Timeline

Key dates in the inquiry's progress, assembled from its recorded milestones and hearing phases.

Hearing-phase dates are taken from the published hearing days; some earlier milestone dates are approximate where the inquiry has not published an exact date.

Milestones & hearing phases

Milestone Hearing phase Reports & costs Still to come
5 Jun 2014
Inquiry Announced
Scottish Ministers established an inquiry into the Edinburgh Tram Project.
12 Jun 2014
Chair and Terms of Reference announced
12 Jul 2014
Chair appointed by letter
5 Sep 2017 to 24 May 2018
Evidential hearings
59 sitting days
22 Mar 2018
Oral evidence ends
19 Sep 2023
Final Report Published
Report published with 24 recommendations.
31 Jan 2024
Government Response
Scottish Government response to recommendations.
1 Sep 2026
Inquiry Closed
Lord Hardie notified the First Minister that the inquiry had ended and published an explanatory note.