Major HS2 contractors willing to renegotiate terms for future infrastructure programme opportunities.
Conclusion
We challenged HS2 Ltd on the feasibility of renegotiating existing contacts to deliver significant cost savings given the lack of incentives for the contractors to change terms. It told us that all major contractors have expressed willingness to discuss and work through a renegotiation as there was recognition from the private sector that better alignment of incentives between the taxpayer and the delivery of the works was necessary to reduce long–term risk. HS2 Ltd also emphasised that the major contractors would want to work on future rail and wider government infrastructure programmes and so would want to help successfully deliver HS2.34
Government Response
A response document is linked to this report, dated 16 May 2025. Response attribution to this conclusion has not been verified. Read the response document.
Source
Committee
Public Accounts Committee
Report
10th Report - HS2: Update following the Northern leg cancellation
28 Feb 2025
HC 357
Addressee Bodies
HM Treasury
Timeline
Recommendation age
1.5 yrs
Report published
28 Feb 2025