Ninth Report - Revised (Draft) National Policy Statement for Energy
Select Committee
Business and Trade Committee
HC 1151
25 February 2022
Recommendations
1 results
2
Accepted in Part
Para 24
As currently drafted, revised (draft) EN-1 does not provide the “step change” needed to deliver...
Recommendation
As currently drafted, revised (draft) EN-1 does not provide the “step change” needed to deliver the required scale of new NSIPs at a sufficiently rapid pace to deliver the Government’s net zero aims. This is largely due to ambiguity in …
Read more
Government Response Summary
The government states that NPSs will start with a presumption in favour of granting consent to applications for energy NSIPs and draft EN-1 has been updated to introduce a new policy presumption known as a critical national priority (CNP) for offshore wind.
Department for Business and Trade