The NIC agreed, stating that when building infrastructure, government needs to spend sufficient time at...

Recommendation
The NIC agreed, stating that when building infrastructure, government needs to spend sufficient time at the start deciding on the exact outcomes it wants and the ways those outcomes can be best achieved. This involves rigorous option appraisal and, critically, meaningful engagement with the public and stakeholders to understand key issues and concerns. Once the best option has been selected, government should commit to a project’s scope, essential if it wants to stick to a project’s cost forecast and delivery timeline.20
Government Response Summary
The government agrees with the recommendation, highlighting ongoing efforts to integrate deliverability and feasibility into planning, establish an outcomes-focused approach via the Public Value Framework, and implement 85 Project Speed reforms. HM Treasury will provide a detailed update to the Committee within six months.
Government Response
Accepted
HM Government Accepted
1.1 The government agrees with the Committee’s recommendations. Target implementation date: August 2021 1.2 HM Treasury has taken significant steps to ensure that the public and private sectors have the capacity to deliver on its investment commitments and this was a priority ahead of the 2020 Spending Review. To support this, government departments worked with functional experts on key programmes and deliverability and feasibility were integrated into the planning and spending process, for example by requiring departments to use the Infrastructure and Projects Authority (IPA) deliverability checklist in their spending proposals. Further scrutiny was applied by a technical appraisal panel on the analysis of specific capital proposals where required. 1.3 Spending Review 2020 also embedded a new focus on real-world outcomes and tied spending and performance more closely together, to ensure that spending delivers value for money. Provisional priority outcomes were published for each UK government department, capturing the government’s long-term policy objectives, from reducing crime to improving education standards across the country. This outcomes- focused approach is part of implementing the Public Value Framework and will place real-world outcomes front and centre in departmental planning and delivery. 1.4 HM Treasury has also established Project Speed, in collaboration with 10 Downing Street and the IPA, to deliver infrastructure projects better, greener and faster. Around 85 Project Speed reforms were announced in the National Infrastructure Strategy in November 2020. The department is now focused on implementing these reforms alongside developing new options to ensure the government is able to deliver on its investment commitments in a timely manner. 1.5 HM Treasury will write to the Committee within six months setting out further information on these measures.
Addressee Bodies
HM Treasury
Timeline
Recommendation age 5.5 yrs
Report published 29 Jan 2021