27

In early 2022, HMPPS decided to outsource this role again in its re-procurement and transition...

Conclusion
In early 2022, HMPPS decided to outsource this role again in its re-procurement and transition to the new service. The NAO outlined areas where HMPPS will need to be prepared to manage risks with this approach, including: • Parties having different interpretations of what the integrator role involves and where accountability sits if problems arise; • The integrator having no contractual oversight of the other supplier; and • The potential for real or perceived conflicts of interest, given that its field services supplier will be responsible for delivering substantial work while integrating others’ work.52
Government Response

A response document is linked to this report, dated 14 December 2022. Response attribution to this conclusion has not been verified. Read the response document.

Addressee Bodies
HM Treasury
Timeline
Recommendation age 3.9 yrs
Report published 21 Oct 2022