Fifty-Third Report - The performance of UK Security Vetting

Select Committee
Public Accounts Committee HC 994 12 May 2023
Report Status Government responded
Conclusions & Recommendations 24 items (4 recs)
Government Response (AI assessment · 24 of 24 classified)
Government response
Treasury minutes: Government response to the Committee of Public Accounts on the Fifty-third report from Session 2022-23 · published 21 Jul 2023

Recommendations & Conclusions

3 results
20 Conclusion Deferred
UKSV's £40 million transformation programme business cases have faced repeated rejection by COAB.
Conclusion
UKSV has been trying, largely unsuccessfully, to modernise the vetting system since it launched a Vetting Reform programme in 2019.50 UKSV’s Chief Executive said, “if we had a magic wand and we could build a new system tomorrow, we absolutely … Read more
Government Response Summary
The Cabinet Office has contracted external support for a 10-week enhanced discovery to review delivery models for Vetting Transformation, with outputs forming an Outline Business Case for consideration in October 2023.
HM Treasury
View Details
22 Conclusion Deferred
Previous IT modernisation efforts led to significant budget overruns and project failures for UKSV.
Conclusion
As part of the Vetting Reform programme, the Cabinet Office planned to replace UKSV’s legacy IT system, the National Security Vetting System, through the Future Vetting System programme, by February 2020 at a cost of £19 million. Failures in project … Read more
Government Response Summary
The Cabinet Office has commissioned a 10-week enhanced discovery phase with external support to review delivery models for Vetting Transformation, which will inform an Outline Business Case to be considered in October 2023.
HM Treasury
View Details
23 Conclusion Deferred
Cabinet Office's cautious approach delays Vetting Transformation programme following past IT modernisation failures.
Conclusion
The Cabinet Office told us that following its bad experience with its first attempt to modernise IT, it was now adopting a more cautious approach to transformation, and that it rejected the business plan for the Vetting Transformation programme on … Read more
Government Response Summary
The Cabinet Office has contracted external support for a 10-week discovery phase to review and advise on Vetting Transformation delivery models, with outputs forming an Outline Business Case for consideration in October 2023.
HM Treasury
View Details