20th Report - DCMS management of COVID-19 loans

Select Committee
Public Accounts Committee HC 364 2 April 2025
Report Status Government responded
Conclusions & Recommendations 25 items (1 rec)
Government Response (AI assessment · 25 of 25 classified)
Government response
Treasury minutes: Government response to the Committee of Public Accounts on the Twentieth report from Session 2024-25 · published 10 Jul 2025

Recommendations & Conclusions

12 results
2 Conclusion Accepted
Ensure PwC delivers full loan system functionality by September 2025 and prepare for contract end.
Conclusion
The Department’s management of its contract with PwC has been poor. The Department originally appointed PwC to advise on options for the management of its loans. After PwC identified the need for a managed service provider, the Department appointed PwC … Read more
Government Response Summary
The government states that PwC delivered the full additional functionality for the loan management system in March 2025 for under £300,000. They have extended PwC's original contract for a year for business continuity and a strategic review will inform the future requirement for a Managed Service Provider, with re-tendering planned if needed.
HM Treasury
View Details
3 Conclusion Accepted
Department lacks understanding of long-term value for money for loan book management options.
Conclusion
The Department does not yet know which options for the loan book’s future management would provide best value for the taxpayer in the long term. The costs of managing the loan book to date have been significant, at about £17 … Read more
Government Response Summary
The government states it will undertake a strategic review of the loan book programme, to be completed this financial year (2025-26), to re-assess its strategic options, including a sale or partial sale, once all borrower repayment holidays end in September 2025.
HM Treasury
View Details
4 Conclusion Accepted
Revisit loan repayment estimates and demonstrate tough management of troubled borrowers.
Conclusion
The Department is being overly optimistic in the management of its loan book in the face of continuing uncertainty over future repayments. The Department, as at October 2024 had received less in repayments than was due, the level of insolvencies … Read more
Government Response Summary
The government agrees to safeguard taxpayers' money and maximise financial returns, stating it has no current plans to provide further direct loans to sport and culture organizations. They reiterate that grants are awarded for specific projects.
HM Treasury
View Details
5 Conclusion Accepted
Compile a strategy for consistent and fair engagement with different sports borrowers.
Conclusion
The Department is displaying an inconsistent approach to its engagement with professional sports. The majority of the Department’s loans to sport bodies went to professional sport. For example, 57% (£124 million) of the Department’s sports loans went to top–tier, professional … Read more
Government Response Summary
The government is developing a comprehensive borrower engagement plan that will build on existing strategies and be guided by core principles to ensure consistent and fair engagement with different sports and borrowers.
HM Treasury
View Details
1 Conclusion Accepted
Evidence gathered on Department's management of COVID-19 loan book.
Conclusion
On the basis of a report by the Comptroller and Auditor General, we took evidence from the Department for Culture, Media and Sport (the Department) on the management of its COVID–19 loan book.1
Government Response Summary
The government will undertake a strategic review of its loan book management in the current financial year, including an external evaluation and consideration of alternative management options.
HM Treasury
View Details
9 Conclusion Accepted
Hybrid loan management approach caused integration issues and objective tension.
Conclusion
The Department did not employ a specialist loan management company. It told us that it adopted a hybrid approach, with separate loan agents for culture and sport and a managed service provider, to the management of its loan book in … Read more
Government Response Summary
The government agrees to undertake a strategic review of its loan book management by March 2026 including an external evaluation of the efficiency and effectiveness of the current operating model, and will consider alternative management options.
HM Treasury
View Details
10 Conclusion Accepted
Department increased PwC contract scope for loan management system, raising costs.
Conclusion
The Department originally commissioned PwC in 2022 to assess the different options for the long–term management of its loan book. In line with PwC’s advice, the Department decided to retain management of the loan book in–house, with day–to–day management through … Read more
Government Response Summary
The department took steps to ensure it had a robust model in place, and has received 97% of the repayments scheduled at the date of the NAO report.
HM Treasury
View Details
11 Conclusion Accepted
Department justified increased PwC contract scope for system functionality and future flexibility.
Conclusion
We observed that the above arrangements appeared favourable to PwC and that it was not unheard of for government to appoint consultants to implement the advice they have given and for the scope of such implementation work, and therefore its … Read more
Government Response Summary
The full Loan Management System (LMS) Version 2 (V2) functionality was implemented in March 2025 for under £300,000 and the original PwC contract has been extended to preserve business continuity.
HM Treasury
View Details
12 Conclusion Accepted
Loan management system launched 15 months late with ongoing functionality concerns.
Conclusion
The Department planned to have the original data platform in place in March 2023. However, the loan management system only went live in June 2024, 15 months later than originally planned. The Department’s decision to increase the scope of PwC’s … Read more
Government Response Summary
The full Loan Management System (LMS) Version 2 (V2) functionality was implemented in March 2025 for under £300,000 and the original PwC contract has been extended to preserve business continuity.
HM Treasury
View Details
13 Conclusion Accepted
Department spending additional £300,000 to resolve loan management system functionality issues
Conclusion
The Department recognised, at the time of the system going live, that it had to resolve a small number of issues to ensure the system was operating as intended, and it planned further improvements to functionality around, for example, automatic … Read more
Government Response Summary
The full Loan Management System (LMS) Version 2 (V2) functionality was implemented in March 2025 for under £300,000 and the original PwC contract has been extended to preserve business continuity.
HM Treasury
View Details
16 Conclusion Accepted
Nine borrowers became insolvent, defaulting on £46.1 million in loans, exceeding expectations
Conclusion
By October 2024, 45% of solvent borrowers had made at least one repayment on their loans, with the remaining 55% yet to make a repayment. The 45% had paid the Department £40.9 million in total, less than the £42.1 million … Read more
Government Response Summary
The department makes annual adjustments to reflect borrowers' circumstances and recognises an expected credit loss, and will revisit its strategic repayment forecasts after the repayment holiday ends in September 2025, undertaking further cost, repayment and insolvency modelling through the department’s strategic review.
HM Treasury
View Details
19 Recommendation Accepted
Department identified two potential fraud incidents totaling £2.2 million in COVID-19 loans
Recommendation
As at December 2024, the Department had identified two possible incidents of fraud among its borrowers, relating to loans valued at £2.2 million.47 It told us that it considered the level of fraud in its COVID–19 loans to be relatively … Read more
Government Response Summary
The government agrees to develop a comprehensive borrower engagement plan by November 2025 that builds on existing strategies, guided by core principles and medium-term strategies that link key borrower and loan characteristics to appropriate engagement methods.
HM Treasury
View Details