We have examined many major transport programmes over the years, including modernising the Great Western...
Conclusion
We have examined many major transport programmes over the years, including modernising the Great Western railway, the Sheffield to Rotherham tram-train, the Thameslink programme, the A303 Stonehenge tunnel, High Speed Two and Crossrail. We have seen common issues around programmes not keeping to cost or schedule, a lack of transparency about how programmes are progressing, and weaknesses in leadership and governance.60
Government Response
A response document is linked to this report, dated 21 January 2022. Response attribution to this conclusion has not been verified. Read the response document.