1
On the basis of a report by the Comptroller and Auditor General, we took evidence...
Conclusion
On the basis of a report by the Comptroller and Auditor General, we took evidence from the Infrastructure and Projects Authority (the IPA) about the delivery and assurance of government major programmes.1
Government Response
A response document is linked to this report, dated 26 March 2021. Response attribution to this conclusion has not been verified. Read the response document.
Source
Committee
Public Accounts Committee
Report
Thirty-Ninth Report - Lessons from major projects and programmes
29 Jan 2021
HC 694
Addressee Bodies
HM Treasury
Timeline
Recommendation age
5.6 yrs
Report published
29 Jan 2021