Twenty-Fourth - Crossrail: A progress update

Select Committee
Public Accounts Committee HC 184 29 October 2021
Report Status Response document linked Recorded deadline: 29 Dec 2021

Missing links do not establish that no response was published. A linked document does not verify responses to individual findings.

Conclusions & Recommendations 24 items (6 recs)

No response data available yet.

Government response
Treasury minutes: Government response to the Committee of Public Accounts on the Twenty Fourth report from Session 2021-22 · published 21 Jan 2022

Recommendations & Conclusions

24 results
2 Recommendation
The collapse in passenger numbers owing to the pandemic, and subsequent bailout to TfL, has...
Recommendation
The collapse in passenger numbers owing to the pandemic, and subsequent bailout to TfL, has complicated how and when TfL and the Greater London Authority will be able to repay the taxpayer loans for Crossrail. To date, the taxpayer has … Read more
HM Treasury
View Details
3 Recommendation
It is not clear to passengers and businesses when the Elizabeth line will open or...
Recommendation
It is not clear to passengers and businesses when the Elizabeth line will open or what services will be available. The Elizabeth line services will open in stages. Services have been running on the eastern and western ends of the … Read more
HM Treasury
View Details
4 Recommendation
We are concerned that TfL and the Department do not have a plan to maximise...
Recommendation
We are concerned that TfL and the Department do not have a plan to maximise the long-term, wider economic benefits of Crossrail. When open, the Elizabeth line should increase capacity in central London by around 10%, reduce journey times, improve … Read more
HM Treasury
View Details
5 Recommendation
The Department has still not demonstrated that it is embedding lessons learned into its major...
Recommendation
The Department has still not demonstrated that it is embedding lessons learned into its major programmes. This Committee has examined many major transport programmes, such as HS2, Great Western route modernisation and Thameslink, many of which have had significant problems … Read more
HM Treasury
View Details
1 Conclusion
On the basis of a report by the Comptroller and Auditor General, we took evidence...
Conclusion
On the basis of a report by the Comptroller and Auditor General, we took evidence from the Department for Transport (the Department), Transport for London (TfL) and Crossrail Ltd on progress with the Crossrail programme.1
HM Treasury
View Details
6 Conclusion
A significant software update is needed to begin Trial Operations, which will allow up to...
Conclusion
A significant software update is needed to begin Trial Operations, which will allow up to 24 trains an hour to run through the central section.10 Any unexpected issues with software may take time to fix and we have reported on … Read more
HM Treasury
View Details
7 Conclusion
Crossrail Ltd is constructing stations along the central section which are then handed over to...
Conclusion
Crossrail Ltd is constructing stations along the central section which are then handed over to the eventual infrastructure maintainer - Rail for London Infrastructure (RfLi) or London Underground. TfL told us that completing the stations is on the critical path … Read more
HM Treasury
View Details
8 Conclusion
The estimated cost of Crossrail has increased by £1.9 billion since we last reported and...
Conclusion
The estimated cost of Crossrail has increased by £1.9 billion since we last reported and now stands at £18.9 billion.18 This excludes the £1.1 billion cost of the new trains and the depot at Old Oak Common which have historically … Read more
HM Treasury
View Details
9 Conclusion
The £1.9 billion estimated cost increase consisted of £1,510 million of Crossrail Ltd costs, and...
Conclusion
The £1.9 billion estimated cost increase consisted of £1,510 million of Crossrail Ltd costs, and £390 million of Network Rail costs. Schedule delay was the largest category of cost increase of Crossrail Ltd costs, accounting for £934 million. This was … Read more
HM Treasury
View Details
10 Recommendation
At May 2021, Crossrail Ltd estimated that its cost to complete the programme would be...
Recommendation
At May 2021, Crossrail Ltd estimated that its cost to complete the programme would be between £15,820 million and £16,008 million, with a middle value of £15,910 million. This was between £30 million and £218 million above the current funding … Read more
HM Treasury
View Details
11 Conclusion
TfL told us that further funding may not be needed if the railway is opened...
Conclusion
TfL told us that further funding may not be needed if the railway is opened earlier and everything goes to plan.29 By July 2021, Crossrail Ltd expected to have updated its plans to reflect progress and risks remaining, which would … Read more
HM Treasury
View Details
12 Conclusion
In August 2020, Crossrail Ltd announced that up to £1.1 billion of further funding would...
Conclusion
In August 2020, Crossrail Ltd announced that up to £1.1 billion of further funding would be needed to complete the programme. In December 2020, the government agreed to loan the Greater London Assembly (GLA) £825 million to complete the programme, … Read more
HM Treasury
View Details
13 Conclusion
TfL told us that it is over-reliant on income through the farebox which accounts for...
Conclusion
TfL told us that it is over-reliant on income through the farebox which accounts for 72% of TfL income. TfL compared this to New York City Transit which received 38% of its income from fares.37 It told us that COVID … Read more
HM Treasury
View Details
14 Conclusion
The Elizabeth line services will open in stages as different part of the line are...
Conclusion
The Elizabeth line services will open in stages as different part of the line are completed. Services have been running on the eastern and western ends of the line (under the brand name ‘TfL Rail’) since June 2017 and May … Read more
HM Treasury
View Details
15 Recommendation
Once the central section opens, commuters must still change to other Elizabeth line services to...
Recommendation
Once the central section opens, commuters must still change to other Elizabeth line services to continue their journeys on the eastern and western ends. The opening of full east-west services must align with national rail timetable changes which take place … Read more
HM Treasury
View Details
16 Conclusion
In April 2019 we reported that the Department, TfL and the previous Crossrail Ltd management...
Conclusion
In April 2019 we reported that the Department, TfL and the previous Crossrail Ltd management team had focussed on a fixed delivery date of December 2018, which led to warning signs that programme was in trouble being missed or ignored.45 … Read more
HM Treasury
View Details
17 Conclusion
Construction work on the programme started in 2009 and tunnelling began in 2012.47 The majority...
Conclusion
Construction work on the programme started in 2009 and tunnelling began in 2012.47 The majority of major construction work is complete and Crossrail Ltd is now transferring assets, such as stations, to Rail for London Infrastructure (RfLi) and London Underground … Read more
HM Treasury
View Details
18 Conclusion
The Department and TfL told us that, when the Elizabeth line opens, they expect it...
Conclusion
The Department and TfL told us that, when the Elizabeth line opens, they expect it to increase rail capacity in central London by around 10%, reduce journey times, and be fully accessible.50 These were the transport benefits set out in … Read more
HM Treasury
View Details
19 Conclusion
The Department and Crossrail Ltd told us about the benefits Crossrail has achieved during construction.
Conclusion
The Department and Crossrail Ltd told us about the benefits Crossrail has achieved during construction. Crossrail Ltd told us that Crossrail had “overreached” on its apprenticeship targets, achieving 1,000 apprenticeships. Many of the 1,000 were in civil engineering in the … Read more
HM Treasury
View Details
20 Conclusion
The Department told us that Crossrail had completed a property and regeneration study looking at...
Conclusion
The Department told us that Crossrail had completed a property and regeneration study looking at 2008 to 2016 which identified some 90,000 homes and four million square feet of office space resulting from Crossrail. It also noted plans in place … Read more
HM Treasury
View Details
21 Conclusion
The NAO report sets out what it would expect to see in place to achieve...
Conclusion
The NAO report sets out what it would expect to see in place to achieve benefits. It reported that the Department and TfL did not have a clear overarching benefits management strategy or plan for the Elizabeth line, but had … Read more
HM Treasury
View Details
22 Conclusion
We have examined many major transport programmes over the years, including modernising the Great Western...
Conclusion
We have examined many major transport programmes over the years, including modernising the Great Western railway, the Sheffield to Rotherham tram-train, the Thameslink programme, the A303 Stonehenge tunnel, High Speed Two and Crossrail. We have seen common issues around programmes … Read more
HM Treasury
View Details
23 Conclusion
We have asked the Department for the lessons it has learned from these experiences on...
Conclusion
We have asked the Department for the lessons it has learned from these experiences on several different occasions and we asked again at this session in July. The Department referred again to the report it had produced with the Infrastructure … Read more
HM Treasury
View Details
24 Conclusion
The Department also referred to the lessons it and HS2 Ltd have learnt from the...
Conclusion
The Department also referred to the lessons it and HS2 Ltd have learnt from the difficulties Crossrail had in integrating the 36 main works contracts and ensuring that they work together. Informed by the Crossrail experience, at our June 2021 … Read more
HM Treasury
View Details