HS2 Ltd is seeking to renegotiate unproductive civil construction contracts for better risk allocation.
Conclusion
HS2 Ltd told us that it is now seeking to renegotiate these contracts.32 It considers that the current contracts are unproductive and that reset provides the opportunity for a fair allocation of risk and an opportunity to find different ways of commercially incentivising the outcomes that it wants, rather than the ones that it is getting at the moment.33