53rd Report - Cost of maintaining the FCDO’s overseas estate
Select Committee
Public Accounts Committee
HC 884
12 November 2025
Government response
Treasury minutes: Government response to the Committee of Public Accounts on the Fifth-third report from Session 2024-26 · published 19 Jan 2026
Recommendations & Conclusions
2 results
10
Conclusion
Not Addressed
Poor condition of FCDO's overseas estate presents a severe risk and significant maintenance backlog.
Conclusion
FCDO told us that it is not happy with the current condition of its overseas estate and that this presents a severe risk to the organisation.21 Of FCDO’s 6,500 overseas buildings, 933 (around 15%) do not meet its internal target …
Read more
Government Response Summary
Acknowledges the committee's conclusion that much of FCDO's overseas estate is in poor condition and has a large maintenance backlog.
HM Treasury
View Details
18
Conclusion
Not Addressed
FCDO's maintenance backlog was severely underestimated, necessitating external professionals for accurate assessment.
Conclusion
In November 2023, FCDO recognised that its £150 million estimate of its overseas estate maintenance backlog was likely to be an underestimate and commissioned professional surveyors to conduct a one-off exercise to identify the true backlog.47 FCDO ran a programme …
Read more
Government Response Summary
Acknowledges the committee's conclusion that FCDO's overseas estate is in poor condition and has a large maintenance backlog.
HM Treasury
View Details