via energy consumers’ bills, are government schemes for the installation of energy-efficiency improvements in people’s homes, such as insulation. Not-for-profit quality assurance company TrustMark identified issues with both schemes, with government announcing in January 2025 … Read more
19 Recommendations
20 Conclusions
1 Report
1 Oral session
6 Letters
1 Event
Oral evidence sessions 1 session
Clive Maxwell CB CBE · Department for Energy Security and Net Zero Deborah Chittenden · Department for Energy Security and Net Zero Jeremy Pocklington CB · Ministry of Defence Jonathan Brearley · Department for Energy Security and Net Zero Jonathan Brearley · Ofgem Kiera Schoenemann · Ofgem Matt Gantley · United Kingdom Accreditation Service (UKAS) Simon Ayers MBE · TrustMark
Recommendations & Conclusions
9 results
3 Recommendation Accepted
62nd Report - Faulty energy effici…
Update how to protect households from unaffordable repair bills when guarantees are insufficient.
Households do not have real assurance the government will protect them from unaffordable bills when the original installer or guarantees do not cover the cost of repairs. Ministers have stated that no household should have to pay to fix the … Read more
Government Response
The government accepted the recommendation, stating that it provided responses to the Committee's three requests via a letter on 6 February 2026.
HM Treasury
View details
4 Recommendation Accepted
62nd Report - Faulty energy effici…
Review risk management and internal escalation systems to swiftly address scheme issues.
The Department’s senior officials took two years to recognise the scale of the problems, which led to many faulty installations that could have been avoided. This is unacceptable and demonstrates very poor overall supervision. The Department acted in October 2024 … Read more
Government Response
The government accepted the recommendation, stating that risk management and escalation within DESNZ are managed through formal governance. In response to issues, they have established an internal programme board, an external expert panel, and a project board for the find-and-fix programme, with a senior civil servant now observing on the TrustMark board.
HM Treasury
View details
5 Recommendation Accepted
62nd Report - Faulty energy effici…
Publish an annual report to Parliament on all retrofit schemes, non-compliance and fraud.
The Department’s system of quality assurance and consumer protection was far too complicated, and organisations within it focused too much on their own tasks rather than whether the system was protecting consumers. The ECO schemes and the retrofit quality assurance … Read more
Government Response
The government accepted the recommendation, committing to publishing an annual report to Parliament on retrofit schemes, non-compliance, and estimated fraud before Autumn 2027, to be included in the department’s Annual Report and Accounts. It will also establish a standard methodology for reporting on error and fraud for new and existing schemes.
HM Treasury
View details
7 Recommendation Accepted
62nd Report - Faulty energy effici…
Prioritise robust customer protection and remediation for all government-funded retrofit schemes
The serious failings to protect consumers on these schemes risk undermining confidence in all the Department’s retrofit schemes. The Department believes it is rebuilding confidence through the steps it has taken to date, such as suspending 38 installer businesses, implementing … Read more
Government Response
The government accepted the recommendation, affirming high priority for the find-and-fix programme and committing to wholesale reform of the consumer protection system as outlined in the Warm Homes Plan, including developing new competency frameworks.
HM Treasury
View details
25 Recommendation Accepted
62nd Report - Faulty energy effici…
Ensure Government steps in to remediate defects when other avenues are exhausted.
The Department told us that the Ministers are very clear these problems must be fixed at no cost to households who have done nothing wrong. It told us it expects only a “very small number” of homes to not be … Read more
Government Response
The government agrees with the recommendation to step in and ensure defects are remediated where all other avenues have been exhausted, even though the scheme has closed.
HM Treasury
View details
27 Recommendation Accepted
62nd Report - Faulty energy effici…
Department provided limited oversight and influence over ECO4 and GBIS schemes.
The National Audit Office reported that the Department designed both ECO and the consumer protection and quality assurance system to operate at arm’s length from government, and that the Department gave itself limited oversight and influence of ECO4 and GBIS. … Read more
Government Response
The government will publish an annual report to Parliament on its retrofit schemes, their level of non-compliance and estimated fraud, and whether the schemes are working as intended, starting before Autumn 2027. This will be included in the department's Annual Report and Accounts.
HM Treasury
View details
28 Conclusion Accepted
62nd Report - Faulty energy effici…
Available intelligence on risks and non-compliance was not escalated or consolidated effectively.
The National Audit Office reported that TrustMark only developed the analytical capabilities for identifying non-compliance trends in the latter half of 2024. Its funding model meant it did not have the free cashflow to develop these capabilities sooner.60 However, TrustMark … Read more
Government Response
The government agreed with the Committee’s recommendation. TrustMark reached full operational delivery of the find-and-fix programme in late January 2026 and currently intend for the programme to complete by May 2027 in line with ECO4 closure timeframes.
HM Treasury
View details
29 Recommendation Accepted
62nd Report - Faulty energy effici…
Department failed to act sufficiently on identified quality risks in its programme register.
Since November 2022, the Department’s programme risk register had included risks to quality, assessments and standards, yet the Department did not take sufficient action to check whether the risks were materialising, to prevent them from happening, or to escalate the … Read more
Government Response
The government states that risk management and escalation is already managed through formal governance across projects, schemes and portfolios, with risks escalated as appropriate. The department is committed to reform of our consumer protection system and has set up both an internal programme board to track progress which includes Treasury and NISTA representation, as well as an external expert panel.
HM Treasury
View details
30 Recommendation Accepted
62nd Report - Faulty energy effici…
Consumer protection and quality assurance system for ECO4 and GBIS is overly complex.
The National Audit Office’s report considered by the Committee concluded that ECO4 and GBIS combined with the consumer protection and quality assurance system resulted in an overly complex system, with many different actors. It reported that nobody spoken to during … Read more
Government Response
The Department will publish an annual report to Parliament on retrofit schemes, with the first publication before Autumn 2027. This will be included in the department’s Annual Report and Accounts.
HM Treasury
View details
Government Response AI assessment · 37 of 19 classified

Total 19 recs + 20 conclusions
Correspondence 6 letters
21 May 2026 From committee Letter to the Permanent Secretary at the Department for Energy Security and Net Zero relating to Faulty energy efficiency installations, 21 May 2026
Parliament page
23 Feb 2026 To committee Letter from the Interim Permanent Secretary at the Department for Energy Security and Net Zero relating to Recommendation 3 of the Committee’s Report on Faulty energy efficiency installations, 06 February 2026
Parliament page
12 Jan 2026 To committee Letter from the Chief Executive Officer of the Installation Assurance Authority Federation relating to the Committee’s evidence session on 13 November 2025 on Faulty energy efficiency installations, 23 December 2025
Parliament page
8 Dec 2025 To committee Letter from the Chief Executive of the UK Accreditation Service relating to the Committee’s evidence session on Faulty energy efficiency installations on 13 November 2025, 27 November 2025
Parliament page
8 Dec 2025 To committee Letter from the Interim Permanent Secretary at the Department for Energy Security and Net Zero relating to the Committee’s evidence session on Faulty energy efficiency installations on 13 November 2025, 02 December 2025
Parliament page
1 Dec 2025 To committee Letter from the Chief Operating Officer at TrustMark relating to the Committee’s evidence session on Faulty energy efficiency installations on 13 November 2025, 25 November 2025
Parliament page