Persistent and new barriers hinder accelerated progress of cladding remediation efforts.

Conclusion
The Plan identified several barriers to remediating at pace and outlined the steps MHCLG was taking to address them. Some of these barriers are those MHCLG told the previous committee about in 2020, including landlord reluctance to come forward, limited supply chains of skilled workers needed for remediation and constrained regulatory capacity for enforcement. Others are newer, such as social housing provider capability and access to funding, developer inconsistency third–party disputes, and miserable resident experience.11
Government Response

A response document is linked to this report, dated 16 May 2025. Response attribution to this conclusion has not been verified. Read the response document.

Addressee Bodies
HM Treasury
Timeline
Recommendation age 1.5 yrs
Report published 21 Mar 2025