Edinburgh Tram Inquiry
CompletedPublic inquiry into why the Edinburgh Trams project was delivered late, over budget, and with a reduced scope. The project cost £776m against an original estimate of £375m and took 5 years longer than planned.
Live tracking hearings, witnesses and documents synced daily from the inquiry website
Open live tracker
Search evidence
8 years, 10 months
Duration
£13.2m
Total Cost
100
Witnesses
160
Hearing Days
7
Core Participants
6,000,000
Documents
961
Report Pages
Reports (1) Click to expand
| Title | Volume | Publication Date | Tracked recs | Links |
|---|---|---|---|---|
| Edinburgh Tram Inquiry Report | Final Report | 01 Aug 2023 | 24 |
Timeline (6) Click to expand
05 Jun 2014
Inquiry Announced
Scottish Ministers established an inquiry into the Edinburgh Tram Project.
Source
03 Jul 2014
Chair Appointed
Lord Hardie appointed as Chair.
08 Sep 2014
Terms of Reference Set
Inquiry to examine why project was delayed and over budget.
09 Mar 2017
Hearings Begin
Evidence hearings commenced.
31 Jan 2024
Government Response
Scottish Government response to recommendations.
Recommendations (24)
Public Inquiry Efficiency
Recommendation
Scottish Ministers should undertake a review of public inquiries to determine the most cost-effective method of avoiding delay in the establishment of an inquiry, including consideration of establishing a dedicated unit within the Scottish Courts and Tribunals Service and publishing …
Read more
Published evidence summary
- In November 2023, the Scottish Government stated that guidance on efficient public inquiry establishment was "already in development" and had been shared with recent inquiries (Transport Secretary Statement on Edinburgh Tram Inquiry Report, Scottish Government, 2 November 2023).
- In November 2025, the Scottish Government published "Public inquiries: guidance for Ministers and officials", providing guidance on whether an inquiry should be established, covering statutory and non-statutory options, independence requirements, cost and timing considerations, powers available, interaction with parallel investigations, ECHR obligations, and alternative mechanisms (Public inquiries: guidance for Ministers and officials, Scottish Government, 24 November 2025).
- In November 2025, the Scottish Government published "Public inquiries: guidance for Ministers and officials", providing guidance on whether an inquiry should be established, covering statutory and non-statutory options, independence requirements, cost and timing considerations, powers available, interaction with parallel investigations, ECHR obligations, and alternative mechanisms (Public inquiries: guidance for Ministers and officials, Scottish Government, 24 November 2025).
Scottish Government
(Primary)
View Details
Inquiry Independence
Recommendation
In any event Scottish Ministers should not appoint as the sponsor of any public inquiry any department, agency or other government organisation where it, or any of its employees, has had any involvement in the project or other event giving …
Read more
Published evidence summary
- In November 2023, the Scottish Government stated that guidance similar to that suggested was already in development (Transport Secretary Statement on Edinburgh Tram Inquiry Report, Scottish Government, 2 November 2023).
- In November 2025, the Scottish Government published "Public inquiries: guidance for Ministers and officials", which addresses independence requirements for inquiries, including considerations around the relationship between the sponsoring body and the subject matter under investigation (Public inquiries: guidance for Ministers and officials, Scottish Government, 24 November 2025).
- In November 2025, the Scottish Government published "Public inquiries: guidance for Ministers and officials", which addresses independence requirements for inquiries, including considerations around the relationship between the sponsoring body and the subject matter under investigation (Public inquiries: guidance for Ministers and officials, Scottish Government, 24 November 2025).
Scottish Government
(Primary)
View Details
Staffing Guidance
Recommendation
The guidance mentioned in the first recommendation should include: advice concerning the circumstances in which civil servants in the inquiry team may properly transfer to posts, other than promoted posts, within other government departments or agencies; which positions within the …
Read more
Published evidence summary
- In November 2023, the Scottish Government stated that guidance similar to that suggested was already in development (Transport Secretary Statement on Edinburgh Tram Inquiry Report, Scottish Government, 2 November 2023).
- In November 2025, the Scottish Government published "Public inquiries: guidance for Ministers and officials", which covers staffing and resourcing considerations for inquiries (Public inquiries: guidance for Ministers and officials, Scottish Government, 24 November 2025).
- No published guidance specifically addressing circumstances for civil servant transfers, which positions may use agency staff, and suitability of temporary contracts has been identified separately from the general inquiry guidance to March 2026.
- In November 2025, the Scottish Government published "Public inquiries: guidance for Ministers and officials", which covers staffing and resourcing considerations for inquiries (Public inquiries: guidance for Ministers and officials, Scottish Government, 24 November 2025).
- No published guidance specifically addressing circumstances for civil servant transfers, which positions may use agency staff, and suitability of temporary contracts has been identified separately from the general inquiry guidance to March 2026.
Scottish Government
(Primary)
View Details
Inquiry Cost Transparency
Recommendation
In reporting the cost of a public inquiry Scottish Ministers should report its net cost to the public purse, after discounting expenditure already incurred on accommodation, staff and other resources, as well as the total cost appearing in the accounts …
Read more
Published evidence summary
- In November 2023, the Scottish Government stated that guidance similar to that suggested was already in development (Transport Secretary Statement on Edinburgh Tram Inquiry Report, Scottish Government, 2 November 2023).
- In November 2025, the Scottish Government published "Public inquiries: guidance for Ministers and officials", which addresses cost considerations for inquiries (Public inquiries: guidance for Ministers and officials, Scottish Government, 24 November 2025).
- No published guidance specifically requiring disclosure of net costs to the public purse (excluding pre-existing staffing and accommodation costs) alongside total departmental account costs has been identified to March 2026.
- In November 2025, the Scottish Government published "Public inquiries: guidance for Ministers and officials", which addresses cost considerations for inquiries (Public inquiries: guidance for Ministers and officials, Scottish Government, 24 November 2025).
- No published guidance specifically requiring disclosure of net costs to the public purse (excluding pre-existing staffing and accommodation costs) alongside total departmental account costs has been identified to March 2026.
Scottish Government
(Primary)
View Details
Business Case Timing
Recommendation
Where the Business Case for any future light rail project is based upon an assumption that, prior to the award of the contract for the construction of the infrastructure, certain matters will have been completed (e.g. design, the obtaining of …
Read more
Published evidence summary
- In November 2023, the Scottish Government stated it already operates in line with best practices for governance and light rail delivery (Transport Secretary Statement on Edinburgh Tram Inquiry Report, Scottish Government, 2 November 2023).
- No published updated guidance specifically requiring revised Business Cases where pre-contract assumptions on design, approvals, or utility diversions have not been met has been identified to March 2026.
- No published updated guidance specifically requiring revised Business Cases where pre-contract assumptions on design, approvals, or utility diversions have not been met has been identified to March 2026.
Scottish Government
(Primary)
View Details
Optimism Bias in Business Cases
Recommendation
All versions of the Business Case, including any Business Case required as a result of altered assumptions, should include an assessment of risk that takes account of optimism bias in accordance with the current published government guidance.
Published evidence summary
- In November 2023, the Scottish Government stated it already operates in line with best practices for governance and light rail delivery (Transport Secretary Statement on Edinburgh Tram Inquiry Report, Scottish Government, 2 November 2023).
- Scottish Government Green Book supplementary guidance requires consideration of optimism bias in Business Cases, but no published update specifically responding to this recommendation has been identified to March 2026.
- Scottish Government Green Book supplementary guidance requires consideration of optimism bias in Business Cases, but no published update specifically responding to this recommendation has been identified to March 2026.
Scottish Government
(Primary)
View Details
External Peer Review
Recommendation
The assessment of risk at each stage mentioned in Recommendation 6 should be the subject of a peer review by external consultants with experience of similar large-scale infrastructure projects in the transportation sector who should submit a report of each …
Read more
Published evidence summary
- In November 2023, the Scottish Government stated it already operates in line with best practices for governance and light rail delivery (Transport Secretary Statement on Edinburgh Tram Inquiry Report, Scottish Government, 2 November 2023).
- No published requirement for mandatory external peer review of Business Case risk assessments for large-scale transportation infrastructure projects has been identified to March 2026.
- No published requirement for mandatory external peer review of Business Case risk assessments for large-scale transportation infrastructure projects has been identified to March 2026.
Scottish Government
(Primary)
View Details
Update Optimism Bias Guidance
Recommendation
The existing Guidance on optimism bias was based on empirical data available almost two decades ago and should be revised to take into account the additional data that is now available. In particular, the reference classes should be updated to …
Read more
Published evidence summary
- In November 2023, the Scottish Government stated it already operates in line with best practices but would consider updating guidance (Transport Secretary Statement on Edinburgh Tram Inquiry Report, Scottish Government, 2 November 2023).
- No published update to optimism bias guidance incorporating light rail project data or reflecting current empirical evidence has been identified to March 2026.
- No published update to optimism bias guidance incorporating light rail project data or reflecting current empirical evidence has been identified to March 2026.
Scottish Government
(Primary)
View Details
Risk Management Standards
Recommendation
The identification and management of risk should be an integral part of the governance of all major public-sector contracts in future. In identifying and managing risk the following principles should be adopted: • Probabilistic forecasts rather than single-point forecasts should …
Read more
Published evidence summary
- In November 2023, the Scottish Government stated it already operates in line with best practices for governance and light rail delivery (Transport Secretary Statement on Edinburgh Tram Inquiry Report, Scottish Government, 2 November 2023).
- No published updated guidance specifically addressing probabilistic forecasting, early warning detection, and quality-focused evidence for major public sector contracts has been identified to March 2026.
- No published updated guidance specifically addressing probabilistic forecasting, early warning detection, and quality-focused evidence for major public sector contracts has been identified to March 2026.
Scottish Government
(Primary)
View Details
Joint Working Group with COSLA
Recommendation
In the interests of protecting the public purse and maximising the benefits from public expenditure on major projects, the Scottish Ministers should contemplate establishing a joint working group consisting of officials in Transport Scotland and representatives of the Convention of …
Read more
Published evidence summary
- In November 2023, the Scottish Government stated that "effective collaboration sits at the heart of this Government" and cited the Verity House Agreement as a testament to its collaborative approach with local government (Transport Secretary Statement on Edinburgh Tram Inquiry Report, Scottish Government, 2 November 2023).
- No published evidence that a specific joint working group with COSLA representatives has been established to leverage Transport Scotland's project management experience for light rail projects has been identified to March 2026.
- No published evidence that a specific joint working group with COSLA representatives has been established to leverage Transport Scotland's project management experience for light rail projects has been identified to March 2026.
Scottish Government
(Primary)
View Details
Public Fund Protection
Recommendation
The Scottish Ministers and local authorities responsible for funding light rail projects should be mindful at all times of their obligation to protect public funds and to obtain value for public expenditure. In that regard: • the Scottish Ministers should …
Read more
Published evidence summary
- In November 2023, the Scottish Government stated that while responsibility for delivery remains with councils as project leads, the Government committed to championing closer working through the Verity House Agreement (Transport Secretary Statement on Edinburgh Tram Inquiry Report, Scottish Government, 2 November 2023).
- No published updated guidance specifically requiring conditional grant payments with review hold points, critical review of Business Cases, or Scottish Government involvement in project delivery for light rail has been identified to March 2026.
- No published updated guidance specifically requiring conditional grant payments with review hold points, critical review of Business Cases, or Scottish Government involvement in project delivery for light rail has been identified to March 2026.
Scottish Government
(Primary)
View Details
Record Keeping Requirements
Recommendation
For reasons of transparency and accountability for public expenditure, the Scottish Ministers should keep minutes of: • the nature and content of any discussions and the reasons for any decisions taken at all meetings, discussions or telephone conversations, and in …
Read more
Published evidence summary
- In November 2023, the Scottish Government stated that "robust and enhanced procedures regarding minute-taking and documentation management have also been embedded within the Government and the Civil Service" (Transport Secretary Statement on Edinburgh Tram Inquiry Report, Scottish Government, 2 November 2023).
- No independently published assessment of whether the enhanced documentation procedures are operating effectively in relation to publicly funded major projects has been identified to March 2026.
- No independently published assessment of whether the enhanced documentation procedures are operating effectively in relation to publicly funded major projects has been identified to March 2026.
Scottish Government
(Primary)
View Details
Utility Diversion Planning
Recommendation
The procurement strategy for any future light rail project should make adequate provision for the uncertainties concerning the location of utilities and redundant equipment belonging to present and past utility companies, particularly in urban centres. In particular, although it is …
Read more
Published evidence summary
- In November 2023, the Scottish Government stated it already operates in line with best practices for governance and light rail delivery (Transport Secretary Statement on Edinburgh Tram Inquiry Report, Scottish Government, 2 November 2023).
- No published updated procurement guidance specifically addressing utility location uncertainties, requiring route exposure and clearance before construction, has been identified to March 2026.
- No published updated procurement guidance specifically addressing utility location uncertainties, requiring route exposure and clearance before construction, has been identified to March 2026.
Scottish Government
(Primary)
View Details
Utility Diversion Risk Management
Recommendation
Although some participants in the Inquiry criticised the use of MUDFA to divert utilities in advance of the infrastructure works and advocated the “bow wave” approach to the diversion of utilities that followed the mediation settlement at Mar Hall, I …
Read more
Published evidence summary
- In November 2023, the Scottish Government stated it already operates in line with best practices for governance and light rail delivery (Transport Secretary Statement on Edinburgh Tram Inquiry Report, Scottish Government, 2 November 2023).
- No published updated guidance specifically addressing utility diversion risk management approaches has been identified to March 2026.
- No published updated guidance specifically addressing utility diversion risk management approaches has been identified to March 2026.
Scottish Government
(Primary)
View Details
Qualified Project Management
Recommendation
In recognition of the various difficulties likely to be experienced in the design and construction of a light rail project through a city centre, the promoter and owner of the project should appoint as its procurement and project manager a …
Read more
Published evidence summary
- In November 2023, City of Edinburgh Council Leader Cammy Day stated that the Council broadly agreed with Lord Hardie's recommendations and noted improvements had been implemented for the successful delivery of the Trams to Newhaven project (City of Edinburgh Council response, November 2023).
- In a subsequent Council committee report (16 November 2023), the Council noted that the Trams to Newhaven project had demonstrated improved procurement and project management practices (City of Edinburgh Council Committee Report, 16 November 2023).
- No published formal framework requiring appointment of experienced permanent employees for light rail project management has been identified to March 2026.
- In a subsequent Council committee report (16 November 2023), the Council noted that the Trams to Newhaven project had demonstrated improved procurement and project management practices (City of Edinburgh Council Committee Report, 16 November 2023).
- No published formal framework requiring appointment of experienced permanent employees for light rail project management has been identified to March 2026.
City of Edinburgh Council
(Primary)
View Details
Design Engagement Process
Recommendation
Immediately following the appointment of the designer, and throughout the design of the project, the designer should engage with the promoter and owner of the project, the procurement and project manager, the local planning authority, the utility companies and interested …
Read more
Published evidence summary
- In November 2023, the Council stated it broadly agreed with Lord Hardie's recommendations, noting improvements had been implemented for Trams to Newhaven (City of Edinburgh Council response, November 2023).
- The Council committee report (16 November 2023) acknowledged that the original tram project lacked a single point of contact to coordinate design responses, and that this had been addressed in the Newhaven project (City of Edinburgh Council Committee Report, 16 November 2023).
- No published formal guidance requiring continuous engagement between promoters, owners, and planning authorities on design criteria for future light rail projects has been identified to March 2026.
- The Council committee report (16 November 2023) acknowledged that the original tram project lacked a single point of contact to coordinate design responses, and that this had been addressed in the Newhaven project (City of Edinburgh Council Committee Report, 16 November 2023).
- No published formal guidance requiring continuous engagement between promoters, owners, and planning authorities on design criteria for future light rail projects has been identified to March 2026.
City of Edinburgh Council
(Primary)
View Details
Governance Structure
Recommendation
The governance structure for the delivery of a major project such as a light rail scheme should follow the published guidance and should ensure that there is clarity regarding the respective roles of the various bodies and individuals involved in …
Read more
Published evidence summary
- In November 2023, the Council stated it broadly agreed with Lord Hardie's recommendations, noting that governance improvements had been implemented for Trams to Newhaven (City of Edinburgh Council response, November 2023).
- The Council committee report (16 November 2023) acknowledged difficulties in the governance of the first phase due to complexity in the governance structure and lack of understanding by individuals of their roles and responsibilities (City of Edinburgh Council Committee Report, 16 November 2023).
- No published updated governance framework specifically prohibiting the chairman of a procurement company from also serving as its chief executive has been identified to March 2026.
- The Council committee report (16 November 2023) acknowledged difficulties in the governance of the first phase due to complexity in the governance structure and lack of understanding by individuals of their roles and responsibilities (City of Edinburgh Council Committee Report, 16 November 2023).
- No published updated governance framework specifically prohibiting the chairman of a procurement company from also serving as its chief executive has been identified to March 2026.
City of Edinburgh Council
(Primary)
View Details
Interviews of Key Personnel in Readiness Reviews
Recommendation
As part of their investigations, representatives of OGC undertaking an independent “readiness review” of a publicly funded project and representatives of any person, including representatives of any public body such as Audit Scotland, undertaking a review of the progress of …
Read more
Published evidence summary
- In November 2023, the Council stated it broadly agreed with Lord Hardie's recommendations, noting improvements in communication and reporting had been implemented for Trams to Newhaven (City of Edinburgh Council response, November 2023).
- The Council committee report (16 November 2023) stated that the Council agreed to support any future readiness review or audit to ensure clear understanding of progress and reporting (City of Edinburgh Council Committee Report, 16 November 2023).
- No published formal framework for mandatory progress reporting and escalation procedures in major publicly funded projects has been identified to March 2026.
- The Council committee report (16 November 2023) stated that the Council agreed to support any future readiness review or audit to ensure clear understanding of progress and reporting (City of Edinburgh Council Committee Report, 16 November 2023).
- No published formal framework for mandatory progress reporting and escalation procedures in major publicly funded projects has been identified to March 2026.
City of Edinburgh Council
(Primary)
View Details
Collaborative Delivery
Recommendation
At all stages of the project there should be a collaborative approach to delivering it. This should include the co-location of representatives from each organisation relevant to the particular stage reached and having an interest in its completion to enable …
Read more
Published evidence summary
- In November 2023, the Council stated it broadly agreed with Lord Hardie's recommendations, noting that co-location of representatives had been successfully adopted on the Trams to Newhaven project (City of Edinburgh Council response, November 2023).
- The Council committee report (16 November 2023) acknowledged that co-location had proven advantageous on the Newhaven project (City of Edinburgh Council Committee Report, 16 November 2023).
- No published formal requirement for collaborative co-location in future major infrastructure projects has been identified to March 2026.
- The Council committee report (16 November 2023) acknowledged that co-location had proven advantageous on the Newhaven project (City of Edinburgh Council Committee Report, 16 November 2023).
- No published formal requirement for collaborative co-location in future major infrastructure projects has been identified to March 2026.
City of Edinburgh Council
(Primary)
View Details
Prohibition on Misleading Reports from ALEOs
Recommendation
The directors, employees and consultants of the company responsible for the procurement and delivery of the project as project managers, including an arm’s-length external organisation (“ALEO”) wholly owned by the local authority that is the promoter and owner of the …
Read more
Published evidence summary
- In November 2023, the Council stated it broadly agreed with Lord Hardie's recommendations (City of Edinburgh Council response, November 2023).
- The Council committee report (16 November 2023) noted that scrutiny of arm's-length external organisations (ALEOs) had significantly improved since the original tram project, with reviews in 2012 and 2016 strengthening governance arrangements and the Council's relationship with its ALEOs (City of Edinburgh Council Committee Report, 16 November 2023).
- No published formal prohibition on ALEO directors or employees submitting public interest claims without the approval of senior officers of the parent local authority has been identified to March 2026.
- The Council committee report (16 November 2023) noted that scrutiny of arm's-length external organisations (ALEOs) had significantly improved since the original tram project, with reviews in 2012 and 2016 strengthening governance arrangements and the Council's relationship with its ALEOs (City of Edinburgh Council Committee Report, 16 November 2023).
- No published formal prohibition on ALEO directors or employees submitting public interest claims without the approval of senior officers of the parent local authority has been identified to March 2026.
City of Edinburgh Council
(Primary)
View Details
Duty of Officials to Councillors
Recommendation
Local authority officials should be mindful at all times of the distinction in roles between them and councillors, who are solely responsible for strategic decisions, and of their duty to provide accurate reports to councillors to enable them to take …
Read more
Published evidence summary
- In November 2023, the Council stated it broadly agreed with Lord Hardie's recommendations (City of Edinburgh Council response, November 2023).
- The Council committee report (16 November 2023) noted that the Council's Member/Officer Protocol highlights the distinction in roles between officials and councillors (City of Edinburgh Council Committee Report, 16 November 2023).
- No published updated guidance specifically requiring accurate reporting to councillors on major project progress has been identified to March 2026.
- The Council committee report (16 November 2023) noted that the Council's Member/Officer Protocol highlights the distinction in roles between officials and councillors (City of Edinburgh Council Committee Report, 16 November 2023).
- No published updated guidance specifically requiring accurate reporting to councillors on major project progress has been identified to March 2026.
City of Edinburgh Council
(Primary)
View Details
Civil Sanctions for Misleading Reports
Recommendation
Where a company, including an ALEO, knowingly submits a report or other information to local authority officials that is misleading by reason of the inclusion of false statements or the omission of relevant facts or where such officials knowingly submit …
Read more
Published evidence summary
- In November 2023, the Scottish Government stated it was "giving careful consideration" to the recommendations about civil damages provisions for misleading evidence, noting that existing remedies may already exist under delictual law (Transport Secretary Statement on Edinburgh Tram Inquiry Report, Scottish Government, 2 November 2023).
- No published decision on whether to introduce new civil liability provisions for knowingly submitting misleading reports or information has been identified to March 2026.
- No published decision on whether to introduce new civil liability provisions for knowingly submitting misleading reports or information has been identified to March 2026.
Scottish Government
(Primary)
View Details
Criminal Sanctions for Misleading Information
Recommendation
In addition to any civil liability arising from any sanction introduced in accordance with Recommendation 22, the Scottish Ministers should consider whether there is a need for a statutory criminal offence involving strict liability once it is established that the …
Read more
Published evidence summary
- In November 2023, the Scottish Government stated it was "giving careful consideration" to the recommendations about criminal statutory offences for misleading evidence, noting that existing remedies may already exist (Transport Secretary Statement on Edinburgh Tram Inquiry Report, Scottish Government, 2 November 2023).
- No published decision on whether to introduce a statutory criminal offence of strict liability for submitting misleading information or reports has been identified to March 2026.
- No published decision on whether to introduce a statutory criminal offence of strict liability for submitting misleading information or reports has been identified to March 2026.
Scottish Government
(Primary)
View Details
Duty of Disclosure Legislation
Recommendation
The Scottish Ministers should also give consideration to the need for legislation to impose a similar duty of disclosure to that owed by policyholders to their insurers upon a company, its directors, employees or consultants and upon a local authority …
Read more
Published evidence summary
- In November 2023, the Scottish Government stated it was "giving careful consideration" to the recommendations about provisions for misleading evidence (Transport Secretary Statement on Edinburgh Tram Inquiry Report, Scottish Government, 2 November 2023).
- No published decision on whether to introduce legislation imposing a duty of disclosure upon companies, directors, and local authority officials towards audit and review bodies has been identified to March 2026.
- No published decision on whether to introduce legislation imposing a duty of disclosure upon companies, directors, and local authority officials towards audit and review bodies has been identified to March 2026.
Scottish Government