Second Report - The condition of school buildings
Select Committee
Public Accounts Committee
HC 78
19 November 2023
Recommendations
0 resultsNo recommendations found matching the selected filters. Clear filters
Conclusions (1) Observations and findings — click to expand
2
Conclusion
Accepted in Part
DfE’s risk appetite regarding the school estate, and how this aligns with its recent approach on RAAC, appears unclear. Since summer 2021, DfE has recognised a significant safety risk across the school estate. In spring 2023, it continued to assess that its mitigations would not bring the risk likelihood down …
Government Response Summary