13
Government funding programmes exclude non-cladding fire safety defects, burdening property owners and leaseholders.
Recommendation
In their written evidence to us, the National Fire Chiefs Council (NFCC) and The Property Institute also raised concerns about the exclusion of non– cladding defects from government funded programmes. The NFCC told us there was a “large proportion” of buildings needing temporary measures— such as waking watches—to ensure life safety for serious internal fire safety issues other than cladding, and it was unclear who would pay to remediate them.18 The Property Institute told us that the exclusion of non– cladding issues undermined the integrity of building safety standards, failed to protect resident communities and placed a heavy burden on property owners and leaseholders.19
Government Response
A response document is linked to this report, dated 16 May 2025. Response attribution to this conclusion has not been verified. Read the response document.
Source
Committee
Public Accounts Committee
Report
17th Report - The Remediation of Dangerous Cladding
21 Mar 2025
HC 362
Addressee Bodies
HM Treasury
Timeline
Recommendation age
1.5 yrs
Report published
21 Mar 2025